Rev a to IOP-8,Unit Off-Line to Hot Standby or Hot Shutdown
ML20066C820
Person / Time
Site: 05000605
Issue date: 01/09/1991
From: Torres W
GENERAL ELECTRIC CO.
To:
Shared Package
ML20066C783 List:
References
23A6169AH, 23A6169AH-RA, NUDOCS 9101110244
Download: ML20066C820 (7)


Text

{{#Wiki_filter:, - - . . . . - . - -- - - . . . _ ~ ~ . . - . } , i* 23A6169AH goo t , '* My A REVISION STATUS SHEET i DOCUMENT TITLE IOP-8, UNIT OFF-LINE TO HOT STANDBY OR HOT SHUTDOWN LEGEND OR DESCRIPTION OF GROUPS TYPE: OPERATING PROCEDURE FMF: K 6/7 MPL ITEM NO; A80-3020 l l REVISIONS l A PRELIMINARY ISSUE PER OAB l ERM - DMH-3234 l 9 l l 1 l I i 766 l l l PRINTS TO MADE BY APPROVALS DEPT LOCATION W D TORRES C K TANO OE NUCLEAR ENEROY - sin JOSE CHKD BY ISSUED . H ET 2 F E WILHEMI O A BAYLIS l-I 9101110244-910109 PDR ADOCK 05000605 g PDR 1 4

  - ,~,          -
                            -   . , ,       -m,.m     , , . . . , - .                                           _ ,       .,_._. -        . - , ,  _.                    . 1,._.....-,         ..    .

L

          \

GE Nuclear Energy 23A6169AH SH W i 2

                                -                                                 AW    A TABLE OF CONTENTS DA22
1. SCOPE / APPLICABILITY 3
2. DISCUSSION 3 3 PRECAUTIONS AND LIMITATIONS 3
4. PREREQUISITES 4
5. PROCEDURE 4 5.1 Preparation for Hot Standby or Hot Shutdown 4 5.2 Placing the Unit in Hot Standby 5 5.3 Placing the Unit in Hot Shutdown 6
6. REFERENCES 7 e

ii .

( i(

                     &                        GE Nuclear Energy 23A6169AH Arv      A SH NO . 3 1.0         SCOPE / APPLICABILITY This procedure provides the detalled instructions for proceeding from a generator off line condition to a Hot Standby or Hot Shutdown operating mode.

2.0 DISCUSSION The plant conditions of Hot Standby and Hot shutdowr, are defined as follows: Condition Mode Switch Position Averace Re&Clat CoolantTemnerature Hot Standby STARTUP/ HOT STANDBY Any temperature Hot Shutdown SHUTDOWN >93'O This procedure outlines the steps required to take the reactor to the Hot Standby or Hot Shutdown mode from a generator off line condition as established in IOP 5, " Unit Shutdown to Unit Off-Line, Main Condenser Available". 3.0 PRECAUTIONS AND LIMITATIONS 3.1 If desired to remain in the Hot Standby Mode for an extended period, RPV pressure should be reduced to approximately 28 kg/cm2, if possible, to minimize the feedwater to reactor differential temperature. 3.2 While operating in the Hot Sta,1dby condition with the reactor critical in the heating range, closely n onitor the neutron instruments for Indicated changes in reactivity or power due to xenon transients or temperature changes, insert control rods as necessary to prevent inadvertent power increases 3.3 Operation in the Hot Standby Mode with reactor coolant temperature greater than 93 'O should be wdh the reactor maintained in a vented condition via steam flow through the main turbine bypass valves. This will prevent non condensible oss bulldup in the reactor coolant. 1 ., ,.- , - . . . .

i 1 )

                                                                                                                                         \b
                               &                   GE Nuclear Energy 23A6169 AH nN             A
                                                                                                                           $%D . 4 i

[ t 3.0 PRECAUTIONS AND LIMITATIONS (continued) 1 3.4 Operation of the reactor In the Hot Standby condition should be i

,                                             performed with a minimum amount of steam flow through the turbine bypass valves. This will limit the amount of cold feedwater flow to the                    [

reactor vessel for makeup.  ; 3.5 The cooldown rate should be limited, when reducing pressure, such , that the rate of positive reactivity added by moderator cooldown does not exceed the capability of the control rods to insert negative ' reactivity to maintain the reactor subcritical. 3.6 As each control rod is inserted, verify that the FULL-IN Indication is operable.  ; 4.0 PREREQUISITES Reactor power has been reduced to approximately L10%) in accordance with instructions in IOP.5, ' Unit Shutdown to Unit O 1-Line, Main Condenser Avallable', and the turbine generator is off line. , 5.0 PROCEDURE I , 5.1 Preparation for Hot Standby or Hot Shutdown

                                               ~ 1.1 Select Display Formats [ LATER ).

l 5.1.2 Insert control rods in the selected sequence to reduce reactor j power to appmximately [8%) .  ; t l 5.1.3 Verify that the SRNMS instruments are operating properly as power decreases. 5.1.4 Place the Reactor Mode Switch to the STARTUP/ HOT STANDBY position.

