BVY 13-107, Notification of Cancelled Regulatory Commitment

From kanterella
Jump to navigation Jump to search
Notification of Cancelled Regulatory Commitment
ML13350A108
Person / Time
Site: Vermont Yankee Entergy icon.png
Issue date: 12/10/2013
From: Wamser C
Entergy Nuclear Operations
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
BVY 13-107
Download: ML13350A108 (2)


Text

Entergy Nuclear Operations, Inc.

Vermont Yankee 320 Governor Hunt Rd Entergy Vernon, VT 05354 Tel 802 257 7711 Christopher J. Wamser Site Vice President BVY 13-107 December 10, 2013 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

SUBJECT:

Notification of Cancelled Regulatory Commitment Vermont Yankee Nuclear Power Station Docket No. 50-271 License No. DPR-28

REFERENCES:

1. Letter, VY to USNRC, "Update on Vermont Yankee Program Commitments Relative to Periodic Testing of Alternate AC Sources," BVY 08-043, dated August 14, 2008
2. Letter, USNRC to VY, "Issuance of Amendment to Renewed Facility Operating License Re: Change to Licensing Basis Regarding Station Blackout (TAC No. MF0422)," NVY 13-090, dated August 15, 2013

Dear Sir or Madam:

In Reference 1, Vermont Yankee Nuclear Power Station (VY) made a commitment related to the testing of the Alternate AC (AAC) power source from the Vernon Hydro Station (VHS), as it applied to compliance with 10 CFR 50.63 (Station Blackout Rule). Specifically, Reference 1 committed to the following:

"Performload test of the alternate AC source every third refueling outage" This commitment is being cancelled as the VHS tie line is no longer relied upon as the AAC power source credited for compliance with 10 CFR 50.63 at VY.

By License Amendment No. 258 (Reference 2) the NRC approved a change to the VY licensing basis which credits a new Station Blackout Diesel Generator as the AAC source for compliance with the Station Blackout Rule, replacing the VHS tie line. Amendment No. 258 documented new commitments for testing of the Station Blackout Diesel Generator in the associated Safety Evaluation.

This letter serves to update the docket relative to our cancellation of a prior commitment.

No NRC action is requested on this issue.

X()o(

0 CL, e-

BVY 13-107 / page 2 of 2 Should you have any questions or require additional information concerning this submittal, please contact Mr. Coley Chappell at (802) 451-3374.

Sincerely,

[CJW/JTM]

cc: Mr. William M. Dean, Regional Administrator U.S. Nuclear Regulatory Commission, Region 1 2100 Renaissance Blvd., Suite 100 King of Prussia, PA 19406-2713 Mr. Douglas Pickett, Project Manager Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop 08C2A Washington, DC 20555 USNRC Resident Inspector Vermont Yankee Mr. Christopher Recchia, Commissioner VT Department of Public Service 112 State Street - Drawer 20 Montpelier, Vermont 05620-2601