MONTHYEARML20217E3021999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Pilgrim Nuclear Station.With ML20216E6881999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Pilgrim Nuclear Power Station.With ML20210R3401999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Pilgrim Nuclear Power Station.With ML20209E6191999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Pilgrim Nuclear Power Station.With ML20195G8231999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Pnps.With ML20206J6611999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Pilgrim Nuclear Power Station.With ML20205L0221999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Pilgrim Nuclear Power Station.With ML20207H5451999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Pilgrim Nuclear Power Station.With ML20206Q2741998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Pilgrim Nuclear Power Station.With ML20197J3591998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Pilgrim Nuclear Power Station.With ML20195C9951998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Pilgrim Nuclear Power Station.With ML20154K0721998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Pilgrim Nuclear Power Station.With ML20151W8231998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Pilgrim Nuclear Power Station.With ML20237A9941998-07-31031 July 1998 Monthly Operating Rept for Pilgrim Nuclear Power Station ML20236P0151998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Pilgrim Nuclear Power Station ML20249A3741998-05-31031 May 1998 Monthly Operating Rept for May 1998 for Pilgrim Nuclear Power Station.W/Undated Ltr ML20247H2081998-04-30030 April 1998 Monthly Operating Rept for Apr 1998 for Pilgrim Nuclear Power Station ML20216G3911998-03-31031 March 1998 Monthly Operating Rept for Mar 1998 for Pilgrim Nuclear Power Station ML20248L2241998-02-28028 February 1998 Monthly Operating Rept for Feb 1998 for Pilgrim Nuclear Station ML20202G5251998-01-31031 January 1998 Monthly Operating Rept for Jan 1998 for Pilgrim Nuclear Power Station ML20198L7701997-12-31031 December 1997 Monthly Operating Rept for Dec 1997 for Pilgrim Nuclear Power Station ML20203D6101997-11-30030 November 1997 Monthly Operating Rept for Nov 1997 for Pilgrim Nuclear Power Station BECO-LTR-97-111, Monthly Operating Rept for Oct 1997 for Pilgrim Nuclear Power Station1997-10-31031 October 1997 Monthly Operating Rept for Oct 1997 for Pilgrim Nuclear Power Station ML20217H5621997-09-30030 September 1997 Monthly Operating Rept for Sept 1997 for Pilgrim Nuclear Power Station ML20216J4131997-08-31031 August 1997 Monthly Operating Rept for Aug 1997 for Pilgrim Nuclear Power Station ML20210J3321997-07-31031 July 1997 Monthly Operating Rept for Jul 1997 for Pilgrim Nuclear Power Station ML20148K4161997-05-31031 May 1997 Monthly Operating Rept for Pilgrim Nuclear Power Station ML20141B9631997-04-30030 April 1997 Monthly Operating Rept for Apr 1997 for Pilgrim Nuclear Power Station ML20137T5631997-03-31031 March 1997 Monthly Operating Rept for Mar 1997 for Pilgrim Nuclear Power Station ML20136G7791997-02-28028 February 1997 Monthly Operating Rept for Feb 1997 for Pilgrim Nuclear Power Station ML20138K5811997-01-31031 January 1997 Monthly Operating Rept for Jan 1997 for Pilgrim Nuclear Power Station ML20133G5831996-12-31031 December 1996 Monthly Operating Rept for Dec 1996 for Pilgrim Nuclear Power Station BECO-96-106, Monthly Operating Rept for Nov 1996 for Pilgrim Nuclear Power Station1996-11-30030 November 1996 Monthly Operating Rept for Nov 1996 for Pilgrim Nuclear Power Station BECO-LTR-96-097, Monthly Operating Rept for Oct 1996 for Pilgrim Nuclear Power Station1996-10-31031 October 1996 Monthly Operating Rept for Oct 1996 for Pilgrim Nuclear Power Station ML20128N2611996-09-30030 September 1996 Monthly Operating Rept for Sept 1996 for Pilgrim Nuclear Power Station BECO-LTR-96-083, Monthly Operating Rept for Pilgrim Nuclear Power Station for Aug 1996 Ltr1996-08-31031 August 1996 Monthly Operating Rept for Pilgrim Nuclear Power Station for Aug 1996 Ltr ML20116L0841996-07-31031 July 1996 Monthly Operating Rept for Jul 1996 for Pilgrim Nuclear Power Station