MONTHYEARBVY 24-026, Pre-Notice of Disbursement from Decommissioning Trust2024-10-0202 October 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-024, Pre-Notice of Disbursement from Decommissioning Trust2024-07-30030 July 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-023, Pre-Notice of Disbursement from Decommissioning Trust2024-07-0202 July 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-022, Pre-Notice of Disbursement from Decommissioning Trust2024-05-30030 May 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-020, Biennial Update of Quality Assurance Program Manual2024-05-22022 May 2024 Biennial Update of Quality Assurance Program Manual BVY 24-019, 2023 Radiological Environmental Operating Report2024-05-0909 May 2024 2023 Radiological Environmental Operating Report BVY 24-017, Pre-Notice of Disbursement from Decommissioning Trust2024-05-0606 May 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-018, 2023 Radiological Effluent Release Report2024-05-0505 May 2024 2023 Radiological Effluent Release Report BVY 24-016, 2023 Individual Monitoring NRC Form 5 Report2024-04-18018 April 2024 2023 Individual Monitoring NRC Form 5 Report BVY 24-014, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-04-0101 April 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-015, Pre-Notice of Disbursement from Decommissioning Trust2024-04-0101 April 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-012, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-03-14014 March 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-011, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-03-0606 March 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-010, Pre-Notice of Disbursement from Decommissioning Trust2024-03-0505 March 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-009, Withdrawal of License Amendment Request to Add License Condition 3.K, License Termination Plan; Proposed Change No. 3172024-02-27027 February 2024 Withdrawal of License Amendment Request to Add License Condition 3.K, License Termination Plan; Proposed Change No. 317 BVY 24-007, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-02-26026 February 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-008, ISFSI, Annual Radioactive Effluent Release Report2024-02-26026 February 2024 ISFSI, Annual Radioactive Effluent Release Report BVY 24-006, Pre-Notice of Disbursement from Decommissioning Trust2024-02-0606 February 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-005, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-01-30030 January 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-004, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-01-23023 January 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-003, Nuclear Onsite Property Damage Insurance2024-01-0404 January 2024 Nuclear Onsite Property Damage Insurance BVY 24-001, Pre-Notice of Disbursement from Decommissioning Trust2024-01-0202 January 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-030, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-12-20020 December 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-029, Proof of Financial Protection2023-12-12012 December 2023 Proof of Financial Protection BVY 23-028, Pre-Notice of Disbursement from Decommissioning Trust2023-11-28028 November 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-027, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-11-21021 November 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-026, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-11-13013 November 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-025, Pre-Notice of Disbursement from Decommissioning Trust2023-11-0202 November 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-023, License Amendment Request Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 3172023-10-10010 October 2023 License Amendment Request Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 317 BVY 23-022, Pre-Notice of Disbursement from Decommissioning Trust2023-08-23023 August 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-020, Pre-Notice of Disbursement from Decommissioning Trust2023-08-0202 August 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-021, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-08-0202 August 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-019, Update to 2022 Radiological Effluent Release Report2023-07-24024 July 2023 Update to 2022 Radiological Effluent Release Report BVY 23-018, Update to Nuclear Onsite Property Damage Insurance2023-07-12012 July 2023 Update to Nuclear Onsite Property Damage Insurance BVY 23-017, Pre-Notice of Disbursement from Decommissioning Trust2023-06-29029 June 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-016, 10 CFR 72.48 Report2023-06-0505 June 2023 10 CFR 72.48 Report BVY 23-015, Report of Investigation Pursuant to 1O CFR 20, Appendix G2023-06-0505 June 2023 Report of Investigation Pursuant to 1O CFR 20, Appendix G BVY 23-014, Pre-Notice of Disbursement from Decommissioning Trust2023-05-31031 May 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-013, 2022 Radiological Environmental Operating Report2023-05-10010 May 2023 2022 Radiological Environmental Operating Report BVY 23-011, 2022 Radiological Effluent Release Report2023-05-10010 May 2023 2022 Radiological Effluent Release Report BVY 23-012, Pre-Notice of Disbursement from Decommissioning Trust2023-05-0202 May 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-009, 2022 Individual Monitoring NRC Form 5 Report2023-04-24024 April 2023 2022 Individual Monitoring NRC Form 5 Report BVY 23-008, Pre-Notice of Disbursement from Decommissioning Trust2023-04-0606 April 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-006, Status of Decommissioning and Spent Fuel Management Fund for Year Ending 20222023-03-29029 March 2023 Status of Decommissioning and Spent Fuel Management Fund for Year Ending 2022 BVY 23-007, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-03-29029 March 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-005, Nuclear Onsite Property Damage Insurance2023-03-13013 March 2023 Nuclear Onsite Property Damage Insurance BVY 23-004, Pre-Notice of Disbursement from Decommissioning Trust2023-03-0202 March 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-003, Pre-Notice of Disbursement from Decommissioning Trust2023-01-31031 January 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 22-030, Documentary Evidence of Performance Bond2022-12-30030 December 2022 Documentary Evidence of Performance Bond BVY 22-028, Re Proof of Financial Protection2022-11-28028 November 2022 Re Proof of Financial Protection 2024-07-30
[Table view] |
Text
Entergy Nuclear Operations, Inc.
