Progress Energy Crystal River Nuclear Plant Docket No. 50-302 Operating license No. DPR-72 Ref: ITS 5.7.1.2 April 7, 2004 3F0404-01 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001
Subject:
Crystal River Unit 3 - March 2004 Monthly Operating Report
Dear Sir:
Florida Power Corporation, doing business as Progress Energy Florida, Inc., hereby submits the Crystal River Unit 3 (CR-3) March 2004 Monthly Operating Report in accordance with CR-3 Improved Technical Specification 5.7.1.2.
If you have any questions regarding this submittal, please contact Mr. Sid Powell, Supervisor, Licensing and Regulatory Programs at (352) 563-4883.
Si J A. Franke lant General Manager JAF/ff Attachment xc:
Regional Administrator, Region II Senior Resident Inspector NRR Project Manager Progress Energy Florida, Inc.
Crystal River Nuclear Plant 15760 W. Power Line Street Crystal River, FL 34428
I APPENDIX A OPERATING DATA REPORT DOCKET NO.
50-302 UNlTNAME FLCRP-3 DATE April 1, 2004 COMPLETED BY J. E. Lane X Y9"'
TELEPHONE (352) 795-6486 x3698 REPORTING PERIOD (MonthlYear):
March 2004 MONTH YEAR TO DATE CUMULATIVE 1
DESIGN ELECTRICAL RATING (MWe-Net) 2 MAXIMUM DEPENDABLE CAPACITY (Mwe-Net) 3 NUMBER OF HOURS REACTOR WAS CRITICAL 4
NUMBER OF HOURS THE GENERATOR WAS ON LINE 5
UNIT RESERVE SHUTDOWN HOURS 6
NET ELECTRICAL ENERGY GENERATED (MWH) 860 838 694.2 672.3 0.0 563,406 2,134.2 2,112.3 0.0 1,806,278 168205.5 165839.9 0.0 129,655,279
APPENDIX B UNIT SHUTDOWNS DOCKET NO.
50-302 UNITNAME FLCRP-3 DATE April 1, 2004 COMPLETED BY J. E Lane TELEPHONE (352) 795-6486 x3698 REPORTING PERIOD:
March 2004 No.
Date Type Duration Reason Method of Cause / Corrective Actions F: Forced (Hours)
(1)
Shutting S: Scheduled Down (2)
Comments 2004-01 03/03/04 S
36.53 B
I Planned shutdown to repair a reactor coolant pump motor oil leak.
2004-02 03/24/04 F
35.13 A
3 Reactor trip due to an electronic card failure in the Integrated Control System.
SUMMARY
Crystal River Unit 3 shutdown two times this month.
(I) Reason:
A-EQUIPMENT FAILURE (Explain)
B-MAINTENANCE OR TEST C-REFUEUNG D-REGULATORY RESTRICTION E-OPERATOR TRAINING I UCENSE EXAMINATION F-ADMINISTRATIVE G-OPERATIONAL ERROR (Explain)
H-OTHER (Explahn)
(2) Method 1-MANUAL 2-MANUAL TRP I SCRAM 3-AUTO TRIP / SCRAM 4-CONTINUATON 5-OTHER (Explain)