ENS 47500
ENS Event | |
---|---|
21:29 Oct 11, 2011 | |
Title | Loss of Vital Ac Power While Shutdown |
Event Description | This 60-day telephone notification is being made pursuant to 10CFR50.73(a)(2)(iv)(A) and 10CFR50.73(a)(1) to describe an invalid actuation of a containment heat removal system.
On October 11, 2011, with the reactor shutdown for refueling, a partial loss of vital AC power was experienced which resulted in a loss of shutdown cooling as well as PCIS group 2, 3, 4, and 5 half isolations. The actuation was determined to be invalid as it occurred because a breaker supplying power to the 'A' vital AC was manually opened, resulting in actuation of the associated PCIS logic circuitry. The Group 4 actuation resulted in a complete isolation of the single train Residual Heat Removal shutdown cooling suction path. The shutdown cooling path was isolated for approximately 12 minutes resulting in a coolant temperature increase of approximately 2 degrees F. At the time of the event, the reactor cavity was flooded with the spent fuel pool gates removed and the normal fuel pool cooling system in operation to provide reactor cavity cooling. Based on this, there was no impact on public health and safety. The licensee notified the NRC Resident Inspector. |
Where | |
---|---|
Vermont Yankee Vermont (NRC Region 1) | |
Reporting | |
10 CFR 50.73(a)(1), Submit an LER, Invalid Actuation | |
Time - Person (Reporting Time:+1331.77 h55.49 days <br />7.927 weeks <br />1.824 months <br />) | |
Opened: | Kevin Murphy 10:15 Dec 6, 2011 |
NRC Officer: | Mark Abramovitz |
Last Updated: | Dec 6, 2011 |
47500 - NRC Website
Loading map... {"minzoom":false,"maxzoom":false,"mappingservice":"leaflet","width":"350px","height":"250px","centre":false,"title":"","label":"","icon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"zoom":6,"defzoom":14,"layers":["OpenStreetMap"],"image layers":[],"overlays":[],"resizable":false,"fullscreen":false,"scrollwheelzoom":true,"cluster":false,"clustermaxzoom":20,"clusterzoomonclick":true,"clustermaxradius":80,"clusterspiderfy":true,"geojson":"","clicktarget":"","imageLayers":[],"locations":[{"text":"\u003Cb\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003E\u003Ca class=\"mw-selflink selflink\"\u003EENS 47500\u003C/a\u003E - \u003Ca href=\"/Vermont_Yankee\" title=\"Vermont Yankee\"\u003EVermont Yankee\u003C/a\u003E\n\u003C/p\u003E\u003C/div\u003E\u003C/b\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003ELoss of Vital Ac Power While Shutdown\n\u003C/p\u003E\u003C/div\u003E","title":"ENS 47500 - Vermont Yankee\n","link":"","lat":42.77900833333333,"lon":-72.51328611111111,"icon":"/w/images/7/79/Entergy_icon.png"}],"imageoverlays":null} | |
WEEKMONTHYEARENS 501642014-04-05T11:00:0005 April 2014 11:00:00
[Table view]10 CFR 50.73(a)(1), Submit an LER Invalid Primary Containment Isolation System Actuation ENS 498252013-12-15T05:00:00015 December 2013 05:00:00 10 CFR 50.73(a)(1), Submit an LER 60 Day Optional Telephone Notification of Invalid Pcis System Actuation ENS 493582013-07-23T04:00:00023 July 2013 04:00:00 10 CFR 50.73(a)(1), Submit an LER Invalid Primary Containment Isolation System Group 3 Actuation ENS 492112013-06-14T22:06:00014 June 2013 22:06:00 10 CFR 50.73(a)(1), Submit an LER Invalid Primary Containment Isolation System Actuation Due to a Radiation Monitor Spike ENS 475002011-10-11T21:29:00011 October 2011 21:29:00 10 CFR 50.73(a)(1), Submit an LER Loss of Vital Ac Power While Shutdown ENS 460702010-05-17T04:00:00017 May 2010 04:00:00 10 CFR 50.73(a)(1), Submit an LER 60 Day Report - Invalid Actuation of Hpci and Rcic Systems ENS 450092009-03-24T17:26:00024 March 2009 17:26:00 10 CFR 50.73(a)(1), Submit an LER Primary Containment Isolation System (Pcis) Group 3 Invalid Actuation ENS 437292007-09-15T04:00:00015 September 2007 04:00:00 10 CFR 50.73(a)(1), Submit an LER Invalid Primary Containment Isolation ENS 421202005-11-04T21:08:0004 November 2005 21:08:00 10 CFR 50.73(a)(1), Submit an LER Temporary Loss of the Running Rhr Pump During a Bus Transfer ENS 422352005-11-03T00:01:0003 November 2005 00:01:00 10 CFR 50.73(a)(1), Submit an LER Inadvertent Containment Isolation Signal Affecting Containment Isolation Valves ENS 410042004-07-31T17:56:00031 July 2004 17:56:00 10 CFR 50.73(a)(1), Submit an LER Invalid Pcis Actuation ENS 403712003-10-31T05:00:00031 October 2003 05:00:00 10 CFR 50.73(a)(1), Submit an LER Invalid Group Iii Primary Containment Isolation System Actuation 2014-04-05T11:00:00 | |