NRC Staff Letter Providing Nonconcurrence Record
ML14066A443
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 03/07/2014
From: Hair C C
NRC/OGC
To: Jeffries J D, Karlin A S, Ryerson P S
Atomic Safety and Licensing Board Panel
SECY RAS
References
50-237-EA, 50-249-EA, ASLBP 14-930-01-EA-BD01, Enforcement Action, RAS 25679
Download: ML14066A443 (7)


Text

March 7, 2014 Paul S. Ryerson, Chairman Dr. Jeffrey D.E. Jeffries, Administrative Judge Atomic Safety and Licensing Board Atomic Safety and Licensing Board U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Washington, D.C. 20555 Washington, D.C. 20555 Alex S. Karlin, Administrative Judge Atomic Safety and Licensing Board U.S. Nuclear Regulatory Commission Washington, D.C. 20555

In the Matter of Exelon Generation Company, LLC Dresden Nuclear Power Station Confirmatory Order Modifying License Docket Nos. 50-237-EA and 50-249-EA ASLBP No. 14

-930-01-EA-BD01

Dear Administrative Judges,

During the oral argument in this proceeding held on March 6, 2014, the Board requested the NRC Staff to provide the Board and parties with a copy of the Non-Concurrence Process Record relating to the Staff's enforcement action in this proceeding.

The Staff has enclosed the public version of this document, which can also be accessed i n ADAMS at Accession Number ML13329A531.

The Staff notes that the public version has been redacted for attorney

-client privileged information. Respectfully submitted, /RA/ _________________________

Christopher C. Hair Counsel for the NRC Staff

Enclosures:

Non-Concurrence Process Record NCP

-2013-10 cc: Attached Service List

Non-Concurrence Process Record for NCP-2013-010 The U.S. Nuclear Regulatory Commission (NRC) strives to establish and maintain an environment that encourages all employees to promptly raise concerns and differing views without fear of reprisal and to promote methods for raising concerns that will enhance a strong Individuals are expected to discuss their views and concerns with their immediate supervisors on a regular, ongoing basis. If informal discussions do not resolve concerns, individuals have various mechanisms for expressing and having their concerns and differing views heard and considered by management. -Concurrence Process, describes the Non-Concurrence Process (NCP). http://pbadupws.nrc.gov/docs/ML0706/ML070660506.pdf The NCP allows employees to document their differing views and concerns early in the decision-making process, have them responded to, and attach them to proposed documents moving through the management approval chain. NRC Form 757, Non-Concurrence Process is used to document the process. Section A of the form includes the personal opinions, views, and concerns of an NRC employee. Section B of the form includes the personal opinions and views immediate supervisor. position and outcome. NOTE: Content in Sections A and B reflects personal opinions and views and does not represent official factual representation of the issues, nor official rationale for the agency facts, issues, and rationale for the final decision. -concurrence) is included in ADAMS Accession Number ML13184A232. Include one of the following statements: This record has been redacted prior to discretionary release to the public.

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of

) ) EXELON GENERATION COMPANY, LLC.

) Docket Nos. 50

-237-EA and 50-249-EA ) (Dresden Nuclear Power Station

) ASLBP No. 14

-930-01-EA-BD01 Confirmatory Order Modifying License)

) CERTIFICATE OF SERVICE Pursuant to 10 C.F.R § 2.305 (revised), I hereby certify that copies of the foregoing "Letter i n the Matter of Exelon Generation Company, LLC" in the above

-captioned proceeding have been served via the Electronic Information Exchange (EIE) this 7th day of March, 2014. /Signed (electronically) by/

Christopher C. Hair Counsel for the NRC Staff U.S. Nuclear Regulatory Commissio n Mail Stop O

-15 D21 Washington, DC 20555

-0001 (301) 415-2174 Christopher.Hair@nrc.gov Date of Signature: March 7 , 2014