ENCLOSURE 1 NOTICE OF VIOLATION Virginia Electric and Power Company Docket No. 50-339 North Anna Unit 2 License No. NPF-7 During an NRC inspection conducted on December 19, 1993 - January 21, 1994, a violation of NRC requirements was identified.
In accordance with the " General Statement of Policy and Procedure for NRC Enforcement Actions," 10 CFR Part 2, Appendix C, the violation is listed below:
10 CFR 50.55a(g) and TS 3.4.10.1 require that American Society of Mechanical Engineers (ASME) Code Class 1, 2 and 3 components be subject to inservice inspection requirements delineated in Section XI of the i
ASME Boiler and Pressure Vessel Code.
Section XI of the ASME Code paragraph IWA-5250, 1986 Edition, requires that leakage detected at bolted connections during pressure tests be evaluated by removing the bolting and performing a VT-3 visual examination.
Contrary to the above, on January 6, 1994, it was determined that leakage detected at seven bolted connections during pressure tests on September 29, October 3, and October 6, 1993, was not evaluated by performing VT-3 visual examinations with the bolting removed.
This is a Severity Level IV violation (Supplement I).
Pursuant to the provisions of 10 CFR 2.201, Virginia Electric and Power Company is hereby required to submit a written statement or explanation to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, D.C. 20555 with a copy to the Regional Administrator, Region II, and a copy to the NRC Resident Inspector at the facility that is the subject of this Notice,_
within 30 days of the date of the letter transmitting this Notice of Violation (Notice).
This reply should be clearly marked as a " Reply to a Notice of l
Violation" and should include for each violation:
(1) the reason for the violation, or, if contested, the basis for disputing the violation, (2) the i
corrective steps that have been taken and the results achieved, (3) the corrective steps that will be taken to avoid further violations, and (4) the date when full compliance will be achieved.
If an adequate reply is not received within the time specified 4.t this Notice, an order or demand for
)
information may be issued as to why the license should not be modified, j
suspended, or revoked, or why such other action as may be proper should not be taken. Where good cause is shown, consideration will be given to extending the response tima Dated at Atlanta, Georgia this 17th day of February, 1994 9405230070 940217 PDR ADOCK 05000338 G-PDR
.