Enclosurequest for Additional Information [Request for Additional Information Regarding Sacramento Municipal Utility District'S Decommissioning Funding Plan Update for Rancho Seco Independent Spent Fuel Storage Installation]
ML18094A262
Person / Time
Site: 07200011
Issue date: 04/03/2018
From: Pamela Longmire
Spent Fuel Licensing Branch
To: Tallman D A
Rancho Seco Assets Power Generation, Sacramento Municipal Utility District (SMUD)
Longmire P
Shared Package
ML18094A264 List:
References
CAC 001028, EPID L-2017-FPR-0059
Download: ML18094A262 (1)


Text

Enclosure REQUEST FOR ADDITIONAL INFORMATION REGARDING SACRAMENTO MUNICIPAL UTILITY DISTRICT'S DECOMMISSIONING FUND PLAN UPDATE FOR THE RANCHO SECO NUCLEAR GENERATING STATION INDEPENDENT SPENT FUEL STORAGE INSTALLATION DOCKET NO. 72-11 Regulatory Requirement Pursuant to Title 10 of the Code of Federal Regulations (10 CFR) 72.30(c), at the time of license renewal and at intervals not to exceed 3 years, the decommissioning funding plan (DFP) required to be submitted by 10 CFR 72.30(b) must be resubmitted with adjustments as necessary to account for changes in costs and the extent of contamination. The DFP must update the information submitted with the original or prior approved plan. In addition, the DFP must also specifically consider the effect of the following events on decommissioning costs, as required by 10 CFR 72.30(c)(1)-(4): (1) spills of radioactive material producing additional residual radioactivity in onsite subsurface material, (2) facility modifications, (3) changes in authorized possession limits, and (4) actual remediation costs that exceed the previous cost estimate. Background By letter dated April 7, 2016, Sacramento Municipal Utility District (SMUD) submitted, for U.S. Nuclear Regulatory Commission (NRC) staff review and approval, a decommissioning fund plan update (DFP Update) for the independent spent fuel storage installation (ISFSI) at Rancho Seco Nuclear Generating Station (Agencywide Documents Access and Management System Accession No. ML16106A109). The NRC staff reviewed SMUD's DFP update and believes SMUD's submittal was not sufficient to meet the intent of the requirement in 72.30(c). The DFP update does not provide sufficient information to allow the NRC to determine that the events listed in 10 CFR 72.30(c)(1)-(4) have been specifically considered.

RAI 1 Provide a revised DFP that includes information on the effect on decommissioning costs, of each of the events listed in 10 CFR 72.30(c)(1)-(4): (1) spills of radioactive material producing additional residual radioactivity in onsite subsurface material, (2) facility modifications, (3) changes in authorized possession limits, and (4) actual remediation costs that exceed the previous cost estimate.