Pacific Gas and Electric C:ompany.r-May 5, 2017 PG&E Letter DCL-17-042 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Diablo Canyon Units 1 and 2 Paula Gerfen Station llirector 10 CFR Part 55 lliablo Canyon Power Plant Mail code 1 04/5/502 P.O. Box 56 Avila Beach, CA 93424 805.545.4596 Internal: 691.4596 Fax: 805.545.4234 Response to NRC Regulatory Issue Summary 2017-03, Preparation and Scheduling of Operator Licensing Examinations
Dear Commissioners and Staff:
Pursuant to the request for voluntary information identified in NRC Regulatory Issue Summary 2017-03, a completed NRC Form 536, "Operator Licensing Examination Data," is enclosed. This completed form provides Proposed Examination Preparation Schedules and Initial Operator License Examination data for years 2019 through 2022.
Pacific Gas and Electric Company makes no new or revised regulatory commitments (as defined by NEI 99-04) in this letter.
If you have any questions, please contact Mr. Bobby Simpson, Operations Training Manager, at (805) 545-3576.
8]2 Paula~~7f-bnsm/4540 Enclosure cc/enc: John M. Becerra, Simulator and Exam Support Supervisor Kriss M. Kennedy, NRC Region IV Administrator Christopher W. Newport, NRC Senior Resident Inspector Bobby Simpson, Operations Training Manager Balwant K. Singal, NRC Senior Project Manager A
member of the STARS Alliance Callaway
- Diablo Canyon
- Palo Verde
- Wolf Creek
NRC Form 536, Enclosure PG&E Letter DCL-17-042 "Operator Licensing Examination Data"
NRC FORM 536 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB: NO. 3150-0131 EXPIRES: 10/31/2017 (05-2016)
~~~
Estimated burden per response to comply v~th this voluntary information collection request: 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. This OPERATOR LICENSING infonnation collection is used to plan budgets and resources for operator examinations.
Send tJ comments regarding burden estimate to the FOIA, Privacy, and Information Collections Branch (T-5
!i
~
F53), U.S. Nuclear Regulatory Commission, Washington, DC20555-0001, or by e-mail to l;;.
'1~:
EXAMINATION DATA
~...,~....,_,.,
lnfocollects.Resource@nrc.gov, and to the Desk Officer, Office of lnfonnation and Regulatory Affairs,
"/.
~
NEOB-10202, (3150-0131), Office of Management and Budget, Washington, DC 20503. If a means
'~--?
~0 used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the infonnation collection.
FACILITY NRC REGION Diablo Canyon Power Plant IV A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY2019 CY2020 CY2021 CY2022 ESTIMATED NUMBER OF LICENSEE-PREPARED 0
2 1
1 I
EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED 0
0 0
0 EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER CY20I9 CY2020 CY2021 CY2022 NUMBER OF REACTOR I I & 8 8
8 8
OPERATORS NUMBER OF SENIOR REACTOR 5&8 8
8 8
OPERATORS-INSTANT NUMBER OF SENIOR REACTOR 0&0 0
0 0
OPERATORS-UPGRADE NUMBER OF SENIOR REACTOR 0&0 0
0 0
OPERATORS-LIMITED PROPOSED DATES PRIMARY DATE l/I4/19 & 12/16/19 12/14/20 12/13/21 12/12/22 ALTERNATE DATE 1/28/19 & 12/09/19 12/07/20 12/06/21 12/05/22 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE PROPOSED CY N/A CY N/A NUMBER MARCH SEPTEMBER MARCH SEPTEMBER ESTIMATED NUMBER OF CANDIDATES NRC FORM 536 (05-2016)