05000259/LER-2014-003, Regarding Turbine Generator Neutral Overvoltage Causes a Reactor Scram

From kanterella
(Redirected from 05000259/LER-2014-003)
Jump to navigation Jump to search
Regarding Turbine Generator Neutral Overvoltage Causes a Reactor Scram
ML14302A164
Person / Time
Site: Browns Ferry Tennessee Valley Authority icon.png
Issue date: 10/24/2014
From: Polson K
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LER 14-003-00
Download: ML14302A164 (8)


LER-2014-003, Regarding Turbine Generator Neutral Overvoltage Causes a Reactor Scram
Event date:
Report date:
Reporting criterion: 10 CFR 50.73(a)(2)(iv)(A), System Actuation

10 CFR 50.73(a)(2)(i)

10 CFR 50.73(a)(2)(vii), Common Cause Inoperability

10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded

10 CFR 50.73(a)(2)(viii)(A)

10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition

10 CFR 50.73(a)(2)(viii)(B)

10 CFR 50.73(a)(2)(iii)

10 CFR 50.73(a)(2)(ix)(A)

10 CFR 50.73(a)(2)(x)

10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor

10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat

10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown

10 CFR 50.73(a)(2)(v), Loss of Safety Function

10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications
2592014003R00 - NRC Website

text

Tennessee Valley Authority, Post Office Box 2000, Decatur, Alabama 35609-2000 October 24, 2014 10 CFR 50.73 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Browns Ferry Nuclear Plant, Unit 1 Renewed Facility Operating License No. DPR-33 NRC Docket No. 50-259

Subject:

Licensee Event Report 50-259/2014-003-00 The enclosed Licensee Event Report provides details of a turbine trip resulting in an automatic reactor scram. The Tennessee Valley Authority (TVA) is submitting this report in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 50.73(a)(2)(iv)(A), Any event or condition that resulted in automatic or manual actuation of any systems listed in paragraph (a)(2(iv)(B), reactor protection and containment isolation systems.

There are no new regulatory commitments contained in this letter. Should you have any questions concerning this submittal, please contact J. L. Paul, Nuclear Site Licensing Manager, at (256) 729-2636.

Respectfully, K. J. Poison Site Vice President

Enclosure:

Licensee Event Report 50-259/2014-003 Turbine Generator Neutral Overvoltage Causes a Reactor Scram cc (w/ Enclosure):

NRC Regional Administrator - Region II Senior Resident Inspector - Browns Ferry Nuclear Plant

ENCLOSURE Browns Ferry Nuclear Plant Unit I Licensee Event Report 50-259/2014-003-00 Turbine Generator Neutral Over-Voltage Causes a Reactor Scram See Enclosed

NRC FORM 366 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB NO. 3150-0104 EXPIRES 0113112017 (02-2014)

, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.

3. PAGE Browns Ferry Nuclear Plant, Unit 1 05000259 1 of 6
4. TITLE: Turbine Generator Neutral Overvoltage Causes a Reactor Scram
5. EVENT DATE
6. LER NUMBER
7. REPORT DATE
8. OTHER FACILITIES INVOLVED SEQUENTIAL REV MONTH DAY YEAR FACILITY NAME DOCKET NUMBER NUMBER NO.

N/A 05000 FACILITY NAME DOCKET NUMBER 08 26 2014 2014 003 00 10 24 2014 N/A 05000

9. OPERATING MODE
11. THIS REPORT IS SUBMITTED PURSUANT TO THE REQUIREMENTS OF 10 CFR §: (Check all that apply)

[1 20.2201(b)

El 20.2203(a)(3)(i)

El 50.73(a)(2)(i)(C)

[I 50.73(a)(2)(vii) 10 20.2201(d)

[I 20.2203(a)(3)(ii)

[] 50.73(a)(2)(ii)(A)

[I 50.73(a)(2)(viii)(A)

