Affidavit of Jc Bukovski.* Affidavit of Jc Bukovski Re Delay in Startup,Testing & Commercial Operation of Unit 1
ML20214N047
Person / Time
Site: Braidwood Constellation icon.png
Issue date: 05/28/1987
From: Bukovski J
COMMONWEALTH EDISON CO.
To:
Shared Package
ML20214N045 List:
References
OL, NUDOCS 8706020039
Download: ML20214N047 (2)


Text

a f ,

AFFIDAVIT OF Jolti C. BUKOVSKI My name is John C. Bukovski. I am an Assistant Vice President of Commonwealth Edison Company. My business address is One First National Plaza.

Post Office Box 767, Chicago. Illinois, 60690.

I received a BSEE degree from the University of Illinois in 1965 and in 1970 a MLA from the Illinois Institute of Technology. I joined Connonwealth Edison in 1965 and have held various positions in engineering, division operations and the financial areas of the Company. My previous position was Division Vice President for the Chicago North Division.

My current responsibilities include general management of the Company's generation planning, corporate modeling and revenue requirements projection activities. The generation planning activities include forecasting generation o by fuel type, capacity planning and projecting the production cost impact of changes in unit availability and performance. [

Purpose of Affidavit The purpose of this affidavit is to describe and quantify the cost to the Company and our customers of a delay in the start-up, testing and comnercial ,

operation of Braidwood Unit 1.

AS stated in the affidavit of Mr. tiallace, final construction and fuel loading are complete and the station personnel are commencing the start-up of the unit.

If the Unit is delayed. Edison's cost of generating electricity will l increase because of the need to replace the generation that would be available from Braidwood Unit I with more costly fossil-fueled generation and purchased energy. An estimate of this additional cost was prepared using PROM 00 !!!.E 070602003r/ 07oppg yDH ADOCK 0D000456 PDM jf PROM 00 !!! is a commercially available program developed by Energy Management Associates. Inc., 100 Northereek. Butte 500. Atlanta.

Georgia. 30327. It is widely used in the electric utility industry.

i

i .

l a production costing model that simulates the manner in which the company's load is assigned to various sources of energy on an economic loading basis while satisfying constraints of operating and spinning reserve requirements and technical limits imposed by the physical characteristics of the various l

generating units. For any given scenario. PROMOD III calculates total system production costs including fuel and purchased energy. By alternately simulating the two scenarios (Braidwood Unit 1 start-up proceeds without delay, or Braidwood Unit 1 is delayed when the Unit reaches % of rated power) and comparing the resulting total system production costs, an estimate of the net replacement cost for the lost output from Brai6eood Unit 1 is determined. The estimate of additional costs of fuel and purchased energy attributable to a one month delay is approximately $10 million. Under the company's currently offective fuel adjustment clause, these charges are passed on to customers as an additional cost of electricity.

The statements in this affidavit are true and correct to the best of my knowledge and belief.

<- / kW t. .

John C. Bukovski e 21stant Vice president commonwealth Edison Company subscribed g d sworn to before me this # 8 - dr.y of May, 1987.