ENS 47201
ENS Event | |
---|---|
17:00 Aug 26, 2011 | |
Title | Unanalyzed Condition Based On Seismic Activity That Potentially Exceeded Design Basis Earthquake Magnitude |
Event Description | On August 23, 2011 at 1351 hours0.0156 days <br />0.375 hours <br />0.00223 weeks <br />5.140555e-4 months <br />, North Anna Power Station experienced a seismic activity event which resulted in a loss of offsite power and automatic reactor trip of both units. At 1403 hours0.0162 days <br />0.39 hours <br />0.00232 weeks <br />5.338415e-4 months <br />, an Alert was declared, based on Shift Manager judgment, due to significant seismic activity on the site. Subsequent to the earthquake, both units were stabilized and offsite power was restored. Following the event, seismic data was retrieved from the installed monitoring system and shipped to the vendor to determine the response spectrum for the event. On August 26, 2011 at 1340 hours0.0155 days <br />0.372 hours <br />0.00222 weeks <br />5.0987e-4 months <br />, initial reviews of the data determined that the seismic activity potentially exceeded the Design Basis Earthquake magnitude value above 5 Hz. Therefore, this is reportable per 10CFR50.72(b)(3)(ii) (B) for the nuclear power plant being in an unanalyzed condition that significantly degrades plant safety.
North Anna Unit 1 is currently in Cold Shutdown with the Residual Heat Removal System providing core cooling. North Anna Unit 2 is currently in Hot Shutdown and will be taken to Cold Shutdown with the Residual Heat Removal System providing core cooling. No significant equipment damage to Safety Related system (including Class 1 Structures) has been identified through site walk-downs nor has equipment degradation been detected through plant performance and surveillance testing following the earthquake. Therefore, there is reasonable assurance that the Safety Related systems are fully functional. The Spent Fuel Pit cooling system also remains fully functional and the temperature of the Spent Fuel Pit remained unchanged during the event. The vendor will complete the analysis of the seismic data and this information will be utilized to address the long term actions following the earthquake. The licensee notified the NRC Resident Inspector.
This is an update to EN 47201 reported on 8/26/2011 where It was reported that North Anna potentially exceeded the Design Basis Earthquake (DBE) magnitude value above 5 Hz. The vibratory motion from the 5.8 magnitude earthquake were recorded in all three orientations at several locations in the plant using two types of instruments: the Engdahl scratch plates that record 12 discrete spectral accelerations between 2 and 25.4 Hz, and the Kinemetrics analog recorders that recorded time histories of the accelerations. Based on evaluation of recorded plant data, it is concluded that the Central Virginia earthquake of 8/23/2011 exceeded the spectral accelerations for the Operational Basis Earthquake (OBE) and DBE of North Anna Plant. Extensive actions are underway to inspect. evaluate, test, and repair if necessary. systems and components to ensure they are capable of performing their required functions. To date, no significant damage to safety related structures, systems or components (SSC) has been identified. The licensee notified the NRC Resident Inspector. Notified R2DO (Rich). |
Where | |
---|---|
North Anna Virginia (NRC Region 2) | |
Reporting | |
10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition | |
Time - Person (Reporting Time:+-0.62 h-0.0258 days <br />-0.00369 weeks <br />-8.49276e-4 months <br />) | |
Opened: | Page Kemp 16:23 Aug 26, 2011 |
NRC Officer: | Bill Huffman |
Last Updated: | Sep 9, 2011 |
47201 - NRC Website
Loading map... {"minzoom":false,"maxzoom":false,"mappingservice":"leaflet","width":"350px","height":"250px","centre":false,"title":"","label":"","icon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"zoom":6,"defzoom":14,"layers":["OpenStreetMap"],"image layers":[],"overlays":[],"resizable":false,"fullscreen":false,"scrollwheelzoom":true,"cluster":false,"clustermaxzoom":20,"clusterzoomonclick":true,"clustermaxradius":80,"clusterspiderfy":true,"geojson":"","clicktarget":"","imageLayers":[],"locations":[{"text":"\u003Cb\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003E\u003Ca class=\"mw-selflink selflink\"\u003EENS 47201\u003C/a\u003E - \u003Ca href=\"/North_Anna\" title=\"North Anna\"\u003ENorth Anna\u003C/a\u003E\n\u003C/p\u003E\u003C/div\u003E\u003C/b\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003EUnanalyzed Condition Based on Seismic Activity That Potentially Exceeded Design Basis Earthquake Magnitude\n\u003C/p\u003E\u003C/div\u003E","title":"ENS 47201 - North Anna\n","link":"","lat":38.06055555555555,"lon":-77.78944444444444,"icon":"/w/images/b/b0/Dominion_icon.png"}],"imageoverlays":null} | |
Unit 1 | |
---|---|
Reactor critical | Not Critical |
Scram | No |
Before | Cold Shutdown (0 %) |
After | Cold Shutdown (0 %) |
Unit 2 | |
---|---|
Reactor critical | Not Critical |
Scram | No |
Before | Hot Shutdown (0 %) |
After | Hot Shutdown (0 %) |
WEEKMONTHYEARENS 553752021-07-22T21:51:00022 July 2021 21:51:00
[Table view]10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Unanalyzed Condition of Fire Safe Shutdown Equipment ENS 514602015-10-08T01:47:0008 October 2015 01:47:00 10 CFR 50.72(b)(3)(v)(A), Loss of Safety Function - Shutdown the Reactor, 10 CFR 50.72(b)(3)(v)(B), Loss of Safety Function - Remove Residual Heat, 10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident, 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition High Energy Line Break Door Found Unlatched ENS 472012011-08-26T17:00:00026 August 2011 17:00:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Unanalyzed Condition Based on Seismic Activity That Potentially Exceeded Design Basis Earthquake Magnitude 2021-07-22T21:51:00 | |