John S. Keenan cP&L Vice President A Progress Energy Company Brunswick Nuclear Plant AUG 2 8 2002 10 CFR 50.4 SERIAL: BSEP 02-0140 U. S. Nuclear Regulatory Commission ATrN: Document Control Desk Washington, DC 20555-0001 BRUNSWICK STEAM ELECTRIC PLANT, UNIT NOS. 1 AND 2 DOCKET NOS. 50-325 AND 50-324/LICENSE NOS. DPR-71 AND DPR-62 NOTIFICATION OF FULL COMPLIANCE WITH ORDER FOR INTERIM SAFEGUARDS AND SECURITY COMPENSATORY MEASURES Ladies and Gentlemen:
On February 25, 2002, the NRC issued a letter
Subject:
"Issuance of Order for Interim Safeguards and Secunty Compensatory Measures for - Brunswick Steam Electric Plant Units 1 & 2."Section III, C.1 of the order required Carolina Power & Light (CP&L)
Company, within 20 days, to submit to the NRC a schedule for achieving compliance with each requirement described in Attachment 2. The schedule for BSEP, Units 1 and 2, was enclosed in letter SERIAL: BSEP 02-0057, "Twenty-Day Response to Order for Interim Safeguards and Security Compensatory Measures for - Brunswick Steam Electnc Plant Units 1 & 2," dated March 15, 2002.
Section III, C.2 of the order requires that CP&L report to the NRC when full compliance with the requirements described in Attachment 2 has been achieved. CP&L hereby notifies the NRC that full compliance with the requirements described in Attachment 2 of the order has been achieved. No commitments are contained in this submittal. Please refer any questions regarding this submittal to Mr. Edward T. O'Neil, Manager - Regulatory Affairs, at (910) 457-3512.
Sincerely, 1?onS. Ke a CRE/cre PO Box 10429 Southport, NC 28461 T> 9104572496 F> 9104572803
N Document Control Desk BSEP 02-0140 / Page 2 John S. Keenan, having been first duly sworn, did depose and say that the information contained herein is true and correct to the best of his information, knowledge and belief; and the sources of his information are officers, employees, and agents of Carolina Power &
Light Company.
Notary (Seal)
My commission expires:
'J9
(* 4 cc:
U. S. Nuclear Regulatory Commission, Region II ATTN: Mr. Luis A. Reyes, Regional Administrator Sam Nunn Atlanta Federal Center 61 Forsyth Street, SW, Suite 23T85 Atlanta, GA 30303-8931 U. S. Nuclear Regulatory Commission ATTN: Mr. Theodore A. Easlick, NRC Senior Resident Inspector 8470 River Road Southport, NC 28461-8869 U. S. Nuclear Regulatory Commission ATTN: Ms. Brenda L. Mozafari (Mail Stop OWFN 8G9) (Electronic Copy Only) 11555 Rockville Pike Rockville, MD 20852-2738