Ack Receipt of Informing NRC of Schedule for Resolving Deficiencies Noted in Emergency Preparedness Insp Repts 50-498/86-35 & 50-499/86-35.Schedule Responsive to Concerns Identified in Repts
ML20209H792
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 04/29/1987
From: Gagliardo J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Goldberg J
HOUSTON LIGHTING & POWER CO.
References
NUDOCS 8705040122
Download: ML20209H792 (2)


See also: IR 05000498/1986035

Text

,

    • -"

APR 291987

In Reply Refer To:

-Dockets: 50-498/86-35

50-499/86-35

Houston Lighting & Power. Company

ATTN: J. H. Goldberg, Group Vice

President, Nuclear

P. O. Box 1700

Houston, Texas 77001

Gentlemen:

Thank you for your letter of March 27, 1987, in response to our letter

dated February 26, 1987. We have reviewed your reply and find the schedule

for resolving deficiencies responsive to the concerns raised in our emergency

preparedness inspection report. We will review the implementation of your

corrective actions during future inspections to determine that an adequate

state of onsite emergency preparedness has been achieved and will be

maintained.

Sincerely,

-ORIGINAL SIGNED BY:

-

J. E. Gagliardo, Chief

Reactor Projects Branch

cc:

Houston Lighting & Power Company

ATTN: M. Wisenberg, Manager,

Nuclear Licensing

P. O. Box 1700

Houston, Texas 77001

Houston Lighting & Power Company

ATTN: Gerald E. Vaughn, Vice President

Nuclear Operations

P. O. Box 1700

Houston, Texas 77001

Texas Radiation Control Program Director

RIV:EP&SP C:EP&SP C:R&SPBb C: C:RPB

JBBaird/jt LAYandell WLFisher ble J Ga ia o

4 /Gb/87 I{/%/87 4/%/87 G}L/1%/87 /g 8j1

/

8705040122 870429

PDR ADOCK O 4y8 ,

a

/y/ji

r

. .

Houston Lighting and Power Company -2-

bec to DMB (IE35)

bec distrib. by RIV:

RPB

DRSP

Resident Inspector-OPS

R. D. Martin, RA

Resident Inspector-CONST.

Section Chief (RPB/C)

R&SPB

MIS SYSTEM

2 4V File

D. Weiss, RM/ALF

RSTS Operator

R. Pirfo, ELD

R. G. Taylor, RPB/C

RSB

Inspector

Section Chief

W. L. Fisher

R. L. Bangart

R. E. Hall

Project Inspector, RPB

D. B. Matthews, NRR

,

. .

.

.. . .

.

s.

c. The Light

m m P u y "eseetia ix&Pe-e, n e.o. 8ex >700 nees ee. rex ,27ooi <2is> 22s.92ii

March 27, 1987

ST-HL-AE-1994

File No.: G9.08

10CFR 50.47

.-

@h

U. S. Nuclear Regulatory Commission

Attention: Document Control Desk <

','.,r ~ " '---- ~]t

Washington, DC 20555 ): ' AM - 2 E

_ h

South Texas Project

Units 1 and 2

Docket Nos. STN 50-498, STN 50-499

Emergency Preparedness Appraisal

In response to Mr. J. E. Gagliardo's letter dated February 27, 1987,

which tratsmitted the Emergency Preparedness Appraisal Inspection Report, we

are submitting the attached schedule for resolving all identified

deficiencies. Houston Lighting & Power (HMP) personnel met with the NRC

staff on Janary 8, 1987 to discuss these items. The attachment also cross

references each of the Inspection Report item numbers to the numbers assigned

by HMP prior to receipt of the inspection report and used during the January

meeting. Also noted on the attachment are any necessary qualifying comments

relative to the schedule dates.

Since the time of the appraisal, HMP has devoted an extensive amount of >

resources to the Emergency Preparedness Program. We believe that with

completion of the procedures, training, systems, etc. listed on the

'

attachment, HMP will be able to demonstrate adequate emergency preparedness

at the South Texas Project Electric Generating Station.

i

l

If you should have any questions on this matter, please contact Mr.

M. A. McBurnett at (512) 972-8530.

J. H. Goldberg

Group Vice President, Nuclear

l MAM/ljm

l

l Attachment: NRC Emergency Preparedness Appraisal Response

l

l -

1

L3/NRC/cp k

%ySM

. .

. .- .

