Interim Deficiency Rept DER 86-29 Re Letdown HX Nozzle Crack.Initially Reported on 861114.Due to Extensive Investigation & Evaluation Required to Address Complexity of Issue,Next Rept Delayed Until 870216
ML20212R330
Person / Time
Site: Palo Verde Arizona Public Service icon.png
Issue date: 01/09/1987
From: Haynes J
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Kirsch D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
ANPP-39651-JGH, DER-86-29, NUDOCS 8702020598
Download: ML20212R330 (2)


Text

.. s,-

e .

Arizona Nuclear Power Project P O. BOX 52034 e PHOENIX. ARIZONA 85072-2034 January 9,1987 ANPP-39651-JGil/DJW/DRL-92.11 U. S. Nuclear Regulatory Commission Region V 1450 !! aria Lane - Suite 210 Walnut Creek, CA 94596-5368 Attention: }!r. D. F. Kirsch, Director Division of Reactor Safety and Projects Palo Verde Nuclear Generating Station (PVNGS)

Unit 3 Docket No. 50/530

Subject:

Time Extension For Report - DER 86-29 A 50.55(e) Potentially Reportable Deficiency Relating to Letdown IIcat Exchanger Nozzle Crack File: 87-006-216

Reference:

(A) Telephone Conversation Between R. C. Sorenson and D. R. Larkin on November 14, 1986. (Initial Notification -

DER 86-29)

(B) ANPP-39248, dated December 5,1986. (Interim Report -

DER 86-29)

Dear Sir:

The NRC was notified of a potentially reportable deficiency in reference (A),

and an interim report by reference (B). At that time it was estimated that a final report would be available by January 15, 1987.

Due to the extensive investigation and evaluation required to address the complexity of this issue, a time extension is needed. It is now expected that this information will be finalized by February 16, 1987 at which time a complete report will be submitted. There is no new information or change to the interim report at this time.

Very truly yours,

' LL At(W J. G. Ilaynes Vice President Nuclear Production JGil/DRL:kp ec: See Page Two 8702020598 870109 i PDR ADOCK 0500 @3o 0 S PDR I

}h)/

.e .

' DER 86 Time Extension Mr. D. F. Kirsch Director Page Two January 9,1987 ANPP-39651-JGH/DJW/DRL-92.11 cc: J. M. Taylor Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555

'n A. C. Gehr (4141)

R. P. Zimmerman (6295)

Records Center Institute of Nuclear Power Operations 1100 circle 75 Parkway - Suite 1500 Atlanta, Georgia 30339