3F0802-02, July 2002 Monthly Operating Report for Crystal River Unit 3
| ML022270642 | |
| Person / Time | |
|---|---|
| Site: | Crystal River |
| Issue date: | 08/08/2002 |
| From: | Franke J Florida Power & Light Co |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| 3F0802-02 | |
| Download: ML022270642 (3) | |
Text
j Florida Power Progress Energy Crystal River Nuclear Plant Docket No. 50-302 Operating License No. DPR-72 Ref: ITS 5.7.1.2 August 8, 2002 3F0802-02 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001
Subject:
Crystal River Unit 3 - Monthly Operating Report
Dear Sir:
Florida Power Corporation hereby submits the Crystal River Unit 3 (CR-3) July 2002 Monthly Operating Report in accordance with CR-3 Improved Technical Specification 5.7.1.2.
If you have any questions regarding this submittal, please contact Mr. Sid Powell, Supervisor, Licensing and Regulatory Programs at (352) 563-4883.
Sincerely, J. A. Franke Plant General Manager JAF/ff Attachment xc:
Regional Administrator, Region II Senior Resident Inspector NRR Project Manager
- ,,:-,~-
- w.
- ,,, ' "/
t jt
APPENDIX A OPERATING DATA REPORT DOCKET NO.
UNIT NAME DATE COMPLETED BY TELEPHONE REPORTING PERIOD (Month/Year):
50-302 FLCRP-3 August 1, 2002 J. E. Lane Q
(352) 7 9 5-6 4h6 x3698 July 2002 MONTH YEAR TO DATE DESIGN ELECTRICAL RATING (MWe-Net)
MAXIMUM DEPENDABLE CAPACITY (Mwe-Net)
NUMBER OF HOURS REACTOR WAS CRITICAL NUMBER OF HOURS THE GENERATOR WAS ON LINE UNIT RESERVE SHUTDOWN HOURS NET ELECTRICAL ENERGY GENERATED (MWH) 1 2
3 4
5 6
825 834 CUMULATIVE 744.0 744.0 0.0 622,390 5,068.0 5,060.4 0.0 4,264,951 154,475 152,183 0
118,234,214
APPENDIX B UNIT SHUTDOWNS DOCKET NO. 50-302 UNIT NAME FLCRP-3 DATE August 1, 2002 COMPLETED BY J. E. Lane TELEPHONE (352) 795-6486 x3698 REPORTING PERIOD:
July 2002 No.
Date Type Duration Reason Method of Cause / Corrective Actions F: Forced (Hours)
(1)
Shutting S: Scheduled Down (2)
Comments None
SUMMARY
Crystal River Unit 3 operated at full power for the entire month.
(1) Reason:
A-EQUIPMENT FAILURE (Explain)
B-MAINTENANCE OR TEST C-REFUELING D-REGULATORY RESTRICTION
&-OPERATOR TRAINING / LICENSE EXAMINATION F-ADMINISTRATIVE G-OPERATIONAL ERROR (Explain)
H-OTHER (Explain)
(2) Method I-MANUAL 2-MANUAL TRIP / SCRAM 3-AUTO TRIP / SCRAM 4-CONTINUATION S-OTHER (Explain)