ML15217A461

From kanterella
Revision as of 01:02, 9 July 2018 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
EN-15-022, Enforcement Notification Regarding Issuance of Final Significance Determination and Notice of Violation for Exelon Generation Company, LLC, Clinton Power Station (EA-15-064)
ML15217A461
Person / Time
Site: Clinton Constellation icon.png
Issue date: 08/05/2015
From: David Furst
NRC/OE
To:
References
EA-15-064 EN-15-022
Download: ML15217A461 (2)


Text

August 5, 2015 EN 15-022 OFFICE OF ENFORCEMENT NOTIFICATION OF SIGNIFICANT ENFORCEMENT ACTION Licensee: Exelon Generation Company, LLC EA-15-064 Clinton Power Station Docket No.: 05000461

Subject:

ISSUANCE OF FINAL SIGNIFICANCE DETERMINATION AND NOTICE OF VIOLATION This is to inform the Commission that a Notice of Violation (NOV) associated with a White Significance Determination Process finding will be issued on or about August 11, 2015, to Exelon Generation Company, LLC (licensee) as a result of an inspection at Clinton Power Station (Clinton). The White finding, an issue of low to moderate safety significance, will result

in additional NRC inspection and potentially other NRC action. The White finding involved the licensee's failure to review the suitability of application of the Division 3 Shutdown Service Water pump modifications, essential to the safety related functions of the High Pressure Core Spray system. Specifically, the licensee failed to ensure the modified pump internals would not degrade under expected operating conditions in a way that impacted the safety function. The causal evaluation determined the pump failed at the conclusion of its surveillance run on May 30, 2014, and this condition did not reveal itself until the attempted pump start on September 16, 2014. This resulted in the pump being inoperable for approximately 108 days, a period greater than the allowed limiting condition for operation outage times provided in the plant technical specifications (TS). Additionally, because the licensee was not aware of the pump's inoperability during the unit's operation cycle, the required actions of the TS were not followed. A NOV is included based on the licensee's failure to establish measures for the selection, and review for suitability of application of materials, parts, equipment, and processes that are essential to the safety-related functions of the structures, systems, and components in accordance with 10 CFR 50, Appendix B, Criterion III, "Design Control".

On June 25, 2015, a Regulatory Conference was held, during which the licensee contested the finding. After considering the additional information provided by the licensee at the conference, the staff concluded that the finding stands, and it is appropriately characterized as White. The licensee has not yet been informed of the specific nature of the enforcement action. The schedule of issuance and notification is: Mailing of Final Significance Determination August 11, 2015 Telephone Notification of Licensee August 11, 2015

The State of Illinois will be notified.

CONTACTS: Kyle Hanley, OE, (301) 415-1975 Nick Hilton, OE, (301) 415-2741 Distribution: EN-15-022, August 5, 2015 OWFN Chairman Burns Comm. Svinicki Comm. Ostendorff

Comm. Baran SECY OCA OPA OIP OWFN EDO DEDR DEDMRT OE OGC NRR OI OIG TWFN OCFO OIS RES ACRS NRO NMSS 3WFN NSIR OP Center

Regional Offices RI RII

RIII RIV

MAIL ADAMS OE staff

Electronic DISTRIBUTION: P. Holahan, OE N. Hilton, OE K. Hanley, OE OE r/f EN binder

X PUBLIC X NON-SENSITIVE

ADAMS ML15217A461 OFFICE OE:ES OE: BC (acting) NAME KHanley DFurst DATE 8/4/2015 8/5/2015 OFFICIAL RECORD COPY