e Fisrida Power fJ RAJLoN o,.E"s*uM w.. opa-n April 16,1998 3F0498-04 U.S. Nuclear Regulatory Commission Attn: Document Control Desk
)
Washington, DC 20555-0001 j
Subject:
SIXTH CONTAINMENT TENDON SURVEILLANCE
SUMMARY
References:
Dear Sir:
Florida Power Corporation (FPC) is hereby submitting the Crystal River Unit 3 (CR-3) Sixth Containment Tendon Surveillance summary report.
The tendon surveillance was conducted between October 20,1997, and January 16, 1998, in accordance with ASME,Section XI,1992 Edition.
FPC previously submitted three Special Reports identifying nonconforming conditions which were identified during the surveillence. This summary report provides the engineering evaluation of those nonconformances. There are no new regulatory commitments made in this submittal.
If you have any questions conceming this s:.bmittal, please contact Ms. Sherry Bernhoft, Manager, Nuclear Licensing at (352) 563-4566.
Sincerely, d
/
r J. S.
aumstark Director Nuclear Engineering and Projects e
\\;
JSB/pmp
.( d Enclosure xc:
Regional Administrator, Region 11 Senior Resident inspector NRR Project Manager 9804220433 980416 PDR ADOCK 05000302 PDR CRYSTAL RIVER ENERGY COMPLEX: 16760 W. Power Line Street