KPNRC2206001 June 27, 2022 Docket No. 507513 US Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 205550001
Subject:
Kairos Power LLC Transmittal of Changes to Construction Permit Application - PSAR Chapter 3
References:
- 1. Letter, Kairos Power LLC to Document Control Desk, Submittal of the Preliminary Safety Analysis Report for the Kairos Power Fluoride SaltCooled, High Temperature NonPower Reactor (Hermes), September 29, 2021 (ML21272A376)
- 2. Audit Plan, Nuclear Regulatory Commission, Plan for a General Audit of the Hermes Construction Permit Application, February 10, 2022 (ML22039A33)
In September 2021, Kairos Power submitted a Preliminary Safety Analysis Report (PSAR) (Reference 1) as part of a Construction Permit Application (CPA) for the Hermes nonpower reactor. This letter transmits changes to the pages of the PSAR to address NRC feedback received on PSAR Chapter 3 in the General Audit (Reference 2). Change to the pages of the PSAR are provided in Enclosure 1. Kairos Power requests NRC review of these changes as part of the continued review of the Hermes CPA.
If you have any questions or need any additional information, please contact Margaret Ellenson at ellenson@kairospower.com or (510) 7551861, or Darrell Gardner at gardner@kairospower.com or (704) 7691226.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on June 27, 2022 Sincerely, Peter Hastings, PE Vice President, Regulatory Affairs and Quality
Enclosures:
- 1) Changes to PSAR Chapter 3 Kairos Power LLC www.kairospower.com 707 W Tower Ave, Suite A 5201 Hawking Dr SE, Unit A 2115 Rexford Rd, Suite 325 Alameda, CA 94501 Albuquerque, NM 87106 Charlotte, NC 28211
KPNRC2206001 Page 2 xc (w/enclosure):
William Kennedy, Acting Chief, NRR Advanced Reactor Licensing Branch Benjamin Beasley, Project Manager, NRR Advanced Reactor Licensing Branch Edward Helvenston, Project Manager, NRR Advanced Reactor Licensing Branch Samuel Cuadrado de Jesus, NRR Advanced Reactor Licensing Branch