,,

Houston 1.ighting & Power Company

ST-HL-AE-1994

File No.: C9.08

Page 2

cc:

Regional Administrator, Region IV M.B. Lee /J.E. Malaski'

Nuclear Regulatory Commission City of Austin

611 Ryan Plaza Drive, Suite 1000 P.O. Box 1088

Arlington, TX 76011 Austin, TX 78767-8814

N. Prasad Kadambi, Project Manager M.T. Hardt/A. von Rosenberg

U.S. Nuclear Regulatory Commission City Public Service Board

7920 Norfolk Avenue P.O. Box 1771

Bethesda, MD 20814 San Antonio, 13t 78296

Robert L. Perch, Project Manager Advisory Committee on Reactor Safeguards

U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission

7920 Norfolk Avenue 1717 H Street

Bethesda, MD 20814 Washington, DC 20555

Dan R. Carpenter

Senior Resident Inspector / Operations

c/o U.S. Nuclear Regulatory

Commission

P.O. Box 910

Bay City, TX 77414

, Claude E. Johnson

! Senior Resident Inspector /STP

c/o U.S. Nuclear Regulatory

Commission

P.O. Box 910

Bay City, TX 77414

j M.D. Schwarz, Jr. , Esquire

'

Baker & Botts

One Shell Plaza

. Houston, TX 77002

J.R. Newman, Esquire

Newman & Holtzinger, P.C.

1615 L Street, N.W.

Washington, DC 20036

T.V. Shockley/R.L. Range

Central Power & Light Company

P. O. Box 2121

Corpus Christi, TX 78403

l-

Revised 2/3/87

L3/NRC/cp

-. . - _ . - _ - _ - - - - .

_ _ - -

, .

'

. '

.

Attachment

ST-HL-AE-1994

  • Page 1 of 5

.

.

NRC Emergency Preparedness Appraisal Response

Scheduled

NRC No. HL&P* No. Completion Date Notes / Comments

8635-001 4a 3/09/87 Completed

8635-002 4a 3/11/87 Completed

8635-003 5b 4/01/87

,

8635-004 3a 4/07/87

8635-005 7a,b,c Fuel Load Installed Systems will be

functional for drill purposes by

4/1/87; however, these systems

will not be . fully operational

until fuel load.

8635-006 lb,6a 4/01/87

8635-007 7a,b,c Fuel Load Installed Systems will be

functional for drill purposes by

4/1/87; however, these systems

will not be fully operational

until fuel load.

8635-008 6b 3/24/87 Completed

8635-009 10b,9c,15 3/02/87 Completed

8635-010 10c 3/09/87 Completed

8635-011 6c 3/24/87 Completed

i 8635-012 7a,b,c Fuel Load Installed Systems will be

l .

functional for drill purposes by

4/1/87; however, these systems

will not be fully operational

until fuel load.

8635-013 9a 5/01/87 The E0C HVAC system does not use

charcoal filters; therefore, no

charcoal testing will be

established for this system. The

Emergency Plan was revised to

delete reference to charcoal

filters.

8635-014 6d 3/24/87 Completed

8635-015 Ic,10a 3/02/87 Completed

l

l

'

- . - . - - _ . . ._ .. - .-- . - - . - . . - - . _ - -

_ .. - . . ..- .- -. .. - . , . . . - --

. .

-

,

. . .

'

Attachment

ST-HL-AE-1994

,

Page 2 of 5

.

Scheduled

NRC No. HL&P* No. Completion Date Notes / Comments

8635-016 7f Full Power The PASS System is essentially

License complete and partially tested.

Full operability will be

demonstrated prior to full power

operation.

8635-017 7f Full Power The PASS System is essentially

License complete and partially tested.

Full operability will be

demonstrated prior to full power

operation.

8635-018 7f Full Power The PASS System is essentially

License complete and partially tested.

Full operability will be

demonstrated prior to full power

operation.

8635-019 --

6/01/67 There is no dedicated system for

post accident sampling of plant

liquid effluents. Appropriate

ALARA reviews and procedural

precautions are being added to

address such activities at the

normal sample locations.

, 8635-020 10f Fuel Load Offsite reassembly controls will

be established by 4/1/87 and

tested prior to Fuel Load.

8635-021 13a,10e 4/01/87

8635-022 la 12/19/86 Completed

.

8635-023 4c 2/24/87 Completed

l

l 8635-024 --

4/01/87 The additional electrical outlets

'

in the PIO Support room at the

l MIC are being added.

8635-025 7e Fuel Load Non-radiological process systems,

. including their indication and

l alarm functions are scheduled to

'

be completed and operational

j prior to issuance of the low

j power license.

!

8635-026 2e 3/24/87 Completed

l

l

l

!

.

