Request for Extension Until 830815 to File Status Rept on Proceeding.Hearing Cannot Be Held in Sept 1983 Since NRC Has Not Issued Des or Safety Evaluation.Hartsville Group & Util Are to Confer on Interrogatories.Certificate of Svc Encl
ML20077A539
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 07/20/1983
From: Trowbridge G
CAROLINA POWER & LIGHT CO., SHAW, PITTMAN, POTTS & TROWBRIDGE
To:
Atomic Safety and Licensing Board Panel
References
83-484-03LA, 83-484-3LA, ISSUANCES-OLA, NUDOCS 8307220352
Download: ML20077A539 (5)


Text

.

July 20, 1983 D

/ 'f Q'7

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION I

ree g.,,

7 jq C :.:a C ]7033 3 BEFORE THE ATOMIC SAFETY AND LICENSING BOARD a sw%.

y tu:f

/Q gh In the Matter of

)

)

CAROLINA POWER & LIGHT COMPANY

)

Docket tio. 50-261-OLA

)

(H. 3.

Robinson Steam Electric

)

ASLBP No. 83-484-03LA Plant, Unit 2)

)

APPLICANT'S REQUEST TO EXTEND TIME FOR FILING STATUS REPORT In its Memorandum and Order of April 12, 1983, the Licensing Board, after taking into account (1) the Staff's then anticipated schedule for the issuance of a safety evaluation report and for the issuance of either an environmental impact appraisal or draft and final environmental statement and (2) the' discovery schedule agreed upon by the parties and adopted by the Board, set July 25, 1983, as the date for the parties to file a status report on the proceeding.

For the reasons enumerated below, Applicant requests that the date for filing a status report be extended to August 15, 1983.

1.

The Staff has decided to prepare an environmental statement but has not yet issued either a draft environmental statement or a safety evaluation re-port.

Thus the proceeding schedule can no longer allow for an evidentiary hearing to commence in September, 1983, as contemplated in the Board's Memorandum and Order.

8307220352 830720 PDR ADOCK 05000261 G

PDR cg-3

2.

Applicant has objected to certain of the Hartsville Group first set of interrogatories and the Hartsville Group has filed with the Board a motion to compel answers.

Applicant's counsel has made arrangements to discuss with the representative of the Hartsville Group Applicant's objections and Hartsville Group's motion to compel in the hope of eliminating or narrowing some of the differences between the two parties.

Since the status report re-quested by the Board is to include a report on discovery, the status report should await the outcome of these discussions.

Counsel for the NRC Staff and the representative of the.Hartsville Group have advised Applicant's counsel that they have no objection to this request.

Respectfully submitted, l

[

SHAW, ITTMAN, PO P'E g & TROWBRIDGE

}//A/ rl '. / ZJ&f 1 J idhorgd F. Trowbridge,P/C.

Delissa A. Ridgway l

Counsel for Applicant Dated: July 20, 1983 1.

e

July 20, 1983 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY'AND LICENSING BOARD In the Matter of

)

)

CAROLINA POWER & LIGHT COMPANY

)

Docket No. 50-261-OLA

)

(H.

B.

Robinson Steam Electric

)

ASLBP No. 83-484-03LA Plant, Unit 2)

)

CERTIFICATE OF SERVICE I hereby certify that copies of " Applicant's Request to Extend Time for Filing Status Report," dated July 20, 1983, were served upon those persons on the attached Service List by deposit in the United States mail, postage prepaid, this 20th day of July, 1983.

v

/

/2d ZY

//

Meor[eF. Tro bridge, C.

Dated: July 20, 1983

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATCMIC SAFETY AND LICENSING BOARD In the Matter of

)

)

CAROLINA POWER & LIGHT COMPANY

)

Docket No. 50-261

)

(Steam Generator (H.

B.

Robinson Steam Electric

)

Repairs)

Plant, Unit 2)

)

SERVICE LIST Administrative Judge Morton B.

Margulies Chairman, Atomic Safety and-Licensing Board U.S. Nuclear Regulatory Commission Washington, D.C.

20555 Administrative Judge Jerry R.

Kline Atomic Safety and Licensing Board U.S. Nuclear Regulatory Commission Washington, D.C.

20555 Administrative Judge David L. Hetrick Atomic Safety and Licensing Board Professor of Nuclear Engineering University of Arizona Tucson, Arizona 85721 Docketing & Service Section (3)

Office of the Secretary U.S. Nuclear Regulatory Commission Washington, D.C.

20555 Myron Karman, Esquire Office of Executive Legal Director U.S. Nuclear Regulatory Commission Washington, D.C.

20555 B. A. Matthews Hartsville Group P. O. Box 1089 Hartsville, South Carolina 29550

Dr. John C. Ruoff P. O. Box 96 Jenkinsville, South Carolina 29065 Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Washington, D.C.

20555 Atomic Safety and Licensing Appeal Board Panel U.S. Nuclear Regulatory Commission Washington, D.C.

20555 Samantha Francis Flynn, Esq.

Carolina Power & Light Company P. O. Box 1551 Raleigh, North Carolina 27602 f

~,,