|
---|
Category:GENERAL EXTERNAL TECHNICAL REPORTS
MONTHYEARML20203N4171986-04-30030 April 1986 Rev 2 to Tdi Owners Group App Ii:Generic Maint Matrix & Justifications ML20100B6361985-01-21021 January 1985 Rept on Welding Allegations ML20094P7631984-08-0101 August 1984 Handwritten Notes Re Auxiliary Bldg & Underpinning Design Including Settlement Stress,Results of Areas of Max Stress & Rigid Body Rotation ML20094P5651984-07-18018 July 1984 Structural Stresses Induced by Differential Settlement of Diesel Generator Bldg ML20091K9701984-05-25025 May 1984 Request for Exemption from Branch Technical Position BTP-CMEB 9.5-1 for Control Panels C43 & C44 ML20091P0351984-05-11011 May 1984 Assorted Documents,Including Request for Equipment Qualification Rept,Inconsistencies in Specs,Review of Us Testing Lab Tests & Bechtel Problems Alert ML20090J5831984-05-0505 May 1984 Documents from TR Thiruvengadam Re 801211 Oral Deposition ML20090L9571984-05-0404 May 1984 Evaluation of Subsidence. Related Info Encl ML20090L6821984-05-0404 May 1984 Documents Produced by TR Thirvengadam for 801211 Oral Deposition ML20090L8291984-05-0404 May 1984 Us Testing Co Response to Bechtel Rept, `Review of Us Testing Field & Lab Const Test Data on Soils Uses as Fill. Related Info Encl ML20090J4831984-05-0303 May 1984 Contents of E Gallagher 3-Ring Notebook Containing Soils Investigation ML20090J4621984-05-0303 May 1984 Contents of E Gallagher 3-Ring Notebook Containing Soils Investigation,Vol 1 ML20090K8381984-05-0202 May 1984 Documents Requested by NRC from Package Presented by G Keeley,Project Manager,But Not Used as Deposition, Exhibits 801023 ML20090K7571984-05-0202 May 1984 Documents Requested by NRC Staff from Package Presented by D Horn,Field QA Engineer,But Not Used as Deposition. QA Sys Evaluation Check Sheets & Related Info Encl,Including Canonie Const Co W/Addendum to QA Program ML20090K8111984-05-0202 May 1984 Documents Requested by NRC from Package Produced by T Cooke,But Not Used as Deposition, Exhibits 801022.Related Info Encl,Including Notes of 790215-16,0801 & 1009 Meetings of Diesel Generator Bldg Task Group ML20084M0241984-04-27027 April 1984 Const Implementation Overview,Weekly Rept 46,840423-27 ML20084L9381984-04-19019 April 1984 Main Control Room Fire Analysis & Evaluation for C31 Control Panel ML20083P8971984-04-17017 April 1984 Midland Independent Design Const Verification Program Monthly Status Rept,Number 11 for Mar 1984 ML20087H9031984-03-16016 March 1984 Midland Independent Design & Const Verification Program Monthly Status Rept Number 10 for Feb 1984 ML20081C3731984-02-29029 February 1984 Seismic Margin Review,Miscellaneous Subsystems & Components ML20084F9061984-02-24024 February 1984 Const Implementation Overview,Weekly Rept Number 37, for 840220-24 ML20084F9261984-02-17017 February 1984 Const Implementation Overview,Weekly Rept Number 36, for 840210-17 ML20080M7381984-02-15015 February 1984 Independent Design & Const Verification Program Monthly Status Rept 9 for Jan 1984 ML20084F8941984-02-10010 February 1984 Const Implementation Overview,Weekly Rept Number 35, for 840206-10 ML20086M2541984-02-0909 February 1984 Balance-Of-Plant Class 1,2 & 3 Piping,Pipe Supports & Valves, Vol IX to Seismic Margin Review ML20084F8391984-02-0303 February 1984 Const Implementation Overview,Weekly Rept Number 34, for 840130-0203 ML20083G8741984-01-0404 January 1984 Structural Evaluation of Midland Diesel Generator Bldg: Assessment of Structural Performance Capability & Serviceability as Potentially Affected by Settlement Induced Cracking ML20083G5871984-01-0404 January 1984 Midland Independent Design & Const Verification Program: Structural Evaluation