Title | Inadequate Evacuation Time Estimate Submittals |
Description | The NRC identified a NCV of 10 CFR 50.54(q)(2) associated with 10 CFR 50.47(b)(10) and 10 CFR Part 50, Appendix E, Section IV.4, for failing to maintain the effectiveness of the Dresden Nuclear Power Station Emergency Plan as a result of failing to provide the station evacuation time estimate (ETE) to the responsible offsite response organizations (OROs) by the required date. Exelon submitted the Dresden Nuclear Power Station ETE to the NRC on December 12, 2012, prior to the required due date of December 22, 2012. The NRC completeness review found the ETEs to be incomplete due to Exelon fleet common and site-specific deficiencies, thereby preventing Exelon from providing the ETEs to responsible OROs and from updating site-specific protective action strategies as necessary. The NRC discussed its concerns regarding the completeness of the ETE, in a teleconference with Exelon on June 10, 2013, and on September 5, 2013, Exelon resubmitted the ETEs for its sites. The NRC again found the ETEs to be incomplete. The issue is a performance deficiency because it involves a failure to comply with a regulation that was under Exelons control to identify and prevent. The finding is more than minor because it is associated with the emergency preparedness cornerstone attribute of procedure quality and because it adversely affected the cornerstone objective of ensuring that the licensee is capable of implementing adequate measures to protect the health and safety of the public in the event of a radiological emergency. The finding is of very low safety significance because it was a failure to comply with a non-risk significant portion of 10 CFR 50.47(b)(10). The licensee had entered this issue into their corrective action program (CAP) and re-submitted a new revision of the Dresden Nuclear Power Station ETE to the NRC on May 2, 2014, which was found to be complete by the NRC. The cause of the finding is related to the cross-cutting element of Human Performance, Documentation. |
Site: | Dresden |
---|---|
Report | IR 05000237/2014004 Section 1EP5 |
Date counted | Sep 30, 2014 (2014Q3) |
Type: | NCV: Green |
cornerstone | Emergency Prep |
Identified by: | NRC identified |
Inspection Procedure: | IP 71114.05 |
Inspectors (proximate) | A Smith D Lords G Roach J Beavers J Cameron J Kutlesa J Laughlin S Barr |
Violation of: | 10 CFR 50.47(b)(10) 10 CFR 50 Appendix E 10 CFR 50.47 10 CFR 50.54(q) 10 CFR 50.54 |
CCA | H.7, Documentation |
INPO aspect | WP.3 |
' | |