Submits Sys Readiness Review Plan & Schedule for Phase 1 of Review Inadvertantly Omitted from Providing Info on Executive Summary of Plan
ML20137J363
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 03/31/1997
From: Kunsemiller D
FLORIDA POWER CORP.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20137J365 List:
References
3F0397-36, 3F397-36, NUDOCS 9704030278
Download: ML20137J363 (2)


Text

,c^^g

/

m Q?b i

11 Qfh Florida Power CORPORATION omane mace March 31, 1997 l

3F0397-36 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555-0001 j

Subject:

System Readiness Review Plan

References:

FPC to NRC letter 3F0397-19, dated March 27, 1997

Dear Sir:

FPC submitted information on the System Readiness Review being performed at Crystal River Unit 3 in the above referenced letter.

The referenced letter

~

forwarded an Executive Summary of the System Readiness Review Plan (SRRP).

It was intended to include a copy of the SRRP and schedule for Phase 1 of the review, however, those were inadvertently omitted from the packages sent out.

The missing Attachments 2 and 3 are enclosed. Please combine these attachments with the original letter 3F0397-19.

Should you have any questions or require additional information, please contact Brian Gutherman at (352) 563-4566.

Sincerely, Luflc David F. Kunsemiller, Director Nuclear Site Support 030066 f0D/'f Enclosures xc:

Regional Administrator, Region II Senior Resident Inspector NRR Project Manager CRYSTAL FUVER ENERGY COMPLEX: 15760 W Power une St. Crystal River, Florida 344284708 e (35:5 795 4486 A Florida Progress Corrpany 9704030278 970331 PDR ADOCK 05000302' P

PDR ggggggg[g

--._.~,

r i

3F0397-19 j

1 I

FPC - CR3 System Reaciness Review C

Phase :

l l

I, r

i i

)

, Februa ry alarch A p ril hl.,

June J uly A ugust Septem b e s; October i

i a

e i

i a

a a

i i

Level I System Reviews Le vel 2 System Reviews Level 3 System Reviews l

GROUP I Systems I

Level 3 System Reviews l

GROUP 2 Systems f

Level 3 System Reviews l

GRO UP 3 Systems I

j GitOUP 1 Systems - Potential to impact EDG/EFW Dependency G ROllP 2 System s - Potential for discovery of DH or I.fi issue

)

i G ROUP 3 System s. Rem aining System s i