Semantic search

Jump to navigation Jump to search
 Issue dateTitle
IR 05000327/202200410 February 2023Integrated Inspection Report 05000327/2022004 and 05000328/2022004
IR 05000327/20220021 August 2022Integrated Inspection Report 05000327 2022002 and 05000328 2022002
IR 05000327/20210047 February 2022Integrated Inspection Report 05000327/2021004 and 05000328/2021004
Information Notice 2019-01, Inadequate Evaluation of Temporary Alterations12 March 2019Inadequate Evaluation of Temporary Alterations
IR 05000327/20180017 May 2018Nuclear Regulatory Commission Integrated Inspection Report 05000327/2018001 and 05000328/2018001
ML20311A41220 April 20182017 Q1-Q4 ROP Inspection Findings
ML20311A37920 April 20182017 Q1-Q4 ROP Inspection Findings
ML18061A0362 March 2018IAEA Report of the Operational Safety Review Team (Osart) Mission to the Sequoyah Nuclear Power Plant
CNL-14-013, Highlights of Improvements to the Sequoyah Nuclear Plant IPEEE Seismic Analysis Results and Supplemental Response to NRC Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f)Regarding...31 January 2014Highlights of Improvements to the Sequoyah Nuclear Plant IPEEE Seismic Analysis Results and Supplemental Response to NRC Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f)Regarding...
ML13274A50227 September 2013Initial Exam 2012-302 Draft SRO Written Exam
ML13294A43026 September 2013Fukushima Near-Term Task Force Recommendation 2.3: Seismic Response Report, Revision 1
ML13282A23326 September 2013Fukushima Near-Term Task Force Recommendation 2.3: Seismic Response Report
IR 05000327/201300723 September 2013IR 05000327-13-007, 05000328-13-007, on 7/8/2013-8/9/2013, Sequoyah Nuclear Plant, Units 1 and 2, Component Design Bases Inspection
ML13178A28026 June 2013American Society of Mechanical Engineers Request for Alternative 11-SPT-1
IR 05000327/201200513 February 2013IR 05000327-12-005, 05000328-12-005; 10/1-12/31/2012; Sequoyah Nuclear Plant, Units 1 and 2; (I.E. Adverse Weather Protection, Fire Protection, Inservice Inspection Activities, Refueling and Outage Activities, and Problem Identification and
ML12335A34027 November 2012Tennessee Valley Authority - Fleet Response to NRC Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding the Flooding Walkdown Results of Recommendation 2.3 of the Near-Term Task Force Review of
ML12342A13312 November 2012Fukushima Near-Term Task Force Recommendation 2.3: Seismic Response Report
ML12342A13412 November 2012Fukushima Near-Term Task Force Recommendation 2.3: Seismic Response Report
ML12072A2368 March 2012Response to NRC Third Request for Additional Information Regarding the Proposed Technical Specification Changes to Allow Use of Shield Building Dome Penetrations During Modes 1 Through 4
ML11249A06131 August 2011Application for Temporary Change to TS to Allow Use of Penetrations in Shield Building Dome During Modes 1 Through 4;and Request for Specific Usage of Alternate Source Term Methodology for Calculating Radiation Doses Associated.