                            .                  5.1.5 Insert control rods in the selected sequence until:
a. All turbine bypass valves are closed with the pressure regulator setpoint of [ 66.5 kg/cm2 ), and
b. The reactor is critical.

s e

  .          ,- , - - . - .. , , . - -     -                       m       _. e   m             ...e. ,  _ , , , , , - -            ,,

1 A 0 Q GE Nuclear Energy ,,,,, sa s RFV A

                                                 . . . NOTE * *
  • Execute step 5.2 to go into Hot Standby or step 5.3 to go into Hot 5.2 Placing the Unit in Hot Standby Execute the following steps to place the unit on Hot Standby condition:

5.2.1 Initiate cooldown by opening a turbine bypass valve to establish a cooldown rate. Maintain the setpoint of the Pressure Regulator (2 kg/cm2) above reactor pressure. Cooldown may be terminated whenever the desired final conditions of tempesture and pressure are reached; however, the goal is 6 maintain reactor pressure at approximately 28 kg/cm2 to mllilmlys the feedwater-to-reactor differential temperature (TE-later). 5.2.2 When reactor pressure is maintained below [40 kg/cm2) and decreasing, control reactor water level in the Low Flow Control mode with one LPCP and one HPCP. Refer to SOP-C31 and SOP-{later). 5.2.3 Continue to insert control rods in the selected sequence. Maintain the reactor critical [ with SRNMS in the heating range). 5.2.4 If the Reactor must be isolated, execute steps in Subsection 5.3 to place the unit in Hot Shutdown. l This step is necessary until a strategy is developed so that the l USIVs can be closed with the reactor suberltical by a specified amount. This condition should correspond to a condition where RCIC can control stable reactor pressure,since with the reactor isolated and if the decay heat exceeds the capability of RCIC, reactor pressure willincrease and a safety relief valve will have to be opened to control pressure. _Upon closure of the safety relief valve, the pressure increase may cause inadvertent criticality if initially the reactor is subcritical by a smaller amount than the positive reactivity caused by the safety telleve valve closure.) t 5.2.5 Refer to IOP 9, " Maintaining Hot Standby or Hot Shutdown" for o rational procedures on maintenance of the Hot Standby ode of operation. l l

        . - ,     - -                      -                            -~     -. __   -

Q GE Nucleer Energy ,,,,,,,,, A

                                                                                                 ,, uo s REV 5.3 Placing the Unit in Hot Shutdown Execute the following steps to place the unit in Hot Shutdown :

5.3.1 Fully insert all control rods in the selected sequence. 5.3.2 If the MSIVs are open and the main condenser is available, initiate cooldown by opening a turbine bypass valve to estab!ish a cooldown rate. Maintain the setpoint of the Pressure Regulator (2 kg4'.mr ] above reactor pressure. Cooldown may be terminated whenever the desired final conditions of temperature and pressure are reached. 5.3.3 When reactor pressure falls below [40 kg/cm2) and decreasing, control reactor water level in the Low Flow Control mode with one LPCP and one HPCP. Refer to SOP-C31 and SOP-(later). 5.3.4 After all control rods are inserted, place the Reactor Mode Switch to SHUTDOWN position. 5.3.5 Reset the Reactor Trip System in accordance with section 6.1 of SOP-C71, " Reactor Trip System'. 5.3.6 If the reactor is to be Isolated:

                                         -      If main condenser vacuum is to be maintained, start the Startup SJAEs and shift the gland sealing stem from the Steam Seal Evaporator to the Aurillary Boller.

Verify that reactor water levf % being co' colled in accordance with steps 5.3.3. Close the inboard MSIVs (B21 F071s) one at a time by placing its control switch to TEST CLOSE position. Close the main steam line drain line containment isolation valves (B21 F141 and F142). When steam pressure downstream of the MSIVs has decreased to (later), similarly close the outboard MSIVs (B21 F072s). Use the SRVs for depressurization and initiate RHR suppression pool cooling if necessary.

O GE Nuclear Energy 23A6169AH SH No 7

!'                                                                AEV    A 5.3 Placing the Unit in Hot Shutdown (continued) 5.3.7 Refer to IOP 9,
  • Maintaining Hot Standby or Hot Shutdown" for operational procedures on maintenance of the Hot Shutdown Mode of operation, or to IOP-4,"Cooldown to Cold Shutdown, Main Cor. denser Available", or to IOP-7, "Cooldown to Cold Shutdown, Main Condenser Not Available", as directed.

6.0 REFERENCES

6.1 General Electric Service Information Letter SIL-208, ' Minimizing Feedwater Nozzle Thermal Duty", Revision 1, October,1978. l