of Diesel Generator Bldg ML20079E6641983-12-31031 December 1983 Midland Independent Design & Const Verification Program, Monthly Status Rept 8 for Dec 1983 ML20083D9831983-12-0909 December 1983 Auxiliary Bldg Crack Mapping Evaluations for Grillage 8 Initial Jacking & Rejacking ML20083C6631983-11-30030 November 1983 Midland Independent Design & Const Verification (Idcv) Program, Monthly Status Rept 7 for Nov 1983 ML20081J2801983-10-31031 October 1983 Evaluation of Change & Nonconformance Documents,Independent Assessment of Underpinning ML20080D6851983-10-31031 October 1983 Midland Startup Sequence. Related Info Encl ML20082A9691983-10-31031 October 1983 Midland Independent Design & Const Verification Program, Monthly Status Rept 6 for Oct 1983 ML20080T4371983-10-17017 October 1983 Review of Diesel Generator Bldg at Midland Plant ML20085L1141983-10-17017 October 1983 Fifth Monthly Status Rept for Independent Design & Const Verification Program for Sept 1983 ML20080T4221983-09-23023 September 1983 Draft Rept, Review of Diesel Generator Bldg at Midland Plant ML20082G4971983-09-20020 September 1983 Midland Summary Rept ML20080E7881983-08-31031 August 1983 Vol IV to Seismic Margin Review:Svc Water Pump Structure Margin Evaluation ML20076C1621983-08-16016 August 1983 Midland Independent Design & Const Verification Program, Monthly Status Rept 3 for Jul 1983 ML20077A7081983-07-31031 July 1983 Rev 3 to NSSS Equipment & Piping, Vol Viii to Seismic Margin Review ML20077H9721983-07-25025 July 1983 Rev 3 to Diesel Generator Bldg, Vol V to Seismic Margin Review ML20076N2391983-07-15015 July 1983 Midland Independent Design & Const Verification Program, Monthly Status Rept 2 for 830528-830630 ML20072H4981983-06-30030 June 1983 Reclassification of Flued Head Fittings at Midland Plant Units 1 & 2 ML20085D8091983-06-30030 June 1983 Seismic Margin Review,Vol Iii,Auxiliary Bldg ML20024D0181983-06-30030 June 1983 Midland Independent Design & Const Verification Program Monthly Status Rept 2, Second Monthly Status Rept for 830528-0630 ML20076G0631983-06-0202 June 1983 Rev 2 to Midland Energy Ctr Spatial Sys Interaction Program/Seismic Mgjec Project Quality Plan ML20071M3581983-05-27027 May 1983 Midland Independent Design & Const Verification Program Monthly Status Rept 1, Covering Period from Project Inception Through 830527 ML20072E5851983-05-27027 May 1983 Independent Design & Const Verification Program,Monthly Status Rept No 1,Period Inception Through 830527 ML20072M2281983-05-18018 May 1983 Independent Assessment of Auxiliary Bldg Underpinning Weekly Rept 34, for 830508-14 1986-04-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20058L8721992-12-31031 December 1992 1992 Annual Rept,Cpc ML20126D7211992-12-16016 December 1992 Potential Part 21 Rept Re Actual Performance of Rosemount Supplied Bailey Bq Differential Pressure Transmitters Differing from Rosemount Original Spec.Bailey Controls Encl.Evaluation Not Yet Performed ML20246N1221988-12-31031 December 1988 CMS Energy 1988 Annual Rept ML20154J4101988-05-12012 May 1988 Addendum 1 to Supplemental Part 21 Rept 145 Re Potential Problem w/F-573-156 Pressure Sensor/Lube Oil Trip.Initially Reported on 880429.Addl 1-1/8-inch Diameter W/Deep Counterbone in Pressure Head Added to Activate Valve ML20153B6191988-04-29029 April 1988 Part 21 Rept Re Potential Defect in Component of Dsr or Dsrv Standby Diesel Generators Supplied to Utils.Recommends Return of Subj Components in Onsite Warehouse Storage & Suggests Surveillance of Devices Already Installed ML20196J3801987-12-31031 December 1987 CMS Energy Corp 1987 Annual Rept ML20215G2441987-06-16016 June 1987 Part 21 Rept Re Failure of Load Sequencing