El 20.2203(a)(1) 0l 20.2203(a)(4) 0l 50.73(a)(2)(ii)(B)

[E 50.73(a)(2)(viii)(B) 0_ 20.2203(a)(2)(i) 0l 50.36(c)(1)(i)(A) 0l 50.73(a)(2)(iii)

[I 50.73(a)(2)(ix)(A)

10. POWER LEVEL 0l 20.2203(a)(2)(ii) 0l 50.36(c)(1)(ii)(A) 0 50.73(a)(2)(iv)(A)

[I 50.73(a)(2)(x) 0] 20.2203(a)(2)(iii) 0] 50.36(c)(2)

[]50.73(a)(2)(v)(A)

F-1 73.71 (a)(4) 0l 20.2203(a)(2)(iv)

[I 50.46(a)(3)(ii) 0l 50.73(a)(2)(v)(B)

El 73.71(a)(5) 095 El 20.2203(a)(2)(v) 0l 50.73(a)(2)(i)(A)

E] 50.73(a)(2)(v)(C)

El OTHER El 20.2203(a)(2)(vi)

El 50.73(a)(2)(i)(B)

El 50.73(a)(2)(v)(D)

Spefyr nAbstractbeio...in D. Manufacturer and model number (or other identification) of each component that failed during the event:

The failed component was the Generator Circuit Breaker A-Phase Potential Transformer manufactured by ABB. The ABB Part Number is 1 HCO068399M001 1.

E. Other systems or secondary functions affected

There were no other system or secondary functions affected.

F. Method of discovery of each component or system failure or procedure error:

Operations received main control room indications of the turbine trip and subsequent automatic reactor scram.

G. The failure mode, mechanism, and effect of each failed component, if known:

The failed component was the BFN Unit 1 Generator Circuit Breaker A-Phase Potential Transformer. The potential transformer failed catastrophically due to an internal fault. The fault energy vaporized some of the transformer internals and the resulting gas pressure exceeded the strength of the polymeric housing. The resulting tear in the housing relieved the pressure and also provided an escape pathway for the potting compound used to seal and insulate the windings. This failure resulted in a rise in neutral voltage causing the turbine to trip on a generator neutral over voltage signal from the 1A generator neutral overvoltage relay.

H. Operator actions

Following the automatic reactor scram and PCIS isolation, Operations personnel responded to the scram in accordance with the Abnormal Operating Instructions.

Operations personnel entered an Emergency Operating Instruction on Low Reactor Water Level.

111.

Cause of the Event I Problem Statement A. The cause of each component or system failure or personnel error, if known:

Direct Cause The direct cause of the automatic reactor scram was the actuation of the Neutral Overvoltage Relay.

Root Cause The root cause of the event was the failure of an internal fuse [FU] to Generator Circuit Breaker Potential Transformer to clear a fault due to improper fuse size. This was the result of insufficient technical rigor during vendor design and in the Tennessee Valley Authority's (TVA) review of the vendor design.

Contributing Cause

The contributing cause for this event was vendor manufacturing defects caused the Generator Circuit Breaker A-Phase Potential Transformer to experience a catastrophic failure.

NRC FORM 366 (02-2014)

B. The cause(s) and circumstances for each human performance related root

cause

There was not a human performance related root cause.

IV.

Analysis of the event

The TVA is submitting this report in accordance with 10 CFR 50.73(a)(2)(iv)(A), as any event or condition that resulted in manual or automatic actuation of any of the systems listed in paragraph (a)(2)(iv)(B), reactor protection and containment isolation systems.

On August 26, 2014, at 1730 CDT, BFN, Unit 1, experienced a turbine trip resulting in an automatic reactor scram. The cause of the turbine trip was a control valve fast closure signal that was generated by a generator neutral over voltage signal. The generator neutral over voltage relay actuated due to catastrophic failure of the A-Phase Potential Transformer contained in the generator circuit breaker.

