MONTHYEARAEP-NRC-2024-77, U2C28 Steam Generator Tube Inspection Report2024-10-21021 October 2024 U2C28 Steam Generator Tube Inspection Report AEP-NRC-2024-80, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Cask2024-10-15015 October 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-79, Unit 2, Independent Spent Fuel Storage Installation - Registration of Dry Spent Storage Cask2024-09-26026 September 2024 Unit 2, Independent Spent Fuel Storage Installation - Registration of Dry Spent Storage Cask AEP-NRC-2024-78, Reply to a Notice of Violation: EA-24-0472024-09-23023 September 2024 Reply to a Notice of Violation: EA-24-047 AEP-NRC-2024-69, Core Operating Limits Report2024-09-0909 September 2024 Core Operating Limits Report AEP-NRC-2024-76, Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-08-28028 August 2024 Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-51, Annual Report of Loss-Of-Coolant Accident Evaluation Model Changes2024-08-28028 August 2024 Annual Report of Loss-Of-Coolant Accident Evaluation Model Changes AEP-NRC-2024-61, Unit 2 - Response to Request for Additional Information for Neutron Flux Instrumentation License Amendment Request2024-08-15015 August 2024 Unit 2 - Response to Request for Additional Information for Neutron Flux Instrumentation License Amendment Request AEP-NRC-2024-62, Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask2024-08-0707 August 2024 Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-47, Form OAR-1, Owners Activity Report2024-07-30030 July 2024 Form OAR-1, Owners Activity Report AEP-NRC-2024-56, Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask2024-07-0808 July 2024 Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-48, Response to Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-07-0202 July 2024 Response to Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-45, Report Per Technical Specification 5.6.6 for Inoperability of Post Accident Monitoring Neutron Flux Monitoring2024-06-13013 June 2024 Report Per Technical Specification 5.6.6 for Inoperability of Post Accident Monitoring Neutron Flux Monitoring AEP-NRC-2024-23, Core Operating Limits Report2024-05-23023 May 2024 Core Operating Limits Report AEP-NRC-2024-40, Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-05-16016 May 2024 Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-41, Annual Radiological Environmental Operating Report2024-05-15015 May 2024 Annual Radiological Environmental Operating Report AEP-NRC-2024-26, Transmittal of Donald C. Cook Nuclear Plant, Emergency Plan Revision 492024-05-14014 May 2024 Transmittal of Donald C. Cook Nuclear Plant, Emergency Plan Revision 49 AEP-NRC-2024-07, Unit 2 - Transmittal of Report of Changes to the Emergency Plan2024-05-14014 May 2024 Unit 2 - Transmittal of Report of Changes to the Emergency Plan AEP-NRC-2024-24, Form OAR-1, Owners Activity Report2024-05-0707 May 2024 Form OAR-1, Owners Activity Report AEP-NRC-2024-35, Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations2024-04-30030 April 2024 Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations AEP-NRC-2024-28, 2023 Annual Radioactive Effluent Release Report2024-04-29029 April 2024 2023 Annual Radioactive Effluent Release Report AEP-NRC-2024-31, Annual Report of Individual Monitoring2024-04-24024 April 2024 Annual Report of Individual Monitoring AEP-NRC-2024-29, (CNP) Unit 2 - Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-072024-04-0303 April 2024 (CNP) Unit 2 - Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-07 AEP-NRC-2024-02, Unit 2 License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-04-0303 April 2024 Unit 2 License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-19, Annual Report of Property Insurance2024-04-0101 April 2024 Annual Report of Property Insurance AEP-NRC-2024-04, License Amendment Request Regarding a Change to Unit 1 Technical Specification 