| Q | CCA | Title |
---|
05000456/FIN-2015001-01 | 2015Q1 | | Failure to Ensure that Temporary Structures Did Not Adversely Impact Safety during Postulated Probable Maximum Precipitation Event |
05000456/FIN-2015001-02 | 2015Q1 | H.6 | Failure to Adequately Evaluate Operability of a Degraded Control Room Chiller |
05000456/FIN-2015001-03 | 2015Q1 | H.3 | Failure to Activate the ERO During an Actual Event |
05000456/FIN-2015404-01 | 2015Q2 | | Security |
05000456/FIN-2015002-01 | 2015Q2 | | Failure to Update the Final Safety Analysis Report-Thimble Tube Inspection Program |
05000456/FIN-2015002-02 | 2015Q2 | H.14 | Mechanic Joint Leakage Accepted for Continued Service Without Code Corrective Actions |
05000456/FIN-2015002-03 | 2015Q2 | P.3 | Control Room Chiller Inoperability Due to High Oil Content in the Refrigerant |
05000456/FIN-2015007-01 | 2015Q3 | | Failure to Ensure that Circuits Associated with Pressurizer PORVs and Block Valves Were Free of Fire Damage |
05000456/FIN-2015004-03 | 2015Q4 | | Failure to Establish Adequate Feedwater Pump Operational Guidance During a Normal Plant Shutdown |
05000456/FIN-2015004-04 | 2015Q4 | | Failure to Establish a Written Procedure for a Loss of Feedwater Event in Mode 3 |
05000457/FIN-2015004-01 | 2015Q4 | | Loss of Shutdown Cooling Train During Refueling Cavity Fill and Associated Reduced Inventory Operations |
05000457/FIN-2015004-02 | 2015Q4 | | Failure of Startup Feedwater Pump to Start During Plant Shutdown |