Equipment Supplied in Aug 1977 During Scheduled Testing.Caused by Open Electrical Connection on One Crimp Lug.Since 1978,insulated Lugs Used on All Equipment ML20216E4721987-05-28028 May 1987 Part 21 Rept 140 Re Potential Defect in Air Pressure Regulators Mfg by Bellofram.Dripwell Gasket May Fail Due to Mismachining of Gasket Seating Surface Causing Loss of Control Air & Starting Air Pressure ML20207R9041986-12-31031 December 1986 CPC 1986 Annual Rept ML20214A0951986-11-14014 November 1986 Insp & Evaluation Re Adequacy of Stabilization Plan,In Response to Util 860701 Request for Withdrawal of Applications to Extend CP & Util Motions Seeking Withdrawal of OL Application ML20215G6801986-10-10010 October 1986 Part 21 Rept Re Vendor Tests of air-operated Diaphragm Valves Revealing Natural Frequencies Less than Required Values of 33 Hz.Initially Reported on 841227.No Adverse Effects Noted During Testing ML20215G5351986-10-10010 October 1986 Part 21 Rept Re Vendor Tests of air-operated Diaphragm Valves Revealing Natural Frequencies Less than Required Values of 33 Hz.Initially Reported on 841227.No Adverse Effects Noted During Testing ML20205F6141986-08-13013 August 1986 Part 21 Rept Re Connecting Rod Bolts for Dsrv Engines.Listed Procedures Recommended for Next Connecting Rod Insp, Including Replacement of Bolts Due to Cracked Threads & Large Grooves & Galls in Threads ML20206U0591986-07-0202 July 1986 Part 21 Rept Re Potential Defect in Component of Dsrv Standby Diesel Generators,Involving Problem W/Fastening of Engine Connecting Rod Assembly Which Could Result in Engine Nonavailability.Procedure Will Be Issued by 860718 ML20197H2581986-05-0808 May 1986 Part 21 Rept 135 Re Defect W/Lube Oil Sump Tank Foot Valve of Standby Diesel Generator.Caused by Extrusion of Liner Matl Due to Overpressurization.Corrective Actions Being Developed.List of Affected Sites Modified ML20203N4171986-04-30030 April 1986 Rev 2 to Tdi Owners Group App Ii:Generic Maint Matrix & Justifications ML20205N6811986-04-14014 April 1986 Final Part 21 & Deficiency Rept 86-03 Re Consolidated Pipe & Valve Supply,Inc Certified Matl Test Repts.Initially Reported on 860321.Six raised-face Orifice Flanges Statused & Segregated Per QA Procedures ML20205N7381986-04-14014 April 1986 Interim Deficiency & Part 21 Rept 86-02 1 Re Elastomer Liner in Clear Flow Co Foot Valves Used in Lube Oil Sump Tanks of Tdi Diesel Generators.Initially Reported on 860321. Action Will Not Be Pursued Unless Facility Reactivated ML20140H5991986-03-24024 March 1986 Second Interim Deficiency Rept 86-01 Re Error in Bechtel Computer Analysis Program.Initially Reported on 860121.No Corrective Actions Will Be Pursued & No Further Repts Will Be Submitted Unless Project Reactivated ML20154N3431986-03-10010 March 1986 Initial Part 21 Rept 135 Re Potential Problem W/Lube Oil Sump Tank Foot Valve of Dsrv Standby Diesel Generator for Facilities.Cause Not Determined.Recommends Utils Inspect Condition of Foot Valve Liners & Notify Tdi of Findings ML20153F5391986-02-14014 February 1986 Interim Part 21 & Deficiency Rept Re Error in Bechtel Computer Analysis Program ME101.Initially Reported on 860121.No Corrective Actions or Further Repts Will Be Submitted Until Project Reactivated ML20137N6101986-01-10010 January 1986 Interim Part 21 & Deficiency Rept 85-08 Re Isolated Failures of Betts Spring Co Intake & Exhaust Valve Springs Reported by Tdi.Initially Reported on 851218.Corrective Actions Will Be Pursued If Units Reactivated ML20141N8361985-12-31031 December 1985 CPC 1985 Annual Rept ML20138M3891985-12-12012 December 1985 Topical Rept Evaluation of Rev 1 to BAW-1847, Leak Before Break Evaluation of Margins Against