December 22, 2010 MEMORANDUM TO: Sandra Wastler, Chief Materials, Waste and International Security Branch Division of Security Policy Office of Nuclear Security and Incident Response FROM:
Robert Johnson, Acting Chief /RA/
Licensing Branch Division of Spent Fuel Storage and Transportation Office of Nuclear Material Safety and Safeguards
SUBJECT:
TECHNICAL ASSISTANCE REQUEST - REVIEW OF BIG ROCK POINT RESPONSE AND EXEMPTION REQUEST TO THE REVISED 10 CFR 73.55 RULE (TAC NO. L24502)
The Division of Spent Fuel Storage and Transportation (SFST), Office of Nuclear Material Safety and Safeguards (NMSS), requests technical assistance from the Division of Security Policy (DSP), Nuclear Security and Incident Response (NSIR), for the completion of the following project:
PROJECT: Security Evaluation of Big Rock Points response and exemption request to the revised 10 CFR 73.55 rule.
DOCKET NOS: 50-155,72-043 TAC NO: L24502 LICENSE NO: DPR-6 REQUESTED ACTION: NMSS/SFST requests that NSIR/DSP review Big Rock Points response and exemption request to the revised 10 CFR 73.55 rule. (November 30, 2010, cover letter enclosed; the SUNSI attachments are referenced in ADAMS, (ML103540154)). Based on the results of your review, prepare a Security Evaluation documenting the staffs reasons for approving or denying the proposed changes.
To facilitate this request, we ask that you respond by June 30, 2011. Should any additional information be needed from the applicant to support your review, we ask that you transmit a draft Request for Additional Information to us by May 1, 2011. The applicant will normally be allowed two months to provide a response. The SFST project manager will keep your staff informed of any schedule changes.
Please provide the information requested below and return a completed copy to the SFST Project Manager designated below.
Name of NSIR/DSP assigned Reviewer: _________________________________
NSIR/DSP Project Completion Date: _________________________________
NSIR/DSP Branch Chief Signature: _________________________________
Contact:
Pamela Longmire, Ph.D. (301) 492-3562 The above TAC No. should be referenced in future correspondence related to this request and in the Human Resources Management System for recording staff time expended on this effort.
Enclosure:
As stated
Please provide the information requested below and return a completed copy to the SFST Project Manager designated below.
Name of NSIR/DSP assigned Reviewer: _________________________________
NSIR/DSP Project Completion Date: _________________________________
NSIR/DSP Branch Chief Signature: _________________________________
Contact:
Pamela Longmire, Ph.D. (301) 492-3562 The above TAC No. should be referenced in future correspondence related to this request and in the Human Resources Management System for recording staff time expended on this effort.
Enclosure:
As stated Distribution: (w/o attachment)
SFST r/f BWhite, RWharton ADAMS Package: ML103610067 File Location : G:\\SFST\\Big Rock Point\\BRP TAR 73pt55 eval.docx OFC SFST SFST SFST NAME WWheatley PLongmire RJohnson DATE 12/ 22 /2010 12/20/2010 12/ 21 /2010 OFFICIAL RECORD COPY