Forwards Insp Rept 99901064/86-01 on 860915-18 & Notices of Violation & Nonconformance
ML20211D825
Person / Time
Issue date: 10/20/1986
From: Heishman R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
To: Godfrey D
ENERFAB
Shared Package
ML20211D829 List:
References
REF-QA-99901064 NUDOCS 8610220277
Download: ML20211D825 (4)


Text

9 EEGg p[ Ig UNITED STATES y ' ) v. ( g NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 li ?

E kf.....# nctober 20, 1936 Docket No. 99901064/86-01 Enerfab, Incorporated ATTN: Mr. Dwaine A. Godfrey President 4955 Spring Grove Avenue Cincinatti, Ohio 45232 Gentlemen:

This refers to the inspection conducted by E. Yachimiak of this office on September 15-18, 1986, of your facility located in Cincinatti, Ohio, and to the discussions of our findings with Mr. K. T. Shinkle and members of your staff at the conclusion of the inspection.

This inspection was made as a result of the issuance of two 10 CFR Part 21 reports dealing with problems and/or concerns with W. J. Woolley containment personnel airlocks. Areas examined during the inspection and our findings are discussed in the enclosed report. Within these areas, the inspection consisted of an examination of procedures and representative records, interviews with personnel, and observations by the inspector.

During the inspection it was found that the implementation of your QA program failed to meet certain NRC requirements. This consisted of one violation to 10 CFR Part 21, and two nonconformances to Appendix 8 of 10 CFR Part 50.

Specifically, the violation concerned your failure to adopt appropriate proce-dures pursuant to 10 CFR Part 21.21 for the evaluation and reporting of defects and noncompliances. The two nonconformances dealt with: .(1) failure to provide adequate procedures for activities affecting quality (shipping, handling, storage, and receiving inspection) and (2) failure to use a vendor for calibration service which was on the Approved Vendors List. The specific findings and references to the pertinent requirements are identified in the enclosures to this letter.

+

The enclosed Notice of Violation is sent to you pursuant to the provisions of Section 206 of the Energy Reorganization Act of 1974. You are required to submit to this office within 30 days from the date of this letter a written statement containing: (1) a description of steps that have been or will be taken to correct these items; (2) a description of steps that have been or will be taken to prevent recurrence; and (3) the dates your corrective actions and preventive measures were or will be completed. Consideration may be given to extenoing your response time for good cause shown.

8610220277 861020-PDR GA999 EMVENFAB 99901064 PDR

Enerfab, Incorporated October 20, 1986 You are also requested to submit a similar written statement for each item which appears in the enclosed Notice of Nonconformance.

The responses requested by this letter are not subject to the clearance proce-dures of the Office of Management and Budget as required by the Paperwork Reduction Act of 1980, PL 96-511.

In accordance with 10 CFR 2.790 of the Comission's regulations, a copy of this letter and the enclosed inspection report will be placed in the NRC's Public Document Room.

Should you have any questions concerning this inspection, we will be pleased to discuss them with you.

Sincerely,

/ .

US Robert F. Heishman, hief Vendor Program Branch Division of Quality Assurance, Vendor and Technical Training Center Programs Office of Inspection and Enforcement

Enclosures:

1. Appendix A-Notice of Violation
2. Appendix B-Notice of Nonconformance
3. Appendix C-Inspection Report No. 99901064/86-01
4. Appendix D-Inspection Data Sheet (1 page) r

1 Enerfab, Incorporated 2- October 20, 1986 i

You are also requested to submit a similar written statement for each item which appears in the enclosed Notice of Nonconformance.

The responses requested by this letter are not subject to the clearance proce-dures of the Office of Management and Budget as required by the Paperwork Reduction Act of 1980, PL 96-511.

In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of this letter and the enclosed inspection report will be placed in the NRC's Public Document Room.

7 Should you have any questions concerning this inspection, we will be pleased

to discuss them with you.

Sincerely, original signed by:

Ellis H. lierschoff Robert F. Heishman, Chief

.j Vendor Program Branch j Division of Quality Assurance, Vendor i and Technical Training Center Programs

, Office of Inspection and Enforcement

Enclosures:

1. Appendix A-Notice of Violation
2. Appendix B-Notice of Nonconformance
3. Appendix C-Inspection Report No. 99901064/86-01
4. Appendix D-Inspection Data Sheet (1 page)

DISTRIBUTION:

DMB:IE:09' VPB Reading DQAVT Reading RStarostecki BGrimes HMiller RHeishman JStone

, EYachimiak (2)

LParker i

VPB:

Q VT /VPB:00AVT /VPB:00AVT EYachimiak:tt Merschoff (**RHeishman 10gS/86 10/0786 10/s7/86 4

/ $o ,

i l i

l I._.._~ -. - _ _ . , , , _ . . _ . . . _ . . _ , _ _ - . . - . _ , ~ . _ _ . . _ __

Enerfab, Incorporated October 20, 1986 You are also requested to submit a similar written statement for each item which appears in the enclosed Notice of Nonconformance.

The responses requested by this letter are not subject to the clearance proce-dures of the Office of Management and Budget as required by the Paperwork Reduction Act of 1980, PL 96-511.

In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of this letter and the enclosed inspection report will be placed in the NRC's Public Document Room.

Should you have any questions concerning this inspection, we will be pleased to discuss them with you.

Sincerely, original signed by:

Ellis 'cl. Merschoff i Robert F. Heishman, Chief

/

/(\x Vendor Program Branch Division of Quality Assurance, Vendor

\'-

\\ and Technical Training Center Programs 1 Office of Inspection and Enforcement

Enclosures:

1. Appendix 'A-Notice of Violation
2. Appendix B-Notice of Nonconformance
3. Appendix C-Inspection Report No. 99901064/86-01
4. Appendix D-Inspection Data Sheet (1 page)

DISTRIBUTION:

BMB:IE:09-VPB Reading CQAVT Reading RStarostecki BGrimes HMiller i

RHeishman JStone EYachimiak (2)

LParker i

I h

1 C" 0 l VPB: VT j[4VPB:DGAVT /VPB:00AVT

! EYachimiak:tt 'RMerschoff G*RHeishman l 10// S/86 ~ 10/6786 10/47/86 l

'