Full Break for Rcs.... Rept Presents Acceptable Justification to Eliminate Dynamic Effects of Large Ruptures in Piping ML20198C4981985-11-0606 November 1985 Part 21 Rept Re Potential Defect in Dsr or Dsrv Standby Diesel Generator Intake & Exhaust Valve Springs Mfg by Betts Spring Co.Users Recommended to Inspect Engines for Broken Springs & Identify Original Mfg ML20138B9531985-10-0909 October 1985 Interim Deficiency Rept Re Larger than Anticipated Util Movement Where Freezewall Crossed safety-related Utils at Monitoring Pits 1,2,3 & 4.Initially Reported on 850917.No Action Will Be Taken ML20138C3111985-10-0808 October 1985 Interim Deficiency Rept Re Limitorque motor-operated Butterfly Valves Not Opening Electrically After Closed Manually.Initially Reported on 850912.No Corrective Actions Will Be Taken Unless Facility Reactivated ML20138C3251985-10-0808 October 1985 Interim Deficiency Rept Re Loose Set Screws on Anchor Darling Swing Check Valves & Disc Nut Pin Problems Causing Inoperability.Initially Reported on 850912.No Further Corrective Action Will Be Taken Unless Facility Reactivated ML20132B0261985-09-0303 September 1985 Part 21 Rept Re Possibility of Engine Ingestion of Unwelded Part in American Air Filter Standby Diesel Generator Intake Silencer.Immediate Hold Should Be Placed on Diesel Engines/Intake Silencers Not Yet in Svc ML20132D3191985-07-10010 July 1985 Interim Part 21 & Deficiency Rept Re Rupture During Testing by Wj Woolley Co of Inflatable Seal,Mfg by Presray Corp,Used in Personnel Air Locks in Reactor Containment Sys.Initially Reported on 850614 ML20129G0601985-04-26026 April 1985 Interim Deficiency Rept Re Potential for Cracking of Check Valves in on-engine Mounted Starting Air Piping of Tdi Diesel Generators.Initially Reported on 850401.Cause Not Determined.No Corrective Actions.Related Correspondence ML20112J3951985-03-22022 March 1985 Interim Part 21 & Deficiency Rept Re Failure of Gulf & Western MSIV Actuator Latch Roller Bearing.Matter Will Not Be Pursued Unless Plants Reactivated ML20100B6361985-01-21021 January 1985 Rept on Welding Allegations ML20114D3571984-12-21021 December 1984 Interim Deficiency Rept Re Diesel Fuel Oil Tank Soils Borings.Initially Reported on 841121.No Corrective Actions Necessary Due to Present Project Shutdown ML20100K9791984-11-27027 November 1984 Part 21 & Interim Deficiency Rept Re Ruskin Mfg Co Interlocking Blade Fire Dampers.Initially Reported on 841121.Corrective Action Will Not Be Pursued & No Further Repts Will Be Made Unless Plant Reactivated ML20100D9841984-11-21021 November 1984 Deficiency Rept Re Diesel Fuel Oil Tank Boring Logs.Util Response to Dow Chemical Co 841113 Request for Admissions Encl ML20100E2621984-11-15015 November 1984 Interim Part 21 & Deficiency Rept Re Rosemount 1153 Series B Transmitters Potentially Leaking.Initially Reported on 841010.Four Units Shipped to Facilities.Corrective Actions Will Not Be Pursued ML20100E4451984-11-15015 November 1984 Interim Deficiency Rept Re Cardinal Industrial Products Corp Spare Studs Received W/O Ultrasonic Exam.Initially Reported on 841010.Corrective Actions Will Not Be Pursued Unless Midland Reactivated ML20100E2371984-11-15015 November 1984 Interim Part 21 & Deficiency Rept Re Tdi Fuel Control Level Cap Screws.Initially Reported on 841010.No Corrective Actions Will Be Pursued & No Further Repts on Subj Made Unless Midland Reactivated ML20099E3531984-11-0909 November 1984 Interim Deficiency Rept Re Small Bore Piping Anchor Design. Initially Reported on 840816.Listed Corrective Actions Will Not Be Pursued & No Further Repts Will Be Made Unless Facilities Reactivated ML20093C3211984-10-0101 October 1984 Rev 0 to QA