BECO-LTR-96-066, Monthly Operating Rept for June 1996 for Pilgrim Nuclear Power Station1996-06-30030 June 1996 Monthly Operating Rept for June 1996 for Pilgrim Nuclear Power Station BECO-LTR-96-056, Monthly Operating Rept for May 1996 for Pilgrim Nuclear Power Station1996-05-31031 May 1996 Monthly Operating Rept for May 1996 for Pilgrim Nuclear Power Station ML20117E0961996-04-30030 April 1996 Monthly Operating Rept for Apr 1996 for Pilgrim Nuclear Power Station BECO-LTR-96-034, Monthly Operating Rept for Mar 1996 for Pilgrim Nuclear Power Station1996-03-31031 March 1996 Monthly Operating Rept for Mar 1996 for Pilgrim Nuclear Power Station BECO-LTR-96-023, Monthly Operating Rept for Feb 1996 for Pilgrim Nuclear Power Station1996-02-29029 February 1996 Monthly Operating Rept for Feb 1996 for Pilgrim Nuclear Power Station BECO-LTR-96-008, Monthly Operating Rept for Jan 1996 for Pilgrim Nuclear Power Station1996-01-31031 January 1996 Monthly Operating Rept for Jan 1996 for Pilgrim Nuclear Power Station BECO-LTR-96-004, Monthly Operating Rept for Dec 1995 for Pilgrim Nuclear Power Station1995-12-31031 December 1995 Monthly Operating Rept for Dec 1995 for Pilgrim Nuclear Power Station ML20095E7351995-11-30030 November 1995 Monthly Operating Rept for Nov 1995 for Pilgrim Nuclear Power Station Unit 1 BECO-LTR-95-116, Monthly Operating Rept for Oct 1995 for Pilgrim Nuclear Power Station1995-10-31031 October 1995 Monthly Operating Rept for Oct 1995 for Pilgrim Nuclear Power Station ML20093F5221995-09-30030 September 1995 Monthly Operating Rept for Sept 1995 for Pilgrim Nuclear Power Station BECO-LTR-95-097, Monthly Operating Rept for Aug 1995 for Pilgrim Nuclear Power Station1995-08-31031 August 1995 Monthly Operating Rept for Aug 1995 for Pilgrim Nuclear Power Station BECO-LTR-95-081, Monthly Operating Rept for July 1995 for Pilgrim Nuclear Power Station1995-07-31031 July 1995 Monthly Operating Rept for July 1995 for Pilgrim Nuclear Power Station BECO-LTR-95-071, Monthly Operating Rept for June 1995 for Pilgrim Nuclear Power Plant1995-06-30030 June 1995 Monthly Operating Rept for June 1995 for Pilgrim Nuclear Power Plant 1999-09-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217E3021999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Pilgrim Nuclear Station.With ML20212C2921999-09-16016 September 1999 SER Accepting Licensee Request for Relief from ASME Code Section XI Requirements as Endorsed by 10CFR50.55a for Containment Insp for Pilgrim Nuclear Power Station ML20216F3511999-09-0808 September 1999 ISI Summary Rept for Refuel Outage 12 at Pnps ML20216E6881999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Pilgrim Nuclear Power Station.With ML20210R3401999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Pilgrim Nuclear Power Station.With ML20209C4731999-07-0707 July 1999 Addendum to SE on Proposed Transfer of Operating License & Matls License from Boston Edison Co to Entergy Nuclear Generation Co ML20209H8251999-07-0101 July 1999 Provides Commission with Evaluation of & Recommendations for Improvement in Processes Used in Staff Review & Approval of Applications for Transfer of Operating Licenses of TMI-1 & Pilgrim Station ML20209E6191999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Pilgrim Nuclear Power Station.With ML20196H2451999-06-29029 June 1999 SER Denying Licensee Proposed Alternative in Relief Request PRR-13,rev 2.Staff Determined That Proposed Alternative Provides Insufficient Info to Determine Adequacy of Scope of Implementation ML20209A8901999-06-28028 June 1999 SER Accepting Licensee Proposed Alternative to Use Code Case N-573 for Remainder of 10-year Interval Pursuant to 10CFR50.55a(a)(3)(i) ML20209B9861999-06-23023 June 1999 Rev 13A to Pilgrim Nuclear Power Station COLR for Cycle 13 ML20217N9061999-06-21021 June 1999 Rept of Changes,Tests & Experiments for Period of 970422-990621 ML20195K3431999-06-15015 June 1999 Safety Evaluation Granting Licensee Request to Use Guidance of GL 90-05 to Repair Flaws in ASME Class 3 Salt Svc Water System Piping for Plant ML20195G8231999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Pnps.With ML20207E7471999-05-27027 May 1999 Safety Evaluation