NRC Public Meeting Slides from GEH 06-05-2019_Rev2
ML19148A480
Person / Time
Site: Vallecitos Nuclear Center
Issue date: 06/05/2019
From: Heckman D
GE Hitachi Nuclear Energy
To:
Office of Nuclear Reactor Regulation
Hardesty D
References
Download: ML19148A480 (9)


Text

GE Hitachi Meeting with NRC Vallecitos Nuclear Test Reactor (NTR)

R-33 License Renewal Rockville, MD June 5, 2019

Agenda Welcome & Introductions Purpose of Meeting NTR Operation Overview NTR License Current Status License Renewal Plan Additional Licensing Considerations Discussion 2

Copyright 2019 GE-Hitachi Nuclear Energy Americas, LLC - All Rights Reserved

GE Hitachi NTR Operation Site 35 miles E-SE of San Francisco North of State Route 84 2 miles east of I-680 1,600 acre rectangular tract 135 acre site developed area houses all buildings and licensed activities

  • Distances are approximate Copyright 2019 GE-Hitachi Nuclear Energy Americas, LLC - All Rights Reserved

GE Hitachi NTR Operation Site Owner Controlled Area

  • The NTR is in a stand-alone building within the 135 acre site developed area in the SW corner of the Owned Controlled Area
  • The site includes three retired, defueled reactors currently in possession-only status.

Copyright 2019 GE-Hitachi Nuclear Energy Americas, LLC - All Rights Reserved

Vallecitos Nuclear Center Products & Services Medical & Industrial Sealed Source Fabrication Co-60: medical therapy, medical & industrial sterilization Cf-252: nuclear reactor startup & industrial sources Neutron Radiography Non-destructive examination of hardware & components NASA, defense contractors, nuclear industry Copyright 2019 GE-Hitachi Nuclear Energy Americas, LLC - All Rights Reserved

NTR Current Status Operating NTR (R-33):

100 kW thermal NTR used for non-destructive material imaging License issued: October 31, 1957 Licensed renewed: July 22, 1969, December 28, 1984 and April 20, 2001 (current)

License expiration date: April 20, 2021 NTR has unique imaging capabilities, requesting license renewal until 2041 Ongoing principal activity Copyright 2019 GE-Hitachi Nuclear Energy Americas, LLC - All Rights Reserved 5

License Renewal Plan October 2019: Update and incorporate by reference previously submitted SAR and Tech Specs and pending amendments

~April 2020: Submit license renewal application per NUREG-1537/Interim Staff Guidance (Oct.

2009, Streamlined Review Process)

Copyright 2019 GE-Hitachi Nuclear Energy Americas, LLC - All Rights Reserved 6

Additional Licensing Considerations Updates to chapters 4 & 13 involving revisions to core modeling codes, neutronics and thermal hydraulics Inclusion of pending Amendment 24 as necessary Decommissioning Financial Assurance

$5.2 million security bond effective March 28, 2018 Pending revision to $5.4 million Copyright 2019 GE-Hitachi Nuclear Energy Americas, LLC - All Rights Reserved 7

Discussion 8

Copyright 2019 GE-Hitachi Nuclear Energy Americas, LLC - All Rights Reserved