IR 05000327/20110068 July 2011IR 05000327-11-006, 05000328-11-006, on 01/24 - 28/2011 and 02/7 - 11/2011, Sequoyah Nuclear Plant, Units 1 and 2, Fire Protection
ML1103904224 February 2011Initial Exam 2010-302 Final Administrative JPMs
IR 05000327/201000528 January 2011IR 05000327-10-005, 05000328-10-005; 10/01/2010 - 12/31/2010; Sequoyah Nuclear Plant, Units 1 and 2; Fire Protection, and Other Activities
ML11028045928 January 2011IR 05000327-10-005, 05000328-10-005; 10/01/2010 - 12/31/2010; Sequoyah Nuclear Plant, Units 1 and 2; Fire Protection, and Other Activities
ML10204051416 July 2010Application for State Operating Permit (SOP) for Pump and Haul Activities
ML08289054011 October 2008Sequoyah, Units 1 and 2, and Watts Bar, Unit 1 - 9 Month Response to NRC Generic Letter 2008-01: Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems, Dated 01/11/2008
ML08197070923 July 2008Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems, Proposed Alternative Course of Action
ML0816300866 June 2008Browns Ferry, Sequoyah, Watts Bar - Revised Initial Response to NRC Generic Letter 2008-01: Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems, Dated January 11, 2008
ML08072052529 February 2008Feb Exam 05000327-08-301, 05000328-08-301 Final Administrative JPMs
ML08030011525 January 2008Notification of Inspection and Request for Information
ML06121010521 April 2006Risk-Informed Inservice Inspection (RI-ISI) Program and Updated Inservice Inspection Program for Third 10-Year Interval
IR 05000327/200600214 April 2006IR 05000327-06-002, IR 05000328-06-002, on 01/01/2006 - 03/31/2006, Tennessee Valley Authority, and Annual Assessment Meeting Summary
ML06102031311 April 2006Generic Letter 2004-02 - Potential Impact of Debris Blockage on Emergency Recirculation During Design-Basis Accidents at Pressurized Water Reactors - Response to Request for Additional Information
ML06037048010 February 2006Request for Additional Information Response to Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design-basis Accidents at Pressurized-water Reactors
IR 05000327/200500328 July 2005IR 05000327-05-003, 05000328-05-003, on 04/01/2005 - 06/30/2005; Sequoyah Nuclear Power Plant, Units 1 & 2; Flood Protection Measures, Refueling and Outage Activities, Event Followup
ML04202019419 July 2004Relief Request, Inservice Inspection of Class 1 & Class 3 Welds
ML03353000515 December 2003Meeting Handout TVA Nuclear Strategic Performance Improvement Initiatives.
ML0304306065 August 2002December 2002-301 Exam Draft Outlines and JPMs
IR 05000327/200200225 July 2002IR 05000327-02-002 & IR 05000328-02-002 on 03/31 - 06/29/2002, Tennessee Valley Authority, Sequoyah Nuclear Plants, Units 1 and 2. Inservice Inspection Activities, Permanent Plant Modifications
ML02102047326 April 2002Uit 1 - Reuests for Code Relief GISI-1, GISI-2, and GISPT-1
ML03295014925 April 2002TVA - Licensee Exhibit 73 - Rec'D 04/25/02: Significant Corrective Action Report (Scar) No. SQSCA920004 (Cg 1-82)
ML20236Y2097 August 1998Safety Evaluation Accepting Relief Requests RP-03,RP-05, RP-07,RV-05 & RV-06 & Denying RV-07 & RV-08
NRC Generic Letter 1998-0414 July 1998NRC Generic Letter 1998-004: Potential for Degradation of the Emergency Core Cooling System and the Containment Spray System After a Loss-of-coolant Accident Because of Construction and Protective Coating Deficiencies and Foreign Material i
ML20217A64016 April 1998Provides Request for Relief RV-8 from Compliance to ASME OM-10,4.3.2.4(c) Code Requirement,Per 10CFR50.55a(a)(3)(ii) as Hardship or Unusual Difficulty Without Compensating Increase in Level of Quality & Safety
ML20217K46230 January 1998Technical Evaluation Rept on Second 10-Yr Interval ISI Program Plan:Tva,Sequoyah Nuclear Plant,Units 1 & 2
IR 05000327/199700915 September 1997Insp Repts 50-327/97-09 & 50-328/97-09 on 970804-08.No Violations Noted.Major Areas Inspected:Operations,Maint & Engineering Re Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems
ML20138C53724 March 1997Rev 0 to Pressurizer Level Event
ML20137F70818 March 1997Insp Repts 50-327/97-01 & 50-328/97-01 on 970119-0301. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering,Plant Support & Effectiveness of Licensee Controls in Identifying & Preventing Problems
ML20134L30120 November 1996Press Release II-96-97, NRC Staff Proposes $50,000 Fine Against TVA at Sequoyah
ML20134J7458 November 1996Summary of 961104 Meeting W/Tva in Rockville,Md Re Status of Thermo-Lag Fire Barrier Upgrades at Plant.List of Attendees & Copies of Handouts Encl