Forwards IE Insp Rept 70-1151/78-17 on 781211-781213.No Noncompliance Noted
ML19259B245
Person / Time
Site: Westinghouse
Issue date: 12/22/1978
From: Sutherland J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Damore M
WESTINGHOUSE ELECTRIC COMPANY, DIV OF CBS CORP.
Shared Package
ML19259B244 List:
References
NUDOCS 7901180090
Download: ML19259B245 (2)


Text

.

  • M4 UNITED STATES 9[o,,

NUCLEAR REGULATORY COMMISSION 2

o R EGloN il 5

.t 101 M ARIETTA STREET.N.VI.

k 8

ATLANTA, GEORGI A 3030;

\\.....+

DEC 2 21978 In Reply Refer To:

RII:GPC 70-1151/78-17 Westinghouse Electric Corporation ATTN:

Mr. M. D' Amore, Manager Columbia Plant Nuclear Fuel Division

~

Drawer R Columbia, South Carolina 29205 Gentlemen:

This refers to the inspection conducted by Mr. G. P. Coryell of this office on December 11-13, 1978, of activities authorized by NRC License No. SNM-1107 for the Columbia Nuclear Fuel facility, and to the discussioin of our findings held with Mr. W. J. Hartnett at the conclusion of the inspection.

Areas examined during the inspection and our findings are discussed in the enclosed inspection report. Within these areas, the inspection consisted of selective examinations of procedures and representative records, interviews with personnel, and observations by the inspector.

Within the scope of this inspection, no items of noncompliance were disclosed.

We have examined actions you have taken with regard to previously identified enforcement matters. These are discussed in the enclosed inspection report.

In accordance with Section 2.790 of the NRC's " Rules of Practice", Part 2, Title 10, Code of Federal Regulations, a copy of this letter and the enclosed inspection report will be placed in the NRC's Public Document Room. If this report contains any information that you (or your contractor) believe to be proprietary, it is necessary that you make a written application within 20 days to this office to withhold such information from public disclosure.

Any such application must include a full statement of the reascas on the basis of which it is claimed that the information is proprietary, and should be prepared so that proprietary information identified in the application is contained in a separate part of the. document. If we do not hear from you in this regard within the specified period, the report will be placed in the Public Document Room.

7901180090

DEC 2 21978 Westinghouse Electric Corporation Should you have any questions concerning this letter, we vill be glad to discuss them with you.

Sincerely,

)K 4

i

. Tack T. Sutherland, Chief Fuel Facility and Materials Safety Branch

Enclosure:

Inspection Report No. 70-1151/78-17