Granting Request Re Reduction of IGSCC Insp of Category D Welds Due to Implementation of HWC to License DPR-35 ML20206M1971999-05-11011 May 1999 SER Accepting Request for Approval to Repair Flaws in ASME Code Class 3 Salt Svc Water Piping at Plant ML20206J6611999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Pilgrim Nuclear Power Station.With ML20205L0221999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Pilgrim Nuclear Power Station.With ML20207J5471999-03-0909 March 1999 Training Simulator,1999 4-Yr Certification Rept ML20207F9401999-03-0101 March 1999 Long Term Program Semi-Annual Rept for Pilgrim Nuclear Power Station ML20207H5451999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Pilgrim Nuclear Power Station.With ML20196E2151998-12-31031 December 1998 1998 Annual Rept for Boston Edison & Securities & Exchange Commission Form 10-K Rept.With ML20206Q2741998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Pilgrim Nuclear Power Station.With ML20197J3591998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Pilgrim Nuclear Power Station.With ML20195C9951998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Pilgrim Nuclear Power Station.With ML20154K0721998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Pilgrim Nuclear Power Station.With ML20153D3901998-09-22022 September 1998 Safety Evaluation Granting 970707 Request to Use Guidance in GL 90-05 to Repair Flaws in ASME Class 3 Salt Svc Water Sys Piping for Pilgrim Nuclear Power Station ML20197C5011998-09-0404 September 1998 Rev 12C,Pages 4 & 5 to Pilgrim Nuclear Power Station Colr ML20197C5471998-08-31031 August 1998 Rev 12C to Pilgrim Nuclear Power Station Colr ML20151W8231998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Pilgrim Nuclear Power Station.With ML20237E2251998-08-26026 August 1998 Suppl & Revs to SE for Amend 173 for Pigrim Nuclear Power Station ML20237A9941998-07-31031 July 1998 Monthly Operating Rept for Pilgrim Nuclear Power Station ML20236U8201998-07-13013 July 1998 Rev 12B to Pilgrim Nuclear Power Station COLR (Cycle 12) ML20236P0151998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Pilgrim Nuclear Power Station ML20249A3741998-05-31031 May 1998 Monthly Operating Rept for May 1998 for Pilgrim Nuclear Power Station.W/Undated Ltr ML20247H2081998-04-30030 April 1998 Monthly Operating Rept for Apr 1998 for Pilgrim Nuclear Power Station ML20207B7601998-03-31031 March 1998 Final Rept, Pilgrim Nuclear Power Station Site-Specific Offsite Radiological Emergency Preparedenss Prompt Alert & Notification System Quality Assurance Verification, Prepared for FEMA ML20216G3911998-03-31031 March 1998 Monthly Operating Rept for Mar 1998 for Pilgrim Nuclear Power Station ML20216J3741998-03-19019 March 1998 Safety Evaluation Accepting Licensee Request to Evaluate Elevated Tailpipe Temp on Safety Relief Valve SRV 203-3B ML20248L2241998-02-28028 February 1998 Monthly Operating Rept for Feb 1998 for Pilgrim Nuclear Station ML20202G5251998-01-31031 January 1998 Monthly Operating Rept for Jan 1998 for Pilgrim Nuclear Power Station ML20236M8511997-12-31031 December 1997 1997 Annual Rept for Boston Edison & Securities & Exchange Commission Form 10-K Rept ML20198L7701997-12-31031 December 1997 Monthly Operating Rept for Dec 1997 for Pilgrim Nuclear Power Station ML20203D6101997-11-30030 November 1997 Monthly Operating Rept for Nov 1997 for Pilgrim Nuclear Power Station ML20202D5761997-11-0808 November 1997 1997 Evaluated Exercise BECO-LTR-97-111, Monthly Operating Rept for Oct 1997 for Pilgrim Nuclear Power Station1997-10-31031 October 1997 Monthly Operating Rept for Oct 1997 for Pilgrim Nuclear Power Station ML20217D6431997-10-0101 October 1997 Safety Evaluation Granting Request for Approval to Repair Flaws in Accordance W/Gl 90-05 for ASME Class 3 SSW Piping for Pilgrim ML20217H5621997-09-30030 September 1997 Monthly Operating Rept for Sept 1997 for Pilgrim Nuclear Power Station ML20216J4131997-08-31031 August 1997 Monthly Operating Rept for Aug 1997 for Pilgrim Nuclear Power Station ML20210J3321997-07-31031 July 1997 Monthly Operating Rept for Jul 1997 for Pilgrim Nuclear Power Station 1999-09-08
[Table view] |
Text
. .
