Rescheduling Radiation Protection Inspection to Occur the Week of August 11, 2003
ML032170721
Person / Time
Site: Quad Cities  Constellation icon.png
Issue date: 08/01/2003
From: Kenneth Riemer
Plant Support Branch II
To: Skolds J
Exelon Generation Co, Exelon Nuclear
References
Download: ML032170721 (4)


Text

August 1, 2003 Mr. John L. Skolds, President Exelon Nuclear Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555

Dear Mr. Skolds:

We have rescheduled a radiation protection inspection at your Quad Cities Station, Units 1 and 2, that was to occur the week of August 11, 2003, due to temporary personnel reassignments in the Plant Support Branch. This change was communicated during a telephone conversation between Mr. A. Fuhs of your staff and Mr. J. House on July 28, 2003. The radiation protection inspection (IP 71121.01 and 71122.03), which will cover access control to radiologically significant areas and the Radiological Environmental Monitoring Program, will be combined with the inspection scheduled for November 17, 2003, and will begin November 12, 2003. If you have any questions concerning this information, please contact J. House of my staff at (630) 829-9824.

In accordance with 10 CFR 2.790 of the NRCs "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Kenneth R. Riemer, Chief Plant Support Branch Division of Reactor Safety Docket Nos. 50-254; 50-265 License Nos. DPR-29; DPR-30 See Attached Distribution

Mr. John L. Skolds, President Exelon Nuclear Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555

Dear Mr. Skolds:

We have rescheduled a radiation protection inspection at your Quad Cities Station, Units 1 and 2, that was to occur the week of August 11, 2003, due to temporary personnel reassignments in the Plant Support Branch. This change was communicated during a telephone conversation between Mr. A. Fuhs of your staff and Mr. J. House on July 28, 2003. The radiation protection inspection (IP 71121.01 and 71122.03), which will cover access control to radiologically significant areas and the Radiological Environmental Monitoring Program, will be combined with the inspection scheduled for November 17, 2003, and will begin November 12, 2003. If you have any questions concerning this information, please contact J. House of my staff at (630) 829-9824.

In accordance with 10 CFR 2.790 of the NRCs "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Kenneth R. Riemer, Chief Plant Support Branch Division of Reactor Safety Docket Nos. 50-254; 50-265 License Nos. DPR-29; DPR-30 See Attached Distribution DOCUMENT NAME: G:\\DRS\\ML032170721.wpd To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RIII RIII N RIII D

NAME JHouse:sd MRing KRiemer DATE 08/01/03 08/01/03 08/01/03 OFFICIAL RECORD COPY

J. Skolds cc:

Site Vice President - Quad Cities Nuclear Power Station Quad Cities Nuclear Power Station Plant Manager Regulatory Assurance Manager - Quad Cities Chief Operating Officer Senior Vice President - Nuclear Services Senior Vice President - Mid-West Regional Operating Group Vice President - Mid-West Operations Support Vice President - Licensing and Regulatory Affairs Director Licensing - Mid-West Regional Operating Group Manager Licensing - Dresden and Quad Cities Senior Counsel, Nuclear, Mid-West Regional Operating Group Document Control Desk - Licensing Vice President - Law and Regulatory Affairs Mid American Energy Company M. Aguilar, Assistant Attorney General Illinois Department of Nuclear Safety State Liaison Officer, State of Illinois State Liaison Officer, State of Iowa Chairman, Illinois Commerce Commission D. Tubbs, Manager of Nuclear MidAmerican Energy Company

J. Skolds cc:

Site Vice President - Quad Cities Nuclear Power Station Quad Cities Nuclear Power Station Plant Manager Regulatory Assurance Manager - Quad Cities Chief Operating Officer Senior Vice President - Nuclear Services Senior Vice President - Mid-West Regional Operating Group Vice President - Mid-West Operations Support Vice President - Licensing and Regulatory Affairs Director Licensing - Mid-West Regional Operating Group Manager Licensing - Dresden and Quad Cities Senior Counsel, Nuclear, Mid-West Regional Operating Group Document Control Desk - Licensing Vice President - Law and Regulatory Affairs Mid American Energy Company M. Aguilar, Assistant Attorney General Illinois Department of Nuclear Safety State Liaison Officer, State of Illinois State Liaison Officer, State of Iowa Chairman, Illinois Commerce Commission D. Tubbs, Manager of Nuclear MidAmerican Energy Company ADAMS Distribution:

AJM DFT CFL RidsNrrDipmIipb GEG HBC KKB DRPIII DRSIII PLB1 JRK1