Other: L-MT-12-092, Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), L-MT-13-016, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), L-MT-13-080, Monticellos First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), L-MT-14-015, Plants Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), L-MT-14-072, Plants Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), L-MT-15-005, Plants Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), L-MT-15-046, Plant Completion of Reqiuired Action by NRC Order EA-12-051, Reliable Spent Fuel Pool Instrumentation, ML14290A367, ML15072A098
|
MONTHYEARML12054A6792012-03-12012 March 2012 Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation Project stage: Approval L-MT-12-092, Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2012-10-29029 October 2012 Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other L-MT-13-016, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2013-02-28028 February 2013 Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML13176A3312013-06-0707 June 2013 NRR E-mail Capture - Monticello Nuclear Generating Plant - Requests for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation Project stage: RAI L-MT-13-058, Responses to Requests for Additional Information Regarding Monticello Overall Integrated Plan Submitted in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrument2013-07-12012 July 2013 Responses to Requests for Additional Information Regarding Monticello Overall Integrated Plan Submitted in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentati Project stage: Response to RAI L-MT-13-080, Monticellos First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2013-08-28028 August 2013 Monticellos First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML13275A1872013-10-28028 October 2013 Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051 Project stage: RAI L-MT-14-015, Plants Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2014-02-28028 February 2014 Plants Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other L-MT-14-072, Plants Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2014-08-28028 August 2014 Plants Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML14290A3672014-10-22022 October 2014 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Order EA-12-049 and EA-12-051 Project stage: Other L-MT-15-005, Plants Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2015-02-24024 February 2015 Plants Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML15072A0982015-03-17017 March 2015 Report for the Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other L-MT-15-046, Plant Completion of Reqiuired Action by NRC Order EA-12-051, Reliable Spent Fuel Pool Instrumentation2015-07-28028 July 2015 Plant Completion of Reqiuired Action by NRC Order EA-12-051, Reliable Spent Fuel Pool Instrumentation Project stage: Other 2013-08-28
[Table View] |
Text
Xcel Energy
- October 29,2012 Monticello Nuclear Generating Plant 2807 W County Road 75 Monticello, MN 55362 L-MT-12-092 10 CFR 2.202 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Monticello Nuclear Generating Plant Docket No. 50-263 Renewed Facility Operating License No. DPR-22 Initial Status Report in Response to March 12, 2012 Commission Order Modifvinq Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation lOrder Number EA-12-051)
References:
- 1. NRC Order EA-12-051, "Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," dated March 12,2012 (Accession No. ML12054A679).
- 2. NRC Interim Staff Guidance JLD-ISG-2012-03, "Compliance with Order EA-12-051, Reliable Spent Fuel Pool Instrumentation," Revision 0, dated August 29, 2012 (Accession No. ML12221A339).
On March 12, 2012, the NRC staff issued Order EA-12-051, "Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," (Reference
- 1) to all NRC power reactor licensees and holders of construction permits in active or deferred status. The NRC order was immediately effective and directs Northern States Power Company (NSPM), a Minnesota corporation, d/b/a Xcel Energy, to have a reliable indication of the water level in the spent fuel storage pool for Monticello Nuclear Generating Plant (MNGP). Specific requirements are outlined in Attachment 2 of Reference 1.
Reference 1 requires submission of an initial status report 60 days following issuance of the final interim staff guidance. The final Interim Staff Guidance (ISG) JLD-ISG-2012-
Document Control Desk Page 2 03, Revision 0, "Compliance with Order EA-12-051, Reliable Spent Fuel Pool Instrumentation," (Reference 2) was issued August 30, 2012. The purpose of this letter is to provide the initial status report pursuant to Section IV, Condition C.2, of Reference 1 within 60 days following issuance of Reference 2. This report confirms NSPM has received Reference 2 and is in the process of evaluating the guidance for the purpose of providing a reliable indication of the water level in the MNGP spent fuel storage pool as described in Attachment 2 of Reference 1.
Major activities completed during this reporting period:
e Resources are being identified and project plans initiated, including development of milestones, to assure compliance with Reference 1.
Planned activities for the next six months:
Development and submittal of the overall integrated plan.
Technical difficulties encountered that could affect the ability to provide the licensee's February 28, 201 3, submittal:
None at this time.
Project milestones schedule through completion of installation and testing:
A project milestones schedule will be provided with the overall integrated plan.
Implementation of the order will be completed for MNGP prior to startup from Refueling Outage (RFO) R27 (Spring 201 5).
If there are any questions or if additional information is needed, please contact Ms.
Jennie Eckholt, Licensing Engineer, at 612-330-5788.
Summarv of Commitments This letter proposes no new commitments and no revisions to existing commitments.
Document Control Desk Page 3 I declare under penalty of perjury that the foregoing is true and correct.
Executed on 0ctober & 201 2.
John C. Grubb Plant Manager,, ru/
onticello Nuclear Generating Plant Northern States Power Company - Minnesota cc:
Director, Office of Nuclear Reactor Regulation Administrator, Region Ill, USNRC NRR Project Manager, Monticello, USNRC Resident Inspector, Monticello, USNRC Ms. Lisa M. Regner, NRRIJLDIPMB, NRC Mr. Blake A. Purnell, NRRIJLDIPMB, NRC Mr. Steven R. Jones, NRRIDSSISBPB, NRC