AVELAGE DAILY UNIT POWER LEVEL DOCKET NO. 50-293 UNIT Pilgrim 1 DATE 12/11/84 COMPLETED BY P. Hamilton TELEPHONE (617)746-7900 MONTH November 1984 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net) (MWe-Net) 1 0, 17 0.
2 0. _
18 0.
3 0. 19 0.
4 0. 20 0.
5 0. 21 0.
6 0. -
22 0.
7 0. 23 0.
8 0. 24 0.
9 0. 25 0.
10 0. 26 0.
11 0. 27 0.
12 0. 28 0.
13 0. 29 0.
14 0. 30 0.
15 0, 31 N/A 16 0.
INSTRUCTIONS On this format, list the average daily unit power level in MWe-Net for each day in the reporting month. Compute to the nearest whole megawatt.
8412210062 B41130 PDR ADOCK 05000293 .
R PDR \
R OPERATING DATA REPORT DOCKET NO. 50-293 DATE 12/11/84 COMPLETED BY P. Hamilton TELEPHONE (617)746-7900 OPERATING STATUS
- 1. Unit Name Pilerl<n 1 Notes
- 2. Reporting Period Novagber 1984
- 3. Licensed Thermal Power (MWt) 1993
- 4. Nameplate Rating (Gross MWe) 678
- 5. Design Electrical Rating (Net MWe)_ 655
- 6. Maximum Dependable Capacity (Gross MWe) 690
- 7. Maximum Dependable Capacity (Net MWe)___670
- 8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report, Give Reasons:
None
- 9. Power Level To Which Restricted, If Any (het MWe) None
- 10. Reasons For Restrictions, If Any N/A This Month Yr-to-Date Cumulative
- 11. Hours In Reporting Period 720.0 8040.0 105000.0
- 12. Number Of Hours Reactor Was Critical 0.0 0.0 69746.3
- 13. Reactor Reserve Shutdown Hours 0.0 0.0 0.0
- 14. Hours Generator On-Line 0.0 0.0 67534.0_
- 15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
- 16. Gross Thermal Energy Generated (MWH) 0.0 0.0 116932632.0
- 17. Gross Electrical Energy Generated (MWH) 0.0 0.0 _39228314.0
- v. Net Electrical Energy Generated (MWH) 0.0 0.0 37693409.0
- 19. Unit Service Factor 0.0 0.0 64.8
- 20. Unit Availability Factor 0.0 0.0 64t3
- 21. Unit Capacity Factor (Using MDC Net) 0.0 0.0 53.6
- 22. Unit Capacity Factor (Using DER Net) 0.0 0.0 54.8
- 23. Unit Forced Outage Rate 0.0 0.0 9.2 24 Sh;tdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):
Shutdown for refuelina and recirculation DiDe reDlacement - Outaae comenced on December 10. 1983.
- 25. If Shut Down At End Of Report Period Estimated Date of Startup Dec. 1984
- 26. Units In Test Status (Prior to Commercial Operation):
Forecast Achieved INITIAL CRITICALITY __
INITIAL ELECTRICITY COMMERCIAL OPERATION (9/77)
e l
UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-293 UNIT NAME Pilerim 1 DATE 12/11/84 COMPLETED BY P. Hamilton TELEPHONE (617) 746-7900 REPORT MONTH Novembe. 1984 METHOD OF LICENSE CAUSE & CORRECTIVE DURATION SHUTTING EVENT SYSTEN COMPONENT ACTION TO NO. DATE TYPEI (HOURS) REASON 2 DOWN REACTOR 3 REPORT # CODE 4 CODES PREVENT RECURRENCE l
~
16 83/12/10 S 720.0 C 1 N/A N/A N/A N/A - Shutdown for refueling and recirculation pipe replacement.