Vermont Yankee Vernon, VT 05354 Tel 802 257 7711 Christopher J. Wamser Site Vice President BVY 13-080 September 19, 2013 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
SUBJECT:
Updated Final Safety Analysis Report, Revision 26 Update Vermont Yankee Nuclear Power Station Docket No. 50-271 License No. DPR-28
REFERENCES:
- 1. Letter, VYNPS to USNRC, "Updated Final Safety Analysis Report, Revision 25 Update," BVY 12-026, dated April 24, 2012
- 2. NEI 98-03, Revision 1 "Guidelines for Updating Final Safety Analysis Reports," June 1999
Dear Sir or Madam:
Pursuant to 10 CFR 50.71(e) and 10 CFR 50.4(b)(6), enclosed is one CD-ROM containing Revision 26 of the Vermont Yankee (VY) Updated Final Safety Analysis Report (UFSAR) and the drawings that are incorporated by reference. The UFSAR file is divided into four (4) parts named 001 UFSARREV26-Part 1.pdf, 002 UFSARREV26-Part 2.pdf, 003 UFSARREV26-Part 3.pdf and 004 UFSARREV26-Part 4.pdf. Part 1 includes the List of Effective Pages and the UFSAR change matrix that details the specific changes made in Revision 26. The sections containing the changed pages since the previous update (Reference 1) are contained in the folder named Rev 26 Changed Sections. The drawings referenced in the UFSAR are included as individual files identified by the drawing number in the folder named UFSAR Drawings.This folder also includes a list of the drawings.
Additionally, pursuant to 10 CFR 50.71(e) and the guidance of NEI 98-03, Revision 1, enclosed is one CD-ROM containing the current revisions of the VY Technical Requirements Manual (TRM), the VY Fire Protection Program (FPP), the VY Fire Hazards Analysis (FHA) and the VY Safe Shutdown Capability Analysis (SSCA). The TRM, FPP, FHA and SSCA are incorporated by reference in the UFSAR. The TRM file is named 001 TRM.pdf, the FPP file is named 002 FPP.pdf,the FHA file is named 003 FHA.pdf and the SSCA file is divided into two (2) parts named 004 SSCA - Part 1.pdf and 005 SSCA - Part 2.pdf.
NRC holders of controlled-copy editions of the VY UFSAR will receive updates to those volumes with appropriate Change Package Instructions under separate cover.
There are no new regulatory commitments being made in this submittal.
Ac?05L
BVY 13-080 / Page 2 of 3 Should you have any questions concerning this submittal, please contact Mr. Coley Chappell at (802) 451-3374.
I declare under penalty of perjury that the foregoing is true and correct. Executed on September 19, 2013.
Sincerely,
[CJWpIc]
Enclosures:
- 1. CD-ROM, Updated Final Safety Analysis Report, Revision 26 and Referenced Plant Drawings List of Files and Folders:
001 UFSARREV26-Part 1.pdf 002 UFSARREV26-Part 2.pdf 003 UFSARREV26-Part 3.pdf 004 UFSARREV26-Part 4.pdf 005 Rev 26 UFSAR Change Matrix.pdf Rev 26 Changed Sections UFSAR Drawings
- 2. CD-ROM, UFSAR Documents Incorporated by Reference List of Files:
001 TRM.pdf 002 FPP.pdf 003 FHA.pdf 004 SSCA - Part l.pdf 005 SSCA - Part2.pdf
BVY 13-080 / Page 3 of 3 cc: Mr. William M. Dean, Regional Administrator U.S. Nuclear Regulatory Commission, Region 1 2100 Renaissance Blvd, Suite 100 King of Prussia, PA 19406-2713 Mr. Douglas V. Pickett, Project Manager Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop 08C2A Washington, DC 20555 USNRC Resident Inspector Entergy Nuclear Vermont Yankee 320 Governor Hunt Road Vernon, Vermont 05354 Mr. Christopher Recchia, Commissioner VT Department of Public Service 112 State Street - Drawer 20 Montpelier, Vermont 05620-2601