Suppl to 901026,910628 & 1118 Applications for Amends to Licenses NPF-37,NPF-66,NPF-72 & NPF-77,changing TS to Allow Setpoint Change for D-4 & D-5 Steam Generators
ML20086T788
Person / Time
Site: Byron, Braidwood  Constellation icon.png
Issue date: 12/24/1991
From: Schuster T
COMMONWEALTH EDISON CO.
To: Murley T
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM), Office of Nuclear Reactor Regulation
References
TAC-M79082, TAC-M79613, TAC-M80872, TAC-M80873, NUDOCS 9201070061
Download: ML20086T788 (2)


Text

,/ .

Commonwealth Edisoa

  • 1400 Opus Place

.~

OO Downers Grove lilinois 60515 December 24, 1991 Dr. Thomas E. Murley, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Hashington, D.C. 20555 Attn: Document Control Desk

Subject:

Byron Station Units 1 and 2 Braidwood Station Units 1 and 2 Supplement to Application for Amendment to facility Operating Licenses NPF-37/66 L HPF 72/77 Appendix A, Technical Specifications TAC M79082, M79613, M80872 and M80873 MCloche t3olu50- 4541455_ and _50-4561/ A 57

References:

(a) October 26, 1990 letter " rom T. Schuster to Dr. T. Murley containing an application for Amendment to the Byron /Braidwood Facility Operating Licenses.

(D-4 Steam Generator Setpoint Change)

(b) November 18, 1991 letter from T. Schuster to Dr. T. Murley supplementing the proposed Amendment of Reference (a),

(D-4 Steam Generator Setpoint Change)

(c) June 28, 1991 letter from T. Schuster to Dr. T. Murley containing an application for Amendment to the Byron /Braidwood Facility _

Operating Licenses.

(D-5 Steam Generator Setpoint Change)

Dear Dr. Murley:

In References (a) through (c), pursuant to 10 CFR 50.90, Commonwealth Edison Company (CECO) proposed to amend Appendix A, Technical Specifications of Facility Operating Licenses NPF-37/66 and NPF-72/77 for Byron /Braidwood Stations. The proposed amendment of Reference (a) and (b) will allow a setpoint change for the Unit 1 Model D-4 Heam Generators level instrumentation, while the proposed amendment of Reference (c) will allow a setpoint change for the Unit 2 Model D-5 Steam Generators level Instrumentation at each plant. Each of these amendments will affect only one unit's license, yet affect common pages in each cf the separate Technical Specifications books being maintained at NRR. Commonwealth Edison requests that after each amendment is appiSved that both unit / license specific Technical Specification books for each station be updated with the amended pages. This request is solely administrative in nature. There is therefore no change in the no bignificant hazards consideration determination of the previous submittals.

ZHLD/1389/8 ]$ M, OO

\\D

s ~

. Dr'. T.E. Murley December 24, 1991 Commonwealth Edison is notifying the State of lilinois of this supplement to on application for amendment by transmitting a copy of this letter and its attachment to the designated State Official.

To the best of my knowledge and belief the statements contained herein are true and correct. In scae respects, these statements are not based on my personal knowledge but upon information received from other Commonwealth Edison and cor. tractor employees. Such information has been reviewed in accordance with Company practice an I believe it to be reliable.

Please direct any questions you may have concerning this matter to this office.

Respectfully, (fus(f YK Terence K. Schuster Nuclear Licensing Administrator cc: W. Kropp - Resident Inspector, Byron S. Dupont - Resident Inspector, Braidwood A. Hsia - Project Manager (Byron), NRR R. Pulsifer - Project Manager (Braidwood), NRR _

B. Clayton - Branch Chief, Region III Office of Nuclear Faci'ity Safety - IDNS s A g biat.3 et _ 60.mty of ..%m

r g 2c; w v  % ge -

- . 5 yE OF IttikO'S Notary Public 7 ,, * : 'W4ES (sis /94 >

, sm2 p~l N

ZNLD/1389/9