i l
i 1 2 2 3 4&5 F-Forced A-Equip Failure F-Admin 1-Manual Exhibit F & H S-Sched 8-Maint or Test G-Oper Error 2-Manual Scram Instructions for C-Refueling H-Other 3-Auto Scram Preparation of D-Regulatory Restriction 4-Continued Data Entry Sheet "
E-Operator Training 5-Reduced Load Licensee Event Report ,
& License Examination 9-Other (LER) File (NUREG-1022)
-- 9 -. - n< .a
REFUELING INFORMATION The following refueling information is included in the Monthly Report as i requested in an NRC letter to BECo, dated January 18, 1978:
l For your convenience, the information supplied has been enumerated so that each number corresponds to equivalent notation utilized in the request.
i 1. The name of this facility is Pilgrim Nuclear Power Station, Docket Number 50-293.
- 2. Scheduled date for next Refueling Shutdown: August 1986 l 3. Scheduled date for restart following refueling: December 1984 j 4.
l S. Due to their similarity, requests 4, 5, & 6 are responded to collectively:
- 6. The new fuel, which is being loaded this refueling outage, is of the same i P8x8R design, as loaded the previous outage and consists of 160 P8DR8282 j assemblies and 32 GE6B-P8DR8282 assemblies.
i
- 7. (a) There are 580 fuel assemblies in the core.
, (b) There are 1,128 fuel assemblies in the spent fuel pool.
1 i 8. (a) The station is presently licensed to store 2320 spent fuel assemblies. The actual spent fuel storage capacity is 1770 fuel i assemblies at present.
I (b) The planned spent fuel storage capacity is 2320 fuel assemblies.
f 9. With present spent fuel in storage, the spent fuel pool now has the j capacity to accommodate an additional 642 fuel assemblies.
i 1
}
i t
4
- , , . , , - , , - - - ,,n.,.n,---- g.nn-w ,--,_,,..m., ,e., - - --,n-----,-... - - - , ,a,-e.---.--,n, n -n-,-,,.
l l
Month November 1984 PILGRIM NUCLEAR POWER STATION MAJOR' SAFETY RELATED MAINTENANCE ,
i CORRECTIVE ACTION i SYSTEM COMPONENT MALFUNCTION CAUSE MAINTENANCE TO PREVENT ASSOCIATED l RECURRENCE LER I
i HVAC Fire Missing Installation Install Isolated Update LER Damper Oversight Incident 84-007 (To be issued.)
l Cont. Valve Failed Packing Repacked N/A Update LER
( Atmos. A0-5033B App. "J" LLRT Leak Valve 83-065 (To be
! Control issued.)
l l
l l
L i
l i
.. 1 1
BOSTON EDISON COMPANY PILGRIM NUCLEAR POWER STATION DOCKET NO. 50-293 Operational Summarv for November 1984 The Unit has been shut down all month for Refuel Outage #6. Refuel operations were completed on 11/14/84. The reactor vessel hydro commenced on 11/30/84.
.All outage work continued.
Safety Relief Valve challenges Month of November 1984 Requirement: NUREG-0737 T.A.P. II.K.3.3 Reason: No safety / relief valve challenges occurred during the month of November 1984. Refuel Outage #6 is in progress.
e . ..
BOSTON EDISON COMPANY I 500 SOVLaTON STREET SOsTON, M AusACHUBETTS O2199 ,
l WILLIAM D. HARRINGTON 5~.$1.""'~~*~~ December 11, 1984 BECo Ltr. #84- 208 Director Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Washington, D.C. 20555 Attn: Document Control Desk License No. DPk-35 Docket No. 50-293
Subject:
November 1984 Nonthly Report
Dear Sir:
In accordance with PNPS Technical Specification 6.9. A.2, a copy of the Operational Status Summary for Pilgrim Nuclear Power Station is attached for your information and planning.
Respectfully submitted, W. D. Harrington
- caw Attachment -
cc: Regional Administrator, Region I U.S. Nuclear Regulatory Commission 631 Park Avenue King of Prussia, PA 19406 U.S. Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555
>