10 CFR 40.33, Issuance of a License for a Uranium Enrichment Facility
Issuance of a license for a uranium enrichment facility
a
(a) The Commission will hold a hearing pursuant to 10 CFR part 2, subparts A, G, and I, on each application with regard to the licensing of the construction and operation of a uranium enrichment facility. The Commission will publish public notice of the hearing in the Federal Register at least 30 days before the hearing.
b
(b) A license for a uranium enrichment facility may not be issued before the hearing is completed and a decision issued on the application.
Federal Register
[[[FR::http://frwebgate.access.gpo.gov/cgi-bin/getpage.cgi?dbname=1992_register&page=18391&position=1%7C57 FR 18391, Apr. 30, 1992]]]
External Links
[[URL::http://www.nrc.gov/reading-rm/doc-collections/cfr/part040/part040-0033.html%7CNRC website 10 CFR 40.33]]