Presentation Slides for the April 11, 2024, Quarterly Observation Public Meeting on the Status of NuScale US460 Standard Design Approval Application
ML24099A032
Person / Time
Issue date: 04/11/2024
From: Getachew Tesfaye
NRC/NRR/DNRL/NRLB
To:
NuScale
Tesfaye, G., NRR/DNRL, 301-415-8013
Shared Package
ML24099A030 List:
References
Download: ML24099A032 (15)


Text

NuScale Standard Design Approval Application for the US460

Quarterly NuScale-NRC Management Public Meeting April 11, 2024 Opening Remarks

2 Agenda Opening Remarks NuScale US460 Standard Design Approval Application (SDAA) Review Overview

Phase A Safety Review Requests for Additional Information (RAI)

High Impact Technical Issues (HITIs)

Focus Items Supporting Reliable Schedule Development (FISDs)

Topical Reports (TRs)

Generic Licensing Activities (Non- SDAA)

Closing remarks

3 US460 SDAA Review Overview

SDAA staged submittal was completed in January 2023

The NRC staff issued the results of its acceptance review with a request for supplemental information (RSI) on March 17, 2023 The staff began detailed safety evaluation of portions of the application not impacted by the RSI on March 20, 2023

Following the receipt of the supplemental information on July 14 and 17, 2023, a docketing letter was issued on July 31, 2023, that included a four phase, 24- month review schedule

The staff issued a resource estimate letter on September 22, 2023. The SDAA review will require approximately 50,000 staff hours and $650,000 for contractor support

4 US460 SDAA Review Overview Four Phase Review milestones

Phase Phase Name End date

Advanced Safety Evaluation Report Phase A (ASER) without open items (draft November 2024 completion date; internal NRC schedule)

Phase B ASER review (technical editing), Management concurrence February 2025

Phase C ACRS Review of ASER May 2025

Phase D Final Safety Evaluation Report (FSER) and SDA July 2025

5 Phase A Safety Review Completed SDAA Phase reviews:

Phase A - Chapters 2, 7, 9, 10, 11, 12,13, 17 (except 17.4),

and 18.

Phase B - Chapters 2, 10, 11, 13, and 17 (except 17.4)

Phase C - Chapters 2, 10, 11, 13, and 17 (except 17.4)

As of April 9, 2024, the NRC staff has presented 983 document requests and items for explanations in the audit.

726 items have been resolved in the audit, 87 items provided by NuScale are under review by the staff, and 101 items are waiting for NuScale to provide in the audit.

37 items resulted in request for additional information

6 ALL FISD HITI

Issues by Category Total Aw aiting Response NRC Review ing Resolved in Audit Sent to RAI process ALL 983 101 87 726 37 FISD 34 2 11 19 2 HITI 47 13 15 18 1

Issues Generated vs Issues Resolved over time (including document requests) 1200 70 Cumulative Issues Resolved 1000 Cumulative Issues Generated 60 Issues Resolved 800 Issues Generated 50

40 600 30 400 20

200 10

0 0 03/15/2023 05/15/2023 07/15/2023 09/15/2023 11/15/2023 01/15/2024 03/15/2024

7 Requests for Additional Information (RAI)

The NRC staff has issued a total of 41 RAI questions, as of April 9, 2024 NuScale responded to RAI questions on or about agreed upon schedule 22 RAI questions have been resolved closed 8 RAI responses are under NRC review 11 RAI are awaiting responses

8 High Impact Technical Issues (HITIs)

1. Design and classification of EDAS
2. LOCA break spectrum
3. Incorporated by Reference (IBR)
4. CNV material change - Resolved
5. Lower RPV material change - Resolved
6. Secondary side controller design for DWO events
7. DWO and steam generator inlet flow restrictor design changes
8. ASME qualification of the helical coil steam generator for the onset of DWO -induced loads
9. Upper-to-lower RPV flange bolted joint shear loading that results from differential thermal expansion - New

9 High Impact Technical Issues (HITIs)

Audit Activities As of April 9, 2024, the staff has presented 47 HITI document requests and items for explanations in the audit.

18 have been resolved in the audit, 15 items provided by NuScale are under review by the staff, 13 items are waiting for NuScale to provide in the audit, and 1 item is sent to RAI process NRC- NuScale additional deep dives on DWO related HITIs scheduled for April.

10 Focus Items For Schedule Development (FISDs)

As of April 9, 2024, the staff presented 34 FISD document requests and items for explanations in the audit.

19 items have been resolved in the audit, 11 items provided by NuScale are under review by the staff, 2 items are waiting for NuScale to provide additional information or revised responses, and 2 items sent to RAI process

11 Topical Reports (TRs)

Eight TRs* submitted prior to the SDAA are completed.

Four TRs submitted with SDAA are included in the SDAA Phase A audit

  • Rod Ejection final SE contingent on Non-LOCA TR completion

12 Generic Licensing Activities (non - SDAA)

Generic TRs:

Mitigation of Beyond Design Basis Events TR submitted on September 11, 2023. The staff accepted the TR for detailed review and plans to complete the Advance SE by August 2024.

Fuel Storage Rack Design TR submitted on October 9, 2023. The staff has accepted the TR for detailed review and plans a complete the Advance SE by May 2025.

Reactor Flange Tool Support Design TRs pre-application meeting was held on October 26, 2023. The planned TR submittal has been delayed until late 2024 Application Specific Modifications to the Base HIPS Platform TR - Pre-application meeting held on November 20, 2023. The planned TR submittal has been delayed until late 2024.

(NuScale DCA) Request for Exemption to the Reporting Requirements of 10 CFR 50.46(a)(3) [Changes to the approved LOCA methodology] - Staff has granted the requested exemption - FRN issued on April 5, 2024

13 Closing Remarks

14 Questions?