Program Plan for Shutdown Phase ML20093H3961984-08-0202 August 1984 Interim Deficiency Rept Re Seismic Qualification of Power Supplies for Eccas & Ni/Rps Equipment.Initially Reported on 840705.No Activity Being Currently Pursued.No Further Repts Will Be Made Unless Facilities Reactivated ML20093H8521984-08-0202 August 1984 Interim Deficiency Rept Re Field Installation of Itt Grinnell Struts & Extension Pieces.Initially Reported on 840705.No Activity Being Currently Pursued.No Further Repts Will Be Made Unless Facilities Reactivated ML20094P7631984-08-0101 August 1984 Handwritten Notes Re Auxiliary Bldg & Underpinning Design Including Settlement Stress,Results of Areas of Max Stress & Rigid Body Rotation ML20093H8111984-07-27027 July 1984 Final Part 21 & Deficiency Rept Re Capstan Springs in Mechanical Shock Arrestors Supplied by Pacific Scientific. All Suspect Shock Arrestor Capstan Springs Will Be Inspected for Cracks & Defective Springs Replaced ML20096A7781984-07-27027 July 1984 Final Deficiency Rept Re Defective Capstan Springs in Pacific Scientific Mechanical Shock Arrestors.Initially Reported on 840106.W/o Description of Investigation & Corrective Actions.Related Correspondence ML20093H8871984-07-20020 July 1984 Interim Deficiency Rept Re Reactor Coolant Pump Seals & Seal Covers.Initially Reported on 840622.No Activity Currently Being Pursued.No Further Repts Will Be Made Unless Facilities Reactivated ML20094P5651984-07-18018 July 1984 Structural Stresses Induced by Differential Settlement of Diesel Generator Bldg ML20090G2141984-07-18018 July 1984 Idcvp:Control Room HVAC Sys Performance Requirements, Draft Topical Rept ML20093H4751984-07-17017 July 1984 Interim Deficiency Rept Re Core Flood Line Piping Supports in Reactor Pressure Vessel Connection Supplied by Bechtel. Overstressing Could Occur in Pipe Supports.No Commitment Made for Further Repts 1992-12-31
[Table view] |
Text
_ _ _ _ __ _
. J.O. NO. 14358 Midlcnd Plcnt Units 1 cnd 2 O O l Independent Ascessment of Underpinning :
Weekly Report No. 31 April 17, 1983 through April 23, 1983 -
Personnel on Site Stone & Webster Michigan, Inc.
W. Kilker 4/18 - 4/23 A. Scott 4/21 - 4/23 P. Barry 4/18 - 4/20 .
A. Lucks 4/19 - 4/21 ;
Parsons, Brinckerhoff Michigan, Inc.
P. Parish 4/18 - 4/22 !
Meetings Attended Date Represented Purpose 4/18 Stone & Webster Daily Meetings through Bechtel 4/22 Consumers Power I Parsons (4/19 - 4/22) 4/21 Stone & Webster " Dry-Run" Pre-Bechtel sentation of Load /
Consumers Power Settlement Data Mergentime Activities Construction -
Pier W12: No activity. ,
Pier W9: No activity.
Pier Wil: The upper and lower leveling plates were installed and grouted. Bearing plates,jackstand, and jacks were placed and the Carlson meter electrical connections and telltale plates, box and dial gauge installations were completed. The pier is essentially ready for load transfer.
Pier W8 drift: Excavation and support of the drift advanced to within 6 ft. of completion. The excavated material consisted of approximately 2 ft, of unreinforced concrete underlain by clay fill with some zones of sand fill.
Pier E12: Routine rejacking based on structure movement was initiated on April 22.
The 110 percent of specified load was re-established by active jacking at which time a loosening of the driving wedges required that the 0.01 inch per 48 hour5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> deflection criteria be satisfied by maintaining active jacking.
1 I
i l
- i. 8307140365 830630 1 l PDR ADOCK 05000329 i O PDR
. . Midland Plant
. Units 1 and 2 Independent Assessment of Underpinning 2 Pier E9: Routine rejacking based on structure movement was initiated on April 22.
