| Q | CCA | Title |
---|
05000390/FIN-2010201-04 | 2010Q3 | | Security |
05000390/FIN-2010201-03 | 2010Q3 | | Security |
05000390/FIN-2010201-02 | 2010Q3 | | Security |
05000390/FIN-2010201-01 | 2010Q3 | | Security |
05000390/FIN-2010007-01 | 2010Q4 | | Use of Omas Potentially Not Consistent with the Fire Protection Licensing Basis |
05000390/FIN-2010005-03 | 2010Q4 | | Failure to Use Worst Case 6900 VAC Bus Voltage in Design Calculations |
05000390/FIN-2010005-02 | 2010Q4 | | Failure to Adequately Qualify Molded-Case Circuit Breakers to Safety-Related Application Through Commercial Grade Dedication |
05000390/FIN-2010007-02 | 2010Q4 | | INSTALLED INSULATING FLUID IN INTERIOR TRANSFORMERS POTENTIALLY DEVIATES FROM LICENSE/DESIGN CRITERION IN SSER 10 AND POSITION D.1.g OF APPENDIX A TO BTP (APCSB) 9.5-1 |
05000390/FIN-2010007-03 | 2010Q4 | | Questions Related to OMA to Establish RCP Seal Cooling in the Event of a Fire in AV-076, Computer Room |
05000390/FIN-2011008-01 | 2011Q1 | | Failure to Submit a Licensee Event Report for a Condition Prohibited by Technical Specifications Associated with the Essential Raw Cooling Water System |
05000390/FIN-2011002-02 | 2011Q1 | | Failure to Ensure Adequacy of AOI-13, Loss of Essential Raw Cooling Water, Revision 0038 |
05000390/FIN-2011002-01 | 2011Q1 | H.5 | Failure to Establish Adequate Compensatory Measures for a Degraded Sprinkler system in Accordance with the Approved Fire Protection Plan |
05000390/FIN-2011403-01 | 2011Q2 | H.8 | Security |
05000390/FIN-2011003-04 | 2011Q2 | | Failure to Translate Moderate Energy Line Break Study Output into a Plant Procedure |
05000390/FIN-2011003-03 | 2011Q2 | H.5 | Failure to Perform a Transient Combustible Evaluation for Storage of Oil in a Safety Related Area in Accordance with the Approved Fire Protection Plan. |
05000390/FIN-2011003-02 | 2011Q2 | H.5 | Procedure AOI-30.2 C.36, Fire Safe Shutdown Room 737-A1A, Non-feasible Operator Manual Action |
05000390/FIN-2011003-01 | 2011Q2 | H.2 | Failure to Ensure The Operability of an Emergency Battery Lighting Unit in Accordance with the Approved Fire Protection Plan |