ML20002A825

From kanterella
Revision as of 16:00, 23 December 2024 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
IE Insp Repts 50-445/80-20 & 50-446/80-20 During Sept 1980. Noncompliance Noted:Unsuitable Weld Surface & Incorrect Design of Pressurizer Spray Sys Control Valve Piping
ML20002A825
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 10/20/1980
From: Crossman W, Renee Taylor
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20002A816 List:
References
50-445-80-20, 50-446-80-20, NUDOCS 8011210631
Download: ML20002A825 (7)


See also: IR 05000445/1980020

Text

1

.

.

,

.

)

-

V

U. S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEFINT

REGION IV

.

Report No. 50-445/80-20; 50-446/80 m

Docket No. 50-445; 50-446

Category A2

Licensee: Texas Utilities Generating Company

2001 Bryan Tower

Dallas, Texas 75201

Facility Name:

Comanche Peak, Units 1 and 2

Inspection at: Comanche Peak Steam Electric Station, Glen Rose, Texas

Inspection conducted: September 1980

Inspector:

  1. 1 EL/

A

R. V.' faylor[ Resident Reactor Inspector, Projects Section

Approved:

-

/d/zc//o

W. A. Crossman, Chief, Projects Section

Date

Inspection Summary:

Inspection during September 1980 (Report No. 50-445/80-20; 50-446/80-20)

Areas Inspected: Routine, announced inspection by the Resident Reactor

Inspector (RRI), with limited support by two Regional IE inspectors, in-

ciuding general site tours; piping, electrical and instrumentation, installa-

tion activities; protection of installed and uninstalled equipment and

pipe supports and restraints. The inspection involved ninety-two inspector

hours by the RRI and four hours by two Regional IE inspectors.

Results:

No items of noncompliance were identified in five of the areas.

One item of noncompliance and a deviation (infraction - unsuitable weld

surface as required by magnetic particle test procedures

paragraph 6;

deviation - incorrect design of pressuri::er spray system control valve

piping

paragraph 5) were identified in two other areas.

801121oggy.

.

.

DETAILS

1.

Persons Contacted

Principal Licensee Employees

  • R. B. Clements, TUGCO, Vice-President, Nuclear Operations
  • D. N. Chapman, TUGCO, Quality Assurance Manager
  • R. G. Tolson, TUGCO, Site Quality Assurance Supervisor

Other Persons

J. V. Hawkins, Brown & Root, Project Quality Assurance Manager

D. C. Frankum, Brown & Root, Construct ion Project Mangager

The RRI also interviewed other lice de and Brown & Root employees

during the inspection period including both craft labor and QA/QC

personnel.

  • Denotes those person:. with whom the RRI held on-site management

meetings during the inspection period.

2.

Site Tours

The RRI toured the safety-related plant areas several times weekly

during the inspection period to observe the general progress of

construction and the p ractices involved. Four of the tours were

accomplished during portions of the second shift where the main

activity continues to be installation of electrical cables and the

application of protective coatings.

No items of noncompliance or deviations were identified.

3.

Protection of Major Installed Equipment

The RRI observed that the Reactor Vessel Internals (core support

structure) were partially installed in the Unit I vessel as part

of the final alignment nachining operation. The internals and

the vessel were well covered and protected from any construction

debris.

The Unit 2 Reactor Vessel continued to be protected during

periods when personnel had to enter the vessel for coolant pipe

welding and weld inspection.

The Unit 2 internals remain in their storage enclosures near a

facility warehouse. The RRI observed tba.*. randomly selected

electric prime sovers for. pumps have Ute.c space heaters energized

as have the actors associated with motor operated valves. The

safety-related switchgear and motor control centers either have

their space heaters energized or have large light bulbs installed

to keep them dry.

The control room panels and boards were maintained

in an air-conditioned environment during the period to preclude heat

damage to the electronic components.

l

\\

No items of noncompliance or deviations were identified.

]

l

2

i

I

,

.

.

4

Storage of Uninstalled Components

The RRI toured the warehouses and outdoor laydown areas during

the inspection period. All components observed, including a

substantial number of prefabricated pipe spools and cable reels,

appeared to be well cared for in accordance with normal industry

practice and the recommendations of the various suppliers of

major components, with_one exception. The RRI noted in touring

an outdoor storage area what appeared to be spent fuel storage

racks identified by an attached sign as "NON-Q" (not within the

scope of the licensee's quality assurance program). Also the

lay-down positions of some of the rack modules were such that

water might collect in some areas in the event of rain.

The RRI reviewed the files of the on-site vendor coordination

and found that the racks had been furnished by Westinghouse as

Seismic I components as indicated by the FSAR Section 17.2 and

that there was a Westinghouse quality release document on file.

The RRI initiated a discussion with licensee QA personnel and

was informed that they were aware of the problem and that a

'

Nonconformance Report had been initiated but not yet finalized.

