Summary of 961003 Meeting W/Nei in Rockville,Md Re NEI New Organization,New Personnel Who Will Be Involved in Deregulation & Other Financial Issues.List of Attendees Encl
ML20129A476
Person / Time
Issue date: 10/17/1996
From: Stewart Magruder
NRC (Affiliation Not Assigned)
To: Matthews D
NRC (Affiliation Not Assigned)
References
PROJECT-689 NUDOCS 9610220155
Download: ML20129A476 (3)


Text

October 17, 1996 MEMORANDUM T0: David B. Matthews, Chief Generic Issues and Environmental Projects Branch Division of Reactor Program Management Office of Nuclear Reactor Regulation FROM: Stewart L. Magruder, Project Manager Original Signed By:

Generic Issues and Environmental Projects Branch Division of Reactor Program Management Office of Nuclear Reactor Regulation

SUBJECT:

SUMMARY

OF OCTOBER 3, 1996, MEETING WITH THE NUCLEAR ENERGY INSTITUTE (NEI) ON NUCLEAR UTILITY DEREGULATION ISSUES On October 3, 1996, representatives of NEI met with representatives of the Nuclear Regulatory Commission (NRC) at the NRC's offices in Rockville,

-Maryland. Attachment 1 provides a list of meeting attendees.

The purposes of the meeting were to discuss NEI's new organization, introduce the NEI personnel who will be involved in deregulation and other financial issues, and have a brief discussion of the activities in these areas.

Dr. Tom Ryan was introduced as one of the new Senior Vice Presidents at NEI.

He will be responsible for regulatory policy and reform issues. Three members of his staff were also introduced. Mr. Richard Myers will deal with restructuring and deregulation from the financial perspective. His responsibilities include, but generally go beyond the scope of, the nuclear industry. Mr. Steve Floyd will deal with the same issues from the nuclear utility perspective. He will interface with the Federal Energy Regulatory Commission, public utility commissions, and will be the primary point of contact for the MC. Mr. Warren Murphy will be Dr. Ryan's executive assistant.

The NEI representatives stated that an NEI task force was formed to discuss deregulation issues and was providing input to the NEI Executive Task Force on Industry Restructuring. The task force is examining the roles of Independent System Operators, responsibilities for controlling the grid, and other legal and financial issues.

The final topic for discussion was antitrust reviews. Specifically, the need for NRC staff to do the reviews and the effort required for a review was discussed. The group consensus was that the staff is still required to perform them.

Project No. 689 h

Document Name: G:\SLM1\MSUM1003.96 To receive a copy of this document, indicate in the bcx: "C" - Copy without attachment / enclosure "E" - Copy with aittachment %ig' osure "N" - No copy 0FFICE PM:PEGB lr_

e SC:PGEB & dL lBC:PjGR4 ( M NAME SMagruder:sw sure FAkstuTgwtM DMattifews h0.3 JCf DATE 10/tc/96 10/ $f96 N 10/d/96 OFFICIAL RECORD COPY h[ g C[

^

9610220155 961017 ~

PDR PROJ 689 PDR

i DISTRIBUTION:

SUMMARY

OF OCTOBER 3,1996 WITH ;iEl DATED October 17, 1996 Hard Cony Project: File PUBLIC PGEB r/f ACRS OGC SMargruder EMail l FMiraglia RZimmerman AThadani 4 TMartin RArchitzel FAkstulewciz LChandler RWood VMcCree SUttal MMalloy l l

l 1

I l

i

==r

gg Krt

% UNITED STATES t

s* j NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20656-0 T1 4.. +

l October 17, 1996 MEMORANDUM TO: David B. Matthews, Chief Generic Issues and Environmental Projects Branch Division of Reactor Program Management Office of Nuclear Reactor Regulation ,

FROM:

Stewart L. Magruder, Generic Issues Project ManagerM1.j h g and Environmental Projects Branch ( ,

Division of Reactor Program Management Office of Nuclear Reactor Regulation

SUBJECT:

SUMMARY

OF OCTOBER 3, 1996, MEETING WITH THE NUCLEAR ENERGY INSTITUTE (NEI) ON NUCLEAR UTILITY DEREGULATION ISSUES On October 3, 1996, representatives of NEI met with representatives of the Nuclear Regulatory Commission (NRC) at the NRC's offices in Rockville, l Maryland. Attachment 1 provides a list of meeting attendees. l The purposes of the meeting were to discuss NEI's new organization, introduce the NEI personnel who will be involved in deregulation and other financial  !

issues, and have a brief discussion of the activities in these areas.

Dr. Tom Ryan was introduced as one of the new Senior Vice Presidents at NEI. <

He will be responsible for regulatory policy and reform issues. Three members l' of his staff were also introduced. Mr. Richard Myers will deal with restructuring and deregulation from the financial perspective. His responsibilities include, but generally go beyond the scope of, the nuclear industry. Mr. Steve Floyd will deal with the same issues from the nuclear utility perspective. He will interface with the Federal Energy Regulatory Commission, public utility commissions, and will be the primary point of contact for the NRC. Mr. Warren Murphy will be Dr. Ryan's executive assistant.

The NEI representatives stated that an NEI task force was formed to discuss deregulation issues and was providing input to the NEI Executive Task Force on Industry Restructuring. The task force is examining the roles of Independent System Operators, responsibilities for controlling the grid, and other legal and financial issues.

The final topic for discussion was antitrust reviews. Specifically, the need i for NRC staff to do the reviews and the effort required for a review was 1 discussed. The group consensus was that the staff is still required to perform them. j l

Project No. 689 .

1

Attachment:

As stated l cc w/att: See next page

\

l NRC/NEI MEETING ON UTILITY DEREGULATION l LIST OF ATTENDEES October 3, 1996 I

fWE ORGANIZATION Warren Murphy NEI Richard Myers NEI Tom Ryan NEI .

Steve Floyd NEI l Nancy Chapman Bechtel/SERCH 1 David Matthews NRC/NRR Ralph Architzel l NRC/NRR I Robert Wood NRC/NRR Mike Davis NRC/NRR Stu Magruder NRC/NRR  !

Susan Uttal NRC/0GC  ;

4 e

Attachment 1

g

( NEI Project No. 689 o

i cc: Mr. Thomas Tipton, Vice President

Operations and Engineering i Nuclear Energy Institute i Suite 400 4 j 1776 I Street, NW

{

Washington, DC 20006-3708

! Ms. Lynnette Hendricks, Director Emergency Preparedness 1

and Waste Regulation Nuclear Energy Institute 1

Suite 400

, . 1776 I Street, NW

Washington, DC 20006-3708
Mr. Ronald Simard, Director

' Advanced Reactors Programs Nuclear Energy Institute Suite 400 1 1776 I Street, NW j Washington, DC 20006-3708

! Mr. Nicholas J. Liparulo, Manager Nuclear Safety and Regulatory Activities

Nuclear and Advanced Technology Division Westinghouse Electric Corporation l P.O. Box 355 -

4 Pittsburgh, Pennsylvania 15230 t

i

. l l