3.4.12, Low Temperature Overpressure Protection (LTOP) System2024-03-0606 March 2024 License Amendment Request Regarding a Change to Unit 1 Technical Specification 3.4.12, Low Temperature Overpressure Protection (LTOP) System AEP-NRC-2024-11, Unit 2 - Response to Request for Additional Information on Requested Change Regarding Neutron Flux Instrumentation2024-02-27027 February 2024 Unit 2 - Response to Request for Additional Information on Requested Change Regarding Neutron Flux Instrumentation AEP-NRC-2024-10, Form OAR-1, Owners Activity Report2024-02-0707 February 2024 Form OAR-1, Owners Activity Report AEP-NRC-2024-01, Emergency Plan Revision 482024-01-0808 January 2024 Emergency Plan Revision 48 AEP-NRC-2023-56, Report Per Technical Specification 5.6.6 for Inoperability of Unit 1 Post Accident Monitoring Reactor Coolant (Loop 3 Cold Leg) Wide Range Temperature Recorder Thermal Sensor2023-12-20020 December 2023 Report Per Technical Specification 5.6.6 for Inoperability of Unit 1 Post Accident Monitoring Reactor Coolant (Loop 3 Cold Leg) Wide Range Temperature Recorder Thermal Sensor AEP-NRC-2023-45, Unit 2 - Schedular Exemption for Enhanced Weapons, Firearms, Background Checks, and Security Event Notifications Implementation2023-11-16016 November 2023 Unit 2 - Schedular Exemption for Enhanced Weapons, Firearms, Background Checks, and Security Event Notifications Implementation AEP-NRC-2023-40, Annual Report of Loss-of-Coolant Accident Evaluation Model Changes2023-08-29029 August 2023 Annual Report of Loss-of-Coolant Accident Evaluation Model Changes AEP-NRC-2023-34, Supplement to Request for Approval of Change Regarding Neutron Flux Instrumentation2023-08-0202 August 2023 Supplement to Request for Approval of Change Regarding Neutron Flux Instrumentation AEP-NRC-2023-29, Core Operating Limits Report2023-06-19019 June 2023 Core Operating Limits Report AEP-NRC-2023-32, Response to NRC Regulatory Issue Summary 2023-1 Preparation and Scheduling of Operator Licensing Examinations2023-06-0606 June 2023 Response to NRC Regulatory Issue Summary 2023-1 Preparation and Scheduling of Operator Licensing Examinations AEP-NRC-2023-33, Renewable Operating Permit2023-06-0505 June 2023 Renewable Operating Permit AEP-NRC-2023-30, Follow-Up Notification of Ph Non-Compliance for Turbine Room Sump2023-06-0101 June 2023 Follow-Up Notification of Ph Non-Compliance for Turbine Room Sump AEP-NRC-2023-27, Annual Radiological Environmental Operating Report2023-05-15015 May 2023 Annual Radiological Environmental Operating Report AEP-NRC-2023-19, Annual Radioactive Effluent Release Report2023-04-30030 April 2023 Annual Radioactive Effluent Release Report AEP-NRC-2023-23, Annual Report of Individual Monitoring for 20222023-04-24024 April 2023 Annual Report of Individual Monitoring for 2022 AEP-NRC-2023-24, Notification of Ph Non-Compliance for Turbine Room Sump2023-04-12012 April 2023 Notification of Ph Non-Compliance for Turbine Room Sump AEP-NRC-2023-20, Annual Report of Property Insurance2023-04-0303 April 2023 Annual Report of Property Insurance AEP-NRC-2023-15, Decommissioning Funding Status Report2023-03-28028 March 2023 Decommissioning Funding Status Report AEP-NRC-2023-11, Form OAR-1, Owners Activity Report2023-01-31031 January 2023 Form OAR-1, Owners Activity Report AEP-NRC-2023-02, Request for Approval of Change Regarding Neutron Flux Instrumentation2023-01-26026 January 2023 Request for Approval of Change Regarding Neutron Flux Instrumentation AEP-NRC-2022-66, Report Per Technical Specification 5.6.6 for Inoperability of Unit 2 Post Accident Monitoring Neutron Flux Monitoring2022-12-15015 December 2022 Report Per Technical Specification 5.6.6 for Inoperability of Unit 2 Post Accident Monitoring Neutron Flux Monitoring AEP-NRC-2022-46, Notification of Deviation from Electric Power Research Institute (EPRI) Materials Reliability Program 2019-008, Interim Guidance