The procedure followed and results obtained were similar to those at pier E12. l Pier Ell: The lower leveling plate bearing plates, telltale bearing plate, box and dial gauges, jackstands and jacks were installed. Load transfer was initiated on April 23 Pier E8 drift: The drift excavation was completed. Installation of the final drift set was completed on April 23 The excavated material consisted of 2 ft.
of unreinforced concrete underlain by clay fill. An abandoned well screen and a deep seated benchmark casing were encountered near the west limit of the drift excavation.
Service Water Pump Structure: Granular backfill was placed and compacted to permit equipment access. Two exterior probe holes were then completed and grouted. The completioncf. coring the concrete floor slab for dewatering wells is delayed pending Engineering resolution of reinforcement bar interferences. '
Auxiliary Building Beam Fix: The major portion of the beam connection nodifications at El. 646, 659 and 704 were completed.
Quality Control, Documentation and Records:
- 1. Witnessed QC inspection of dry-pack grouting the upper level bearing plate at pier W11.
- 2. Witnessed the QC inspection of Hilti bolt holes along a portion of pier E8 drift.
3- 3 Observed the verification survey of centerline of pier W11.
- 4. Witnessed QA/QC sign-off inspection at pier E11 prior to load transfer.
Observations Construction - The installation of bearing plates, jackstands and jacks at piers E/W11 was done in a satisfactory manner. The E/W8 drift excavations were properly advanced and supported. Progress was frequently slowed by the curing time required for grout placed in abandoned Hilti bolt holes.
The rejacking operations at piers E9 and E12 and the initial load transfer at pier E11 were properly executed. The response of the load level at pier E12 during the rejacking of E9 and of load levels at both piers E9 and E12 during the loading of pier E11 demonstrated the sensitivity and interaction of the pier system to the application of loads up to 35 ft. distance.
Quality Control. Documentation and Records - The Team observations of the QC activities indicated the inspections were being properly done. The response of the field organization to the turbine building settlement near pier E8 was in accordance with procedural requirements.
The Assessment Team received a response to NIR #6 concerning the spacing requirements for pi.er lagging sets. In summary, the response stated that the Contractor has agreed with the Subcontractor to use the wider spacers conditions permitting. How-ever, no change would be made to the procedure. The Assessment Team appreciated the concern of the Contractor to changing the procedure. Nevertheless, it is our opinion that wording could be incorporated into the procedure that would assure the use of wider spacers unless certain dimensional orground conditions dictate otherwise.
' ~~~~~~~
J. O. NO. 10359 Miditnd Pltnt )
Unito 1 cnd 2 # (~^
x-
Ind;p;ndsnt Assessm:nt of Underpinning 3 The Assessment Team issued NIR #10 concerning the testing of the frequency of concrete vibrators. ACI 309 requires that concrete vibrators should be checked in concrete. The Contractor has been testing vibrators in air.
Design Work Packages - The Assessment Team performed an overview of the design work packages for the auxiliary building beam fix, the UAT modification and the E/W8 grillage beam installation. The auxiliary building beam fix and UAT packages were judged to be complete. With respect to the grillage beam installation, it was recommended that an additional existing construction procedure and instrumentation procedure be referenecd in the work package summary, and one signature block had not been signed on the installation procedure.
Non-Conformance Identification Reports Status of previous issues: (NIR numbers no longer listed have been closed-out.)
NIR NO. Description Date (Opened) (Closed) 5 Concrete Mix 2/10/83 Qualification 6 Lagging spacers 3/21/83 1
7 Backpacking Material 4/5/83 in Wet areas-Pier W11 8 Load Transfer Meth- 4/5/83 ,
! odology-Pier E12 l l l 9 Release of Pier W9 4/13/83 for Load Transfer 10 Verification of 4/21/83 Vibrator Frequency
!$cfb*lt eN Project Engineer ggg>
g Project Manager gjgG m
-- .. - _ . . - - . . .- _. .- - -= . . - . - . . _ . - .