This situation will be considered to be an unresolved item pending

completion of the Nonconformance Report and whatever actions are

taken to rectify the matter.

5.

Safetv-Related Piping Installation and Welding

The RRI made several general observations of the handling practices

for piping components during the inspection period both in the

on-site fabrication shop and within the sain plant buildings. The

practices were found to be consistent with the construction practices

outlined in Construction Procedure 35-1195-CPM 6.9 which in turn are

consistent with the Project Specification MS-100 and good industry

prac ice.

The RRI observed, during a portion of one of the tours, that the

installation and welding of a portion of the pressurizer spray

piping had evolved to a point where the final layout configuration

of this subsystem of the reactor coolant system was evident. The

RRI obtained the pertinent isometric drawings. for the subsystem

and verified that the piping was installed essentially as shown.

The design layout, however, was found not to match the commitments

of Section 5.1 of the FSAR in that Note 2 of Figure 5.1-1 had not

been achieved. This note requires that pressurizer spray control

valves be located a sinimum of ten feet below the top of the pressur-

1:er while the isometric drawings indicate that the two valves are

actually located two feet eleven inches and one foot four inches,

respectively above -he top of the pressurizer.

,

This-is considered to be a deviation to the FSAR commitments.

3

.

-

.

.

.

The RRI observed the following welds being made during the inspection

period:

Weld No.

Isometric

Filler Ht.

Welder (s)

Procedure

Process

FW-4

AF-2-SB-003 87401

BPK

11321

GTAW

V-7-12

SW-1-SB-003 762550

BWP

88025

GTAW

FW-5

RC-2-520-001 434788

ARN-BRS-AFP

99028

GTAW (Machine)

FW-1

RH-1-RB-001 746100

AEN

88021

GTAW

The RRI verified that the weld filler setals being utilized in the

above welds were certified by the suppliers via certified Material

Test Reports as meeting the applicable requirements of ASME Section II.

The welders and weld procedures noted were verified to have been properly

qualified in accordance with ASME Section IX.

The RRI also examined the radiographs of the following velds for

compliance to the requirements of ASME section III for veld quality

and Section V for the quality of the radiographs themselves.

Weld No.

Isometric

Line No.

W-16

RC-2-RB-073

4-RC-2-091-2501R1

FW-16A

CS-1-RB-028

2-CS-1-112-1501R1

W-4

CS-2-RB-042

3-CS-2-235-2501R1

FW-14

SI-1-RB-017

6-SI-1-046-2501R1

FW-7A

CS-1-RB-028-

' 2-CS-1-112-2501R1 ~

FW-7

SI-1-RB-037

10-SI-1-179-2501R1

W-13

SI-2-RB-042

2-SI-2-036-2501R1

FW-11A

RC-1-RB-006

6-RC-1-070-2501R1

W-19

FW-2-SB-029

6-FW-2-097-1303

Except as noted abeve, no items of noncompliance or deviations were

identified.

6.

Piping System Supports and Restraints

The RRI initiated an inspection of a group of some one hundred

piping system soment restraints that had been fabricated by Chicago

Bridge & Iron Co. under Brown & Root (acting as a purchasing agent

for the licensee) subcontract 35-1195-0585 and shipped to the site

complete, except for sandblasting and painting.

The inspection was initiated as a result of an investigation of

allegations received by Region IV as documented in Inspection

Report 50-445/80-22; 50-446/80-20. The allegation essentially

stated that some of the weld surfaces of the fabrications were such

that a meaningful magnetic particle inspection within the requirements

of ASME Section III, subsection NF could not have been done as

certified to by the subcontractor.

4

l

. -. _ , .-

.

. _ _ -

_ . _ - . -

. - - . - . - - - - - .

.

,

i

,

,

1

,

a

A secondary considerati c csatained within the allegation, although

not specifically stated, was that the Authorized Nuclear Inspector

'

assigned to the facility was derelict -in that the fabrica tion had

been stamped and certified as having met the Code requirements.

'

The RRI, with the assistance of two NRC inspectors specialized in

>

weld inspections and nondestructive examination techniques, performed

a magnetic parti:le and visual examination of selected portions of

j

the welds of four of the fabrications using the Chicago Bridge &

Iron procedures. Several of the selected areas examined revealed

.

indications that could only be resolved by surface removal of the

. welds, thus. substantiating the specific allegation. Tt.e secondary

allegation referred to above was effectively refuted when the RRI

found that the magnetic particle inspection was required by the

i

.

j

Architect / Engineer as a supplemental addition beyond the require-

ments of the ASME Code. Subsection NA of the Code specifically

' excludes the Authorized Nuclear Inspector from taking responsibility

'

for requirements imposed by a designer that are in excess of the Code

i

requirements. The Code requirement was for a visual examination

only oflthese components s'nd each of the welds examined by the NRC

personnel appeared to satisfy the Code stated accept 2nce criteria.