for NEI 03-08 Needed Requirements for Us PWR Plants for Management of Thermal Fatigue in2022-12-12012 December 2022 Notification of Deviation from Electric Power Research Institute (EPRI) Materials Reliability Program 2019-008, Interim Guidance for NEI 03-08 Needed Requirements for Us PWR Plants for Management of Thermal Fatigue in AEP-NRC-2022-58, U1C31 Steam Generator Tube Inspection Report2022-10-24024 October 2022 U1C31 Steam Generator Tube Inspection Report AEP-NRC-2022-61, Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-062022-10-24024 October 2022 Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-06 AEP-NRC-2022-56, Unit 2 - Transmittal of Report of Changes to the Emergency Plan2022-10-12012 October 2022 Unit 2 - Transmittal of Report of Changes to the Emergency Plan 2024-09-09
[Table view] |
Text
NNDIANA MICHIGAN Indiana Michigan Power B101 WE One Cook Place Bridgman, Ml 49106 A unit ofAmerican Electric Power Indiana Michigan Power. com
'March 12, 2010 AEP-NRC-2010-21 10 CFR 50.55a U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001
Subject:
, Donald C. Cook Nuclear Plant Units 1 and 2 Docket No. 50-315 and 50-316 Fourth Ten-Year Interval Inservice Inspection Program Plan
References:
- 1. Letter from L. Raghavan, U. S. Nuclear Regulatory Commission (NRC), to M. K. Nazar, Indiana Michigan Power Company (I&M), "Donald C. Cook Nuclear Plant, Units 1 and 2 (DCCNP-1 and DCCNP-2) - Relief Request ISIR-19 Regarding Class 1 and 2 Piping Weld Inspection Requirements (TAC Nos.
MC8569 and MC8570)," dated May 31, 2006 (ML060820513).
- 2. Letter from P. S. Tam, NRC, to M. K. Nazar, I&M, "Donald C. Cook Nuclear Plant, Unit 1 and 2 - Correction of Safety Evaluation RE. Relief Request ISIR-19 Regarding Class 1 and 2 Piping Weld Inspection Requirements (TAC Nos.
MC8569 and MC8570)," dated December 29, 2006 (ML063420033).
- 3. Letter from L. M. James, NRC, to J. N. Jensen, I&M, "Donald C. Cook Nuclear Plant, Unit 1 and 2 - Relief Requests (ISIR-23, ISIR-24 and ISIR-25) for Inservice Pressure Testing Program (TAC Nos. MD9438 and MD9439)," dated February 18, 2009 (ML090330065).
Dear Sir or Madam:
In accordance with the American Society of Mechanical Engineers Boiler and Pressure Vessel Code,Section XI, Paragraph IWA-1400(c), Indiana Michigan Power Company (I&M) is enclosing an approved copy of the Donald C. Cook Nuclear Plant (CNP) Units 1 and 2 Inservice Inspection (ISI)
Program Plan for the Fourth Ten-Year Interval. The fourth ten-year interval commences on March 1, 2010, and concludes on February 29, 2020. A description of the program is included in the enclosure.
References 1, 2, and 3 approved relief requests for the CNP third ten-year ISI interval. I&M is requesting NRC review and approval of this same set of relief requests for the fourth ten-year interval. Section 5.0, Relief Requests, of the enclosure, ISI Program Plan Fourth Ten-Year Inspection Interval, provides a detailed description of the relief requests. I&M is providing the ISI Program Plan Fourth Ten-Year Interval for information only. I&M is not requesting NRC approval of the program plan.
U. S. Nuclear Regulatory Commission AEP-NRC-2010-21 Page 2 NRC review and approval of the relief requests in Section 5.0 of the ISI Program Plan Fourth Ten-Year Interval is requested by September 1, 2010, for application during the CNP Unit 2 Cycle 19 refueling outage.
There are no new or revised commitments in this letter. Should you have any questions, please contact Mr. James M. Petro, Jr., Regulatory Affairs Manager, at (269) 466-2489.
Sincerely, Raymond A. Hruby, Jr.
Vice President - Site Support Services RSP/rdw
Enclosure:
Donald C. Cook Nuclear Plant Units 1 & 2 ISI Program Plan Fourth Ten-Year Inspection Interval c: T. A. Beltz - NRC Washington, DC J. T. King - MPSC S. M. Krawec, Ft. Wayne AEP, w/o enclosure MDNRE - WHMD/RPS NRC Resident Inspector M. A. Satorius - NRC Region III