05000275/FIN-2008003-01
From kanterella
Revision as of 22:04, 29 May 2018 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Finding | |
---|---|
Title | Failure to Scope Spings Into Maintenance Rule |
Description | The inspectors identified a noncited violation of 10 CFR 50.65(b) after Pacific Gas and Electric Company failed to include a radiation monitoring system in the maintenance rule scope for monitoring of maintenance effectiveness. The licensee relied on the radiation monitoring system for use in plant emergency operating procedures. The inspectors concluded that radiation monitoring system maintenance had not been effective. Between June 2006 and April 2008, twenty failures of the system had occurred. The licensee has taken corrective action to remove the radiation monitoring system from the emergency operating procedures and entered the condition into the corrective action program as Action Request A0728599. This finding is greater than minor because it is associated with the Mitigating Systems Cornerstone attribute of equipment performance and affects the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. The inspectors concluded that the finding is of very low safety significance because it did not represent a loss of system safety function, an actual loss of safety function of a single train for greater than the Technical Specification allowed outage time, or screen as potentially risk significant due to a seismic, flooding, or severe weather initiating event. This finding has a crosscutting aspect in the area of problem identification and resolution, associated with the corrective action program component, because Pacific Gas and Electric Company failed to perform an adequate extent of condition review following a similar finding described in NRC Integrated Inspection Report 05000275 and 05000323/2007003 P.1(c) |
Site: | Diablo Canyon |
---|---|
Report | IR 05000275/2008003 Section 1R12 |
Date counted | Jun 30, 2008 (2008Q2) |
Type: | NCV: Green |
cornerstone | Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | IP 71111.12 |
Inspectors (proximate) | M Brown M Peck P Elkmann J Melfi J Nadel V Gaddy |
CCA | P.2, Evaluation |
INPO aspect | PI.2 |
' | |