ENS 47872
ENS Event | |
---|---|
07:00 Apr 29, 2012 | |
Title | Part 21 Report - Controllers Did Not Meet Emi / Rfi Guidelines |
Event Description | This report constitutes a 10 CFR Part 21 notification. On March 23, 2012, Scientech (a business unit of Curtis Wright Flow Control), sent a 10 CFR Part 21 report (Letter Number 12-09-BB) to Pacific Gas & Electric Company. Diablo Canyon Nuclear Plant (DCPP) entered this report into its corrective action program on April 23, 2012. This Part 21 report identified that eight AMS286 and AMS287 hand controllers supplied to DCPP had a deviation from the purchase specification. DCPP specified the controllers to be qualified to meet electromagnetic interference (EMI) / radio frequency interference (RFI) emissions and susceptibility in accordance with NRC Regulatory Guide 1.180, Rev. 1. Contrary to this requirement, Scientech did not perform the EMI / RFI testing on the AMS286 controllers shipped to DCPP with a Certificate of Conformance to DCPP's specification. Scientech tested the AMS287 controllers, which failed some of the required testing, but were shipped to DCPP with a Certificate of Conformance nonetheless. DCPP accepted the controllers based on the Certificates of Conformance, but did not install them. Following acceptance of the controllers, DCPP identified the nonconformance with its specification, and had another vendor modify the controllers to subsequently pass required testing.
DCPP determined the deviation could have potentially created a substantial safety hazard if the controllers were installed at DCPP. The controllers were intended to control auxiliary feedwater from the Unit 1 control room and the hot shutdown panel as part of an upcoming process control system modification. Following a postulated fire in the control room, plant shutdown would be managed from the hot shutdown panel. In this instance, radios would be used to communicate with operators at the panel. The controllers would be susceptible to EMI/RFI interference and could potentially affect the operators' ability the safely shut down the plant and maintain it in a safe shutdown condition. DCPP notified Scientech of this conclusion on 4/27/12. The licensee notified the NRC Resident Inspector. |
Where | |
---|---|
Diablo Canyon California (NRC Region 4) | |
Reporting | |
10 CFR 21.21(d)(3)(i), Failure to Comply or Defect | |
Time - Person (Reporting Time:+10.58 h0.441 days <br />0.063 weeks <br />0.0145 months <br />) | |
Opened: | Dennis Petersen 17:35 Apr 29, 2012 |
NRC Officer: | Donald Norwood |
Last Updated: | Apr 29, 2012 |
47872 - NRC Website | |
WEEKMONTHYEARENS 547212020-05-18T18:57:00018 May 2020 18:57:00
[Table view]10 CFR 21.21(d)(3)(i), Failure to Comply or Defect Part 21 Report - Inadequate Dedication of Replacement Thermocouples ENS 478722012-04-29T07:00:00029 April 2012 07:00:00 10 CFR 21.21(d)(3)(i), Failure to Comply or Defect Part 21 Report - Controllers Did Not Meet Emi / Rfi Guidelines 2020-05-18T18:57:00 | |