TSTF 2019 Retrospective Page 1 EXCEL Services Corporation
- 2020 marks the 17th year (2003) of the TSTF as a jointly sponsored Owners Group activity (25 years as an organization, 1995)
- One change in TSTF membership (Dwi Murray for David Gullott)
- Travelers:
o Five travelers approved:
TSTF-557, Rev. 1, Spent Fuel Storage Rack Neutron Absorber Monitoring Program, (All) 1/15/2019
- 163 Review Hours TSTF-566, Rev. 0, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems, (BWRs) 2/21/2019
- 347 Review Hours TSTF-569, Rev. 2, Revise Response Time Testing Definition, (Westinghouse
& Combustion Engineering) 8/14/2019
- 332 Review Hours TSTF-541, Rev. 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position, (All) 12/10/2019
- 671 Review Hours TSTF-568. Rev. 2, Revise Applicability of BWR/4 TS 3.6.2.5 and TS 3.6.3.2, (BWRs) 12/17/2019
- 713 Review Hours o Two traveler revisions submitted:
TSTF-568, Revision 2, "Revise Applicability of BWR/4 TS 3.6.2.5 and TS 3.6.3.2," (BWR) 5/21/2019 (approved)
TSTF-541, Revision 2, "Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position," (All) 6/18/2019 (approved) o Three new travelers submitted:
TSTF-554, Revision 0, "Revise Reactor Coolant Leakage Requirements,"
(All) 5/7/2019 TSTF-582, Revision 0, "RPV WIC Enhancements," (BWR) 8/28/2019 TSTF-576, Revision 0, "Revise Safety/Relief Valve Requirements," (BWR) 12/13/2019
TSTF 2019 Retrospective Page 2 EXCEL Services Corporation
- The NRC expended 1,253 hours0.00293 days <br />0.0703 hours <br />4.183201e-4 weeks <br />9.62665e-5 months <br /> reviewing travelers in 2019.
- The TSTF exchanged 26 letters with the NRC:
o 14 from the NRC (excludes meeting notices and summaries) o 12 from the TSTF
- The TSTF held 13 meetings and 15 teleconferences with NRC.
- Other TSTF Activities:
o Withdrew recommendation for adoption and removal of commitments regarding TSTF-493, "Clarify Application of Setpoint Methodology for LSSS Functions,"
6/18/2019.
o Supported the NEI Regulatory Issues Task Force (RITF) on completion and issuance of NEI 18-03, "Operability Determination."
o Supported the NEI Risk Informed Technical Specifications Task Force (RITSTF) in resolving the use of new PRA methods with TSTF-505, "Provide Risk-Informed Extended Completion Times."
o Supported the EPRI Steam Generator Management Program (SGMP) in development of changes to the TS-required inspection frequencies for steam generator tubes.
Decade Retrospective Page 3 EXCEL Services Corporation 0
1 2
3 4
5 6
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Approved Travelers Per Year 2010-2019 0
2 4
6 8
10 12 14 16 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Annual Traveler Inventory vs. Approval Annual Traveler Approvals Annual Traveler Inventory Expon. (Annual Traveler Approvals)
Expon. (Annual Traveler Inventory)
Decade Retrospective Page 4 EXCEL Services Corporation 0
20 40 60 80 100 120 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Approved Amendments to Adopt Travelers by Year 2010-2019