The failed Potential Transformer was installed as part of the generator circuit breaker replacement in December of 2012. In June 2014, preventive maintenance was performed on all three BFN generators and isophase bus systems. No deficiencies related to this failure were identified.

During this event, the 2A protective fuse in the A-Phase Potential Transformer failed to clear. The cause evaluation for this event concluded the fuse's failure to clear the fault was due to improper fuse size resulting from insufficient technical rigor during vendor design and TVA's review of the design. The protective fuse should have been sized to clear all failure modes of the Protective Relay. The corrective action to prevent recurrence will develop and implement a design change to change the Potential Transformer protective fuse from a 2 Amp fuse to a 0.5 Amp fuse. The change in fuse size will cause the fuse to clear prior to the actuation point of the Generator Neutral Overvoltage Relay preventing Potential Transformer failures from impacting plant generation.

V.

Assessment of Safety Consequences

Nuclear Safety was challenged by the need for a reactor scram. However, Nuclear Safety was maintained by the automatic protective functions that resulted in the scram followed by appropriate operator actions based on procedural requirements.

A. Availability of systems or components that could have performed the same function as the components and systems that failed during the event:

The failed component was related to power generation. No safety systems were adversely impacted by this event.

B. For events that occurred when the reactor was shut down, availability of systems or components needed to shutdown the reactor and maintain safe shutdown conditions, remove residual heat, control the release of radioactive material, or mitigate the consequences of an accident:

This event did not occur when the reactor was shut down.

NRC FORM 366 (02-2014)

C. For failure that rendered a train of a safety system inoperable, an estimate of the elapsed time from discovery of the failure until the train was returned to service:

This event did not result in the inoperability of a safety system.

VI.

Corrective Actions

Corrective Actions are being managed by TVA's corrective action program under Problem Evaluation Report (PER) 926429.

Immediate and Interim Corrective Actions

  • TVA implemented a temporary modification to disconnect Unit 1 Main Generator Circuit Breaker Potential Transformers on both the Main Bank Transformer side and Main Generator Neutral Overvoltage Relay
  • Work orders were issued for BFN Unit 1 to perform inspections of the Potential Transformers, Surge Arresters, and Capacitors within the Generator Circuit Breaker for indication of potential failure.

Replaced Potential Transformers.

  • Initiated work orders to perform visual inspections and electrical testing of the BFN Unit 1 isophase bus.

Corrective Actions to Prevent Recurrence The corrective action to prevent recurrence is to develop and implement a design change for all three BFN Units to replace the fuses contained within the Main Generator Circuit Breaker Potential Transformers with a fuse that will coordinate with the Generator Neutral Overvoltage Relay and clear prior to the actuation point of the Generator Neutral Overvoltage Relay during any postulated failure of the Potential Transformers.

VII.

Additional Information

A. Previous similar events at the same plant:

A search of the Corrective Action Program and BFN Licensee Event Reports for Units 1, 2, and 3, for approximately the past three years did not identify any similar events.

B. Additional Information

There is no additional information.

C. Safety System Functional Failure Consideration:

In accordance with the Nuclear Energy Institute (NEI) 99-02, "Regulatory Assessment Performance Indicator Guideline," this event is not considered a system functional failure.

NRC FORM 366 (02-2014)

D. Scram with Complications Consideration:

This event did not result in an unplanned scram with complications because:

1. The Reactor Protection system established a shutdown rod pattern for a cold clean core;
2. Reactor Pressure control was able to be established following the initial transient;
3. Power was not lost to any class 1 E Emergency / Engineered Safety Feature bus;
4. A Level 1 Injection signal was not received;
5. The Main Feedwater system was available or recoverable using approved plant procedures during the scram response: and
6. Following the initial transient, stabilization of the reactor pressure/level and did not require remaining in the BFN emergency operating instructions.

VIII. Commitments

There are no commitments.

NRC FORM 366 (02-2014)