- O O DAILY INDEPENDENT ASSESSMENT TEAM MEETING Date: April 18, 1983 r
i Attendees: Bechtel Stone / Webster MPQAD CPCo E. Cviki W. Kilker R. Sevo G. Murray j J. Fisher P. Barry l
J. Gaydos
, 1. J. Fisher reported the auxiliary building beam fix has been started.
i
- 2. A general discussion was held on the drift set Hilti bolt installation impact on time needed to advance the drifts to the respective piers.
At most drift set plate locations, the Subcontractor has been required to drill numerous additional holes due to encountering steel before full penetration was achieved. The abandoned holes require grouting and cure time before torquing the successful holes. I 3 In response to an earlier inquiry (see notes of April 14) by P. Barry on the NCR on a drift set in pier E12, J. Fisher stated that FSO has dis- i positioned it.
- 4. W. Kilker presented written inquiry on the load transfer interaction effects 3;. on adjacent piers. See attached sheet. J. Fisher will arrange for a separate discussion session with the Subcontractor.
- 5. J. Fisher stated he will measure wedges on E/W9 piers and report on use of various sizes.
- 6. In response to an earlier observation (see notes of April 15) by P. Barry, J. Fisher said that routine rejacking in the future will not necessarily result in a jack load reduction as was done on the April 14 rejacking of pier W9.
- 7. P. Barry discussed the Assessment Team observations on the UAT work package.
A question arose if any grouting of the soil outside the pipe is anticipated prior to opening the pipe wall. If so, the work package submittal may need revision.
a_-
? , r
. . y
(
e'
(
ASSESSMENT TEAM CUESTIONS CONCE?.NING AFFECT OF .
FIER INTERACTION As per specifications it appears that inadvertent unicading cf piers due te the leading of an adjacent pier is prevented by the criteria that requires rejacking at piers when the settlenent exceeds .01 inch in a continucus 43 hcur period. This could nean however, that while a pier is being icaded adjacent pier: may require rejacking at the same time and possibly affect the acceptance criteria of load transfer for the pier being installed. This would be critical where adjacent piers are close and/or have areas of overlapping pressures.
Will the load on piers adjacent to a pier undergoing initial load transfer te maintained by active jacking or will the application of a. rejacking
,f, i
load to these piers be determined by the deflection criteria?
-=.. . .. : ..
b
e u O O D,AILY INDEPENDENT ASSESSMENT TEAM MEETING Date: April 19, 1983 Attendees: Bechtel Stone / Webster MPQAD CPCo i E. Cviki W. Kilker W. Lytle G. Murray J. Fisher P. Barry J. Gaydos Parsons P. Parish
- 1. J. Fisher stated the meeting with Mergentime on the effect of jacking on adjacent piers will be scheduled for the week of April 25.
- 2. J. Gaydos reported that on piers E/W9 all driven wedges were originally 4 ft. long. However, interferences with drift sets required cutting of the ends after they were driven.
3 J. Fisher stated that Resident Engineering had informed him that the UAT work package would not require a change since no grouting will be done prior to opening the pipe wall.
5..
- 4. W. Kilker stated he met informally with J. Northrup. J. Northrup reported making progress in both clarifying inspection requirements and changing the welding requirements particularily on lagging and telltale boxes.
- 5. W. Kilker reported the Assessment Team had received a response from FSO on NIR #6. G. Murray requested a copy for CPCo in order to facilitate the close-out of the item. W. Kilker will report on the response within a day or so.
- 6. E. Cvikl said that to his knowledge no QARs had been issued on the Assessment Team NIRs 6, 7 or 8. W. Lytle will investigate.
- 7. P. Parish questioned if the design considerations had taken into account the extent of "open-area" under the turbine building that now exists. J. Fisher said Mergentime had verified with Project Engineering last month that the i
situation had been anticipated and analyzed.
- 8. E. Cvikl reported that a roof crack in the northwest portion of the SWPS had reached a width of 33 mils and that as an action the investigative
! agency was being alerted to perform an evaluation.
l 9 J. Fisher questioned if the Assessment Team had any concerns about the sampling of concrete at the end of the pumpline. W. Kilker and P. Barry replied that the sampling location does not concern the Team from a quality standpoint.
Any opinions expressed by the Team to date on concrete sampling locations were from the standpoint of logistics and expediency of