3F1103-01, October 2003 Monthly Operating Report for Crystal River Unit 3
| ML033240068 | |
| Person / Time | |
|---|---|
| Site: | Crystal River |
| Issue date: | 11/11/2003 |
| From: | Franke J Progress Energy Florida |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| 3F1103-01 | |
| Download: ML033240068 (3) | |
Text
Progress Energy Docket No. 50-302 Operating License No. DPR-72 Ref: ITS 5.7.1.2 November 11, 2003 3F1 103-01 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001
Subject:
Crystal River Unit 3 - Monthly Operating Report
Dear Sir:
Progress Energy Florida, Inc. hereby submits the Crystal River Unit 3 (CR-3) October 2003 Monthly Operating Report in accordance with CR-3 Improved Technical Specification 5.7.1.2.
If you have any questions regarding this submittal, please contact Mr. Sid Powell, Supervisor, Licensing and Regulatory Programs at (352) 563-4883.
Sincerely, A. Franke Plant General Manager JAF/ff Attachment xc:
Regional Administrator, Region II Senior Resident Inspector NRR Project Manager Progress Energy Florida, Inc.
Crystal River Nuclear Plant 15760 W. Powerline Sireet Crystal River, FL 34428
Lt.
APPENDIX A OPERATING DATA REPORT DOCKET NO. 50-302 UNi NAME FLCRP-3 DATE November 3, 200$
COMPLETEDBY J.E.Lane l
Xt TELEPHONE (352) 795-6486 x3698 REPORTING PERIOD (MonthfYear):
October 2003 MONTH YEAR TO DATE CUMULATIVE I
DESIGN ELECTRICAL RATING (MWe-Net) 860 2
MAXIMUM DEPENDABLE CAPACITY (Mwe-Net) 834 3
NUMBER OF HOURS REACTOR WAS CRITICAL 73.5 6,624.5 164,739 4
NUMBER OF HOURS THE GENERATOR WAS ON LINE 72.0 6,623.0 162,438 5
UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 0
6 NET ELECTRICAL ENERGY GENERATED (MWH) 44,698 5,505,200 126,774,771
If APPENDIX B UNIT SHUTDOWNS DOCKET NO. 50-302 UNIT NAME FLCRP-3 DATE November 3, 2003 COMPLETED BY J. E. Lane TELEPHONE (352) 795-6486 x3698 REPORTING PERIOD:
October2003 No.
Date Type Duration Reason Method of Cause / Corrective Actions F: Forced (Hours)
(1)
Shutting S: Scheduled Down (2)
Comments 03-01 I014/2003 S
672.98 C
I Shutdown for Refuel Outage 13.
SUMMARY
Crystal River Unit 3 shutdown on 10/4/03 to start Refuel Outage 13. The unit is expected to return to service in the early part of November.
(1) Reason:
A-EQUIPMENT FAILURE (Explain)
B-MAINTENANCE OR TEST C-REFUELING D-REGULATORY RESTRICTION E-OPERATOR TRAINING / LICENSE EXAMINATION F-ADMINISTRATIVE G-OPERATIONAL ERROR (Exptain)
H-OTHER (Explatn)
(2) Method I-MANUAL 2-MANUAL TRIP I SCRAM 3-AUTO TRIP I SCRAM 4-CONTINUATION 5-OTHER (Explain)