Forwards Rev 0 to Brunswick Nuclear Plant,Three-Yr Plan. Plan Describes Certain Key Initiatives & Projects Already Begun or to Begin in Early 1993 & Sets Forth Schedule for Completing Tasks Re Intiatives
ML20035E614
Person / Time
Site: Brunswick  Duke Energy icon.png
Issue date: 12/15/1992
From: Morgan R
CAROLINA POWER & LIGHT CO.
To: Ebneter S
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML20035E615 List:
References
BSEP-92-0051, BSEP-92-51, NUDOCS 9304190036
Download: ML20035E614 (2)


Text

-

I F orm 244 z'

.;l%. : ' p g. e." ;r f*.,-9

-i comune p r a ught Company g

3 December 15,1992

_a Company Corresponcence a

mk SERIAL: BSEP-92-0051 3

FILE: B09-134510 b

3 j

Mr. Stewart D. Ebneter 2

Regional Adminictrator United States Nuclear Regulatory Commission 101 Marietta Street, N.W. Suite 2900 2

Atlanta, GA 30323

-i]

BRUNSWICK STEAM ELECI'RIC PLANT, " NIT NOS.1 AND 2 3

DOCKET NOS. 50-325 & 50-324/ LICENSE N,... DPR-71 & DPR-62 BRUNSWICK NUCLEAR PLANT '1HREE-YEAR PLAN (1993-1995) g i

Dear Mr.Ebneter:

3 This letter submits Carolina Power & Light Company's " Brunswick Nuclear Plant nree-Year Plan (1993-1995)" for the Brunswick Steam Electric Plant, Unit Nos. I and 2.

L Carolina Power & Light Company (CP&L) and the Brunswick Nuclear Plant (BNP) 3 teun have established goals and objectives for BNP chnretM=i by high d

management standards of performance, site and individual accountability, effective planning, continuous i

improvement, and people empowerment. De overall objective for the period 1993-1995 is j

to eenhlich the capability for BNP to achieve "world-class *results. That is,CP&L erp te BNP to perform among the top quartile of U.S. nuclear plants in 1996,1997,and beyond i

in the areas of safety, operations, and cost performance, and to sustain in that time period

_y significant improvement in the areas of employee <=tief=< tion and schedule and commitment a

achievement. ' Ibis is a comprehensive improvement plan for BNP, and it incorporates and 34 wg,. des outstanding items from the Inigf.ied Action Plan.

"l Re BNP management team has developed a vision for the plant and the plant organir=tinn

(

to be achieved over the next three years. Based on the projected expectations of the g

customers served by the plant, both internal and extern 21 to CP&L, the BNP team has i

identified the desired results rs" y to meet these ea:pectations. Achievement of the 3

results willrequire certain vip-hianni capabilities. Strategies and===arint~i projects and j

initiatives am being implemented to develop or enhance these capabilities. The goals, 4

vision, strategies, and==arintui initiatives and projects are described in the BNP nree-Year Plan, and are integrated with the CP&L Corporate Improvement Initiatives

[!

described in our November 30,1992 sabmittal.

5

@ " M N 2Nda 4 06 PDR i*I l

j

Mr. Stewart D. Ebneter BSEP-92-0051/ Page 2 The Three-Year Plan spMfim11y describes certain key initiatives and projects for BNP that either have already begun or will begm in early 1993 and sets fonh the schedule for completing tasks relating to these initiatives. Details of activities and schedules in the plan for 1994 and 1995 are not yet as complete and well defined as for 1993. In September 1993, l

after progress has been demnnetrataA, BNP will revise the Three-Year Plan to provide datailed task descriptions and updated schedules for 1994 and 1995. Further, BNP management willcloseJy monitor work under this plan to ensure that the plan is kept up to date and the effort remains focused on achieving the desired results. This will result in periodic changes to the plan, but such changes willbe carefully considered before they are made and will be made in accordance with the change puccss set fonh in the plan.

We willkeep you and your staff periodically informed on the status of plan initiatives and prajects and willdiscuss with you the ehlichment of trackmg milestones, procedures for attemng our progress in achieving desired results, and other aspects of the plan. We would like to meet with you and your staff at your convenience to discuss these matters.

Yours very truly, R. E. Morgan Intenm Site Ahnager Brunswick Nucicar Plant REM /wrm (920051.000)