+

}

The licensee was informed .of the NRC findings informally on September

.

l

19, 1980, and formally by a Region IV letter dated September 24, 1980.

'

i

The licensee placed a QC hold on all of the components and has

a

initiated a' reinspection program involving an identified one hundred

l

'ive units received under the order.

':

-

e

The RRI also became aware of another substantial group of:large

'-

'

i

fabrications used as pipe whip restraints that were fabricated by

,.

Chicago Bridge 86 Iron under ancther subcontract and has initiated

!

an inspection of these that is not complete.

7.

Electrical' Installation Activites

4

The RRI made a number of observations of electrical cable pulling

operations during the period. The RRI observed the activities of

'

4

'esch of the six cable pulling crews one or more times during the.

'

period in order to ascertain whether they were working within the

parameters of the site installation procedures and good practices,

The RRI alo observed the activities of the QA/QC personnel assigned

i

to monitor the pulling crews. The RRI found both groups (craft and

F

QA/QC) to work consistently within their respective procedures,

[

EEI-7,and QE-QP-11.3-26. The RRI also inspected randomly selected

j

cable tray segments in Unit 1 Safeguards area for freedom from cable

,

i

damaging burrs and excessive debris. The selected segments were

found to be in a satisfactory condition for cable pulling.

,

!

.

The RRI examined the wiring within the 118 VAC Distribution Panels

i

.shown~on FSAR Figure 3.3-15 and identified as IPCI thru IPC4.

It

r

was found that from two to four nonsafety cables entered each panel-

,

i

-

-

5

u-

- .

. , 2,

- , _ . - , _

_

.

.

.,

-

_. .

. ..

.

.

_

-. .

_

. - _.

_ __

_ _ _ .

._

.

.

,

.

along with several safety-related cables. Within the panel, the

'

safety and nonsafety cables .were tightly tied together which appears

j

to be contrary to commitments of the FSAR to maintain a six inch space

between safety and nonsafety cables within panels.

Reference to the

above FSAR Figure revealed that safety and nonsafety cables were

'

shown and that the nonsafety cable was to be landed on circuit breakers

assembled among the safety-related breakers which would make the six

inch spacing nearly impossible regardless of cable routing techniques.

The same Figure also shows the nonsafety cabling being powered off a

'

safety bus with no other means than a circuit breaker of an over-current

type to serve as isolation. This situation appears to violate the

recommendations of Regulatory Guide 1.75.

It appears that the nonsafety

1

cables should be designated as associated safety-related cables and

given segregated routing through the cable raceway system.

Since the issue is clearly shown on the referenced FSAR Figure and

,

since the electrical / instrument wiring scheme is still under active

'

review by NRR, this matter will be considered to be an unresolved

ites rather than a deviation subject to either a FSAR revision or

,

specific approval by NRR of the as-built design.

"

8.

Instrument Installation Activities

The RRI observed during the inspection period that various instruments

are being placed on their supports throughout the Unit 1 and Common

Plant areas. The instruments observed were noted to be covered with

wooden boxes wired in place for the purposes aof physical-protection.

Where the-instrument' impulse tubing has not been connected ^to'the

instrument, the ports have been capped to protect from the entrance

of debris, all considered to be good industry practices.

The RRI continued to examine the engineer's drawing in the electrical

,

and instrument areas to establish whether all safety-related devices

and circuits have been identified and to also develop the IE inspection

plan. The RRI noted the Engineer's Instsament Tabulation List does

not appear to address those safety-related devices associated with

the heating and ventilation controls as being within the QA/QC scope

even though they are connected with safety-related cabling to safety-

_

related control circuits. - The RRI discussed this matter with cognizant

j

engineering personnel and was informed that the instrument list was

under active review and would be corrected in a timely manner.

No items of noncompliance or deviations were identified;

,

,

f

9.

Unresolved Items

Unresolved items are satters about which more Laformation is required

in order to ascertain whether they 'are acceptable items, items of

noncompliance, or deviations.

Unresolved items disclosed during the

inspection are discussed in paragraphs 4 and 7 and will, in future

inspection reports, be referred to as:

,

t

l

i

l

6

j

..

a

-

.

.

.

_

-.

--.

. -

-

-.

-. . .

.

-

-

_ _ _

-

-

. . - .

.

.-

.

.

.

a.

50-445/80-20; 50-446/80-20 Spent Feel Storage Racks

b .~ 50-445/80-20; 50-446/80-20 Design of the AC Instr'unent

Distribution Panels

1

'

10.

Manasement Interviews-

The RRI set with one or more of the. persons identified in paragraph I

on September 2, 3, 5, 12, 15, 19, and 24, 1980, to discuss inspection

findings and the licensee's actions and positions.

.

!

a

5

.

I

'

T

t

7

- .-

-

.

.

~ -.-

-.

.

.