Press Release-11-058, NRC Issues Final Supplemental Environmental Impact Statement for Vogtle New Reactors Application

From kanterella
Revision as of 22:11, 8 August 2018 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Press Release-11-058: NRC Issues Final Supplemental Environmental Impact Statement for Vogtle New Reactors Application
ML110840184
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 03/25/2011
From:
Office of Public Affairs
To:
References
Press Release-11-058
Download: ML110840184 (2)


Text

NRC ISSUES FINAL SUPPLEMENTAL ENVIRONMENTAL IMPACT STATEMENT FOR VOGTLE NEW REACTOR S APPLICATION The Nuclear Regulatory Commission has completed its Final Supplemental Environmental Impact Statement (F SEIS) for a limited work authorization (LWA) and the Combined Licenses (COL) for the proposed Vogtle Units 3 and 4 reactors. The NRC, in its FSEIS, conclude d that there are no environmental impacts that would preclude issuing the LWA and COL s for construction and operation of the proposed reactors at the site, near Waynesboro, Ga. The F SEIS will be available on the NRC website at: http://www.nrc.gov/reading

-rm/doc-collections/nuregs/staff/sr1947/. The NRC staff issued a draft SEIS for the LWA and COL s in September 2010 that supplemented its environmental findings from the Early Site Permit issued for the Vogtle site in August 2009

. The staff held a public meetin g in October 2010 to gather comments on the draft SEIS.

Southern Nuclear Operating Company submitted its new reactor application for Vogtle on March 23, 2008, and supplemented the application on Oct. 2, 2009

. Southern is applying for license s to build and operate two AP1000 reactors at the Vogtle site, adjacent to the company's existing reactors approximately 26 miles southeast of Augusta, Ga. Westinghouse submitted an application to amend the already

-certified AP1000, a 1,100 megawatt electric design, on May 26, 2007. More information on the AP1000 amendment review is available on the NRC website here: http://www.nrc.gov/reactors/new

-reactors/design

-cert/amended

-ap1000.html

. The NRC's publishing of the F SEIS is only part of the overall Vogtle COL review. The agency staff continues to compile its final safety evaluation report (SER), which will include recommendations from the NRC's Advisory Committee on Reactor Safeguards, an independent group of nuclear safety experts. The NRC's final licensing decision will be based on the F SEIS and SER findings, along with a ruling from the five

-member Commission that heads the agency.

The Vogtle F SEIS can also be viewed in the NRC's ADAMS online documents system at http://wba.nrc.gov:8080/ves by entering accession number ML11076A010 in the search window.

In addition, the Burke County Library, 130 Highway 24 South in Waynesboro, will have a hardbound copy of the F SEIS available for public inspection.

NRC NEWS U.S. NUCLEAR REGULATORY COMMISSION Office of Public Affairs Telephone: 301/415

-8200 Washington, D.C. 20555

-0001 E-mail: opa.resource@nrc.gov Site: www.nrc.gov Blog: http://public

-blog.nrc-gateway.gov No.11-058 March 25, 2011

      1. News releases are available through a free listserv subscription at the following Web address: http://www.nrc.gov/public

-involve/listserver.html. The NRC homepage at www.nrc.gov also offers a SUBSCRIBE link. E-mail notifications are sent to subscribers when news releases are posted to NRC's website.