05000389/LER-2017-002
07-14-2017 | On May 15, 2017, at 1800 hours0.0208 days <br />0.5 hours <br />0.00298 weeks <br />6.849e-4 months <br />, the St. Lucie Unit 2 2A3 4.16 KV Bus undervoltage protection relays actuated resulting in a loss of power to the bus. The 2A emergency diesel generator (EDG) did not respond to this event as this EDG had been properly removed from service for pre-planned maintenance. The 2A3 4.16 KV Bus was restored to service at 2340 hours0.0271 days <br />0.65 hours <br />0.00387 weeks <br />8.9037e-4 months <br />.
The 2A3 4.16 KV Bus was de-energized when an internal fault within the 2A EDG local voltmeter blew fuses that removed power from the undervoltage relays that resulted in the loads powered from this bus being stripped. Corrective actions included replacing the fuses and replacing the susceptible local EDG voltmeter, as well as the interim use of caution tags on the susceptible voltmeter selection switches until modifications to remove the vulnerability are complete. During this event the B train safety related electrical busses remained operable and energized. All other equipment responded to the event per the existing plant conditions and the unit remained at 100% power. The A train safety related electrical bus was restored to service well within the Technical Specification allowed outage time. Therefore, this event had no significant impact on the health and safety of the public. Reported lessons learned are incorporated into the licensing process and fed back to industry. Send comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by e-mail to Infocollects.Resource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0104), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection. Description On May 15, 2017, St. Lucie Unit 2 was in Mode 1 at 100 percent reactor power. The 2A emergency diesel generator (EDG) [EIIS:DG] was removed from service due to planned maintenance. At 1800 hours0.0208 days <br />0.5 hours <br />0.00298 weeks <br />6.849e-4 months <br />, the 2A3 4.16 KV Bus undervoltage protection relays [EIIS:27] actuated resulting in a loss of power to the bus [EIIS:SWGR]. However, the 2A EDG did not respond to this event as this EDG had been properly removed from service for pre-planned maintenance. The troubleshooting team identified blown potential transformer (PT) fuses [EIIS:FU] in the 2A EDG metering circuit. The failed fuses were replaced and the 2A3 4.16 KV Bus was repowered at 2340 hours0.0271 days <br />0.65 hours <br />0.00387 weeks <br />8.9037e-4 months <br />. The required NRC ENS notification for the system actuation was completed by 0017 hours1.967593e-4 days <br />0.00472 hours <br />2.810847e-5 weeks <br />6.4685e-6 months <br /> on May 16, 2017. During this event the B train safety related electrical busses remained operable and energized and the unit remained at 100% power. ContentsCause of the EventThe direct cause of the bus de-energization was determined to be failed secondary side PT fuses which provide power to the under voltage/degraded grid sensing circuity. The root cause was an internal failure within the local 2A EDG GE AB40 voltmeter [EIIS:MTR] causing a phase to phase short across the variable resistor. This condition resulted in the failure of the secondary PT fuses, resulting in the actuation of the 2A3 4.16 KV Bus UV relays. A contributing cause to this event was a latent design deficiency from original construction; the meter circuit did not have isolation fuses from the PT fuses. This allows an internal fault of the meter to open the protective circuit fuses and subsequently de-energize the UV relays. Analysis of the EventEven though the 2A EDG did not respond to the loss of the 2A3 bus because it was properly removed from service, the 2A3 4.16 KV bus UV protection relays did respond to the event and their actuation is reportable in accordance with 10 CFR 50.73(a)(2)(iv)(A). Two conditions contributed to the plant response to the event: 1. The local voltmeter selector switch was in the 1-3 position. This position allowed the meter fault to be simultaneously communicated to both phases of the PT fuses. These fuses provide sensing power to the UV relays which provide electrical isolation to the safety related 2A3 4.16 KV bus. Upon sensing the loss of power to the onsite power system, the safety portion of the system is automatically isolated from the non- safety portion of the system by the operation of circuit breakers on the lines between non-safety and safety related buses. 2. The 2A EDG was out of service for the on-line preventive maintenance period. This precluded the 2A EDG from starting and assuming the loads of the 2A3 4.16 KV bus. Section 8.3 of the UFSAR, Table 8.3-6 4.16 KV Safety Related System – Failure Modes and Effects Analysis describes the consequences of loss of offsite and EDG power to the 2A3 or 2B3 bus. The analysis states that the loss of an EDG in this case will result in the loss of a one safety related bus, however, the redundant safety system remains to supply the redundant safety related loads. Additionally, DC control power in this event remained unaffected, and the A side instrument inverters remained powered throughout by the A side DC battery. FPL performed extent of condition/extent of cause reviews for AC voltage metering circuits containing the GE AB40 voltmeter, as well as other voltmeters, for both units' safety related 4160 and 480 volt buses. The review determined that, with one exception, all remote voltage indication associated with the reactor turbine generator board (RTGB) voltmeters are all fused providing isolation of the metering circuit from their respective protective functions. The exception involves the Unit 2 local EDG voltmeters. The U2 EDG local metering circuits were determined to be the only safety related 4160 and 480 volt metering circuit whose failure could initiate a Reported lessons learned are incorporated into the licensing process and fed back to industry. Send comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by e-mail to Infocollects.Resource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0104), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection. protective function (e.g., blown PT fuses resulting in the de-energization of its associated bus UV relays). These reviews also identified several metering circuits that were not fuse protected; however, in these cases any proposed meter failure would only annunciate with no corresponding automatic protective function. Safety SignificanceThe 2A EDG received a start signal from the under voltage condition on the 2A3 bus, but did not start as the EDG had been properly removed from service for preplanned maintenance. Upon a loss of indicated power to the potential transformers, the 2A3 4.16 KV bus responded appropriately for the existing plant conditions (e.g., the under voltage circuit relays actuated, the incoming breaker to the 4.16 KV bus opened, and a start signal was provided to the associated 2A EDG which was properly removed from service). Although the safety related 2A3 loads were lost during this event, the redundant loads serviced by the 2B3 train 4.16 KV safety related electrical bus remained unaffected by the event and the unit remained at 100% power. Normal power was restored to the 2A3 4.16KV bus within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> of the event, well within the allowable 8-hour Technical Specification action statement for restoring the 2A3 4.16 KV bus. Therefore, this event had no significant impact on the health and safety of the public. The Unit 2 UFSAR section 8.3 describes Failure Modes and Effects for the 4.16 KV safety related system. This analysis bounds the observation of the event described in this LER. Corrective ActionsEDG voltmeter selector switches directing that the switches not be left in the 1-3 position. 2. The local voltmeter for the 2A EDG was replaced. The following corrective action is being managed under the Corrective Action Program: 3. The local voltmeter for the 2B EDG will be replaced. 4. FPL is developing a modification to the 2A and 2B EDG metering circuit to install coordinated fuses between the metering circuit and the PT fuses to isolate the metering circuit from the UV relays in the event of a voltmeter fault. Failed Components Identified General Electric AB40 voltmeters Additional InformationNone |
---|
St. Lucie Unit 2 | |
Event date: | 5-15-2017 |
---|---|
Report date: | 07-14-2017 |
Reporting criterion: | 10 CFR 50.73(a)(2)(iv)(A), System Actuation |
3892017002R00 - NRC Website | |
|