Forwards IE Insp Rept 50-309/79-02 on 790306-09 & Notice of Violation
ML19259C038
Person / Time
Site: Maine Yankee
Issue date: 03/29/1979
From: Brunner E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Groce R
Maine Yankee
Shared Package
ML19259C036 List:
References
NUDOCS 7906120244
Download: ML19259C038 (2)


See also: IR 05000309/1979002

Text

.9

.

  1. "%

UNITED STATES

4

NUCLEAR REGULATORY COMMisslON

yg)P.

j

E

REGION 1

$

,:.f

$31 PARK AVENUE

of

g

x No or pauss:A PENNSYt.VANI A 19406

.....

Docket No. 50-309

Maine Yankee Atomic Power Company

ATTN: Mr. Robert H. Grace

Licensing Engineer

20 Turnpike Road

Westborough, Massachusetts 01581

Gentlemen:

Subject:

Inspection 50-309/79-02

This refers to the inspection conducted by Mr. W. Baunack of this office

on March 6-9, 1979, at Maine Yankee Atomic Power Station, Wiscasset,

Maine, of activities authorized by NRC License No. DPR-36 and to the

discussions of our findings held by Mr. W. Baunack with Mr. Wood of your

staff at the conclusion of the inspection.

Areas examined during this inspection are described in the Office of

Inspection and Enforcement Inspection Report which is enclosed with this

letter. Within these areas, the inspection consisted of selective

examinations of procedures and representative records, interviews with

personnel, and observations by the inspector..

Our inspector also verified the steps you have taken to correct the item

of noncompliance brought to your attention in a letter dated Septembqr

29, 1978. We have no further questions regarding your action at this

time.

Based on the results of this inspection, it appears that one of your

activities was not conducted in full ccmpliance with NRC requirements,

as set forth in the Notice of Violation, enclosed herewith as Appendix

A.

This item of noncompliance has been categorized into the levels as

described in our correspondence to you dated December 31, 1974. This

notice is sent to you pursuant to the provisions of Section 2.201 of the

NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regulations.

Section 2.201 requires you to submit to this office, within twenty (20)

days of your receipt of this notice, a written statement or explanation

in reply includ M g:

(1) corrective steps which have been taken by you

and the results achieved; (2) corrective steps which will be taken to

avoid further items of noncompliance; and (3) the date when full compliance

will be achieved. We wish to emphasize that you should address the

79 0612 o ovy

2284

185

..

-

Maine Yankee Atomic Power Company

2

tiAR 2 9 ISIS

citation, not the examples listed in that we are primarily concerned

about the implementation of your administrative controls that permitted

them to occur.

Consequently, in your reply, you should describe in

particular, those actions taken or planned to improve the effectiveness

of your administrative control systems.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part

2, Title 10, Code of Federal Regulations, a copy of this letter and the

enclosures will be placed in the NRC's Public Document Room.

If this

report contains any information that you (or your contractor) believe to

be proprietary, it is necessary that you make a written application

within 20 days to this office to withhold such information from public

disclosure. Any such 7pplication must be accompanied by an affidavit

executed by the owner of the information, which identifies the document

or part sought to be withheld, and which contains a statement of reasons

which addresses with specificity the items which will be considered by

the Commission as listed in subparagraph (b) (4) of Section 2.790.

The

information sought to be withheld shall be incorporated as far as possible

into a separate part of the affidavit.

If we do not hear from you in

this regard within the specified period, the report will be placed in

the Public Document Room.

Should you have any questions concerning this inspection, we will be

pleased to discuss them with you.

Sincerely,

f

_na

=

Eldb

J. Brunner, Chief

Reac or Operations and Nuclear

Support Branch

Enclosures:

1.

Appendix A, Notice of Violation

2.

Office of Inspection and Enforcement Inspection Report Number

50-309/79-02

cc w/encls:

E. Wood, Plant Superintendent

E. W. Thurlow. President

4