3F0498-25, Notifies NRC That Util Extending Commitment Date from 980502 to 28 Re Operational Assessment for First Span pit-like Attack

From kanterella
(Redirected from 3F0498-25)
Jump to navigation Jump to search
Notifies NRC That Util Extending Commitment Date from 980502 to 28 Re Operational Assessment for First Span pit-like Attack
ML20217F978
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 04/22/1998
From: Baumstark J
FLORIDA POWER CORP.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
3F0498-25, 3F498-25, NUDOCS 9804290002
Download: ML20217F978 (2)


Text

Fisrida $('

Power f, sTEJA" V

Ope,ating Lice se No. DPR-72 April 22,1998 3F0498-25 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001

Subject:

Commitment Due Date Extension

References:

1. FPC to NRC Letter,3F1097-21, dated October 1,1997
2. FPC to NRC Letter,3F1297-22, dated December 5,1997

Dear Sir:

The purpose of this letter is to notify the NRC that Florida Power Corporation (FPC) is extending a commitment due date. In References 1 and 2, FPC discussed the "B" Once -

Through Steam Generator (OTSG) Tube Surveillance Program. FPC made a commitment to submit an operational assessment for the first span pit-like intergranular attack (IGA), within 90 days following plant restart. Crystal River Unit 3 (CR-3) restarted on February 2,1998, therefore, the operational assessment is required to be submitted by May 2,1998. Technical reviews necessary for the assessment are currently in progress, but will not be completed in time to support the May 2,1998 submittal date.

Therefore, FPC is extending the commitment date to May 28,1998.

If you have any questions regarding this submittal, please contact Ms. Sherry Bernhoft, Manager, Nuclear Licenshg, at (352) 563-4566.

Sincerely, ,

J. S. aumstark Director Nuclear Engineering and Projects JSB/pmp Enclosure xc: Regional Administrator, Region ll Senior Resident inspector NRR Project Manager ,))

,, \\

9804290002 980422 PDR ADOCK 05000302 \

P PDR 0 CRYSTAL RIVER ENERGY COMPLEX: 15760 W. Power Line street

  • Crystal River, Florida 344284708 * (352)7954486 N

A Florida Progress Company

___m

. U. S. Nuclear Regulatory Commission 3F0498-25 Page 2 of 2 ENCLOSURE A COMMITMENTS The following identifies those actions committed to by Florida Power Corporation (FPC) in this document. Any other actions discussed represent intended or planned actions by FPC and are described to the NRC Staff for their information and are not regulatory commitments. This commitment is the same commitment made in Special Report 97-05.

COMMITMENT COMMITMENT DUE DATE NUMBER 3F1297-22 FPC will submit an operational assessment May 28,1998 for the first span pit-like intergranular attack l (IGA), within 90 days following plant restart. )

{

l i

i