<

. - - - . . . - . _ . , - _ _ , , _ _ _ . . _ . _ , , . _ , . . , , , . _ _ . . . _ ,,_m _ _ . , , , . , , _ ---_-.,_..,,._m- _

.--

. .

.

. .

.

. Attachment

ST-HL-AE-1994

Page 3 of 5 j

Scheduled

NRC No. HL&P* No. Completion Date Notes / Comments

8635-027 --

4/03/87 Inconsistency between the Plan,

the FSAR and implementing

procedures will be resolved

through transmittal of marked-up

FSAR pages on 4/3/87 and followed

up with a formal FSAR amendment.

8635-028 6a,c.e 3/24/87 Completed

8635-029 6a-e 3/24/87 Completed

8635-030 2e 2/10/87 Completed

8635-031 8a 2/24/87 Completed. There is no back up

communications system to the

State EOC.

8635-032 --

Fuel Load The PNS system sirens have been

completed and tested. The Tone

Alert Radios will be distributed

to EPZ population prior to fuel

load. Programs for operation and

control of the PNS will be in

place prior to 4/1/87

8635-033 Ig 3/31/87

8635-034 13e 4/01/87

8635-035 10 3/09/87 Completed

8635-036 10d 3/09/87 Completed

-

8635-037 10f 3/31/87

8635-038 13d 3/20/87 Completed

8635-039 2e 2/10/87 Completed

8635-040 2d 4/15/87

8635-041 12 3/11/87 Completed

8635-042 4a 3/27/87

0635-043 le 1/09/87 Completed

8635-044 --

4/07/87

8635-045 Sa 4/15/87 Completion delayed to allow for

licensing of one remaining pager

transmitter station.

.-.

_ _ _ . ._. ._

-.

- _ - . .

. .'

. s . -

'

', Attachment

ST-HL-AE-1994

,

Page 4 of 5

..

Scheduled

NRC No. HL&P* No. . Completion Date Notes / Comments

8635-046 8b 6/01/87

8635-047 4a,5a 3/11/87 Completed

8635-048 7c,7q Fuel Load RM21A is functional and

demonstrable for exercise play on

4/8/87, full operational

capability is dependent upon

' plant completion for fuel load.

8635-049 --

4/01/87 The IRDAM program has been

subsequently upgraded and

renamed, STAMPEDE. Final

procedural revisions for STAMPEDE

will be complete 4/1/87.

8635-050 Id 1/09/87 Completed

8635-051 If 3/09/87 Completed

8635-052 13b 4/01/87

8635-053 13c 4/01/87

8635-054 Sc 4/15/87 Completion delayed due to system

expansion.

8635-055 8c 6/01/87

8635-056 14 6/01/87 Procedures for site access and

accountability are complete; the

security system will be completed

and controls demonstrated by

.

6/1/87.

8635-057 13a,10e 4/01/87

8635-058 10f,13a 3/31/87

8635-059 --

4/01/87

8635-060 15 3/02/87 Completed

8635-061 16,lh 4/01/87

8635-062 10g 12/14/86 Completed

8635-063 10h 12/14/86 Completed

8635-064 4f 12/19/86 Completed

~

. .

. . .

.

-

Attachment

ST-HL-AE-1994

Page 5 of 5

.x

Scheduled

NRC No. HL&P* No. Completion Date Notes / Comments

8635-065 2e 2/10/87 Inventory controls complete,

calibration is controlled and is

being conducted as equipment is

received.

8635-066 2e 3/01/87 Inventory controls are complete,

calibration is controlled and is

being conducted as equipment is

,

received.

8635-067 2b 4/01/87

8635-068 2c 4/01/87 The Nuclear Safety Review Board

has accepted responsibility for

12 month EP Program reviews and

will document plans for conduct.

8635-069 2c 3/09/87 The Emergency Plan has been

revised to identify NSRB as the

responsible organization for

10CFR50.54(t). Since NSRB is

independent from the Emergency

Preparedness Department and PORL,

this item is resolved.

8635-070 3b 5/01/87 Respiratory training is scheduled

for April,1987 and will complete

this item.

8635-071 3b 4/07/87

8635-072 17 5/01/87 Transient information has been

- posted with the exception of 3

weatherproof signs to be placed

at public boat ramps.

8635-073 2a 4/01/87

8635-074 --

4/08/87 Procedures, training and drill

experience have significantly

improved these performance items

since December, 1986, as will be

evidenced by exercise performance

on April 8, 1987.

8635-075 4d 3/03/87 Completed

  • The HL&P number is the number used by HL&P to identify the deficiency in the

meeting on January 8, 1987.

-

. - .. -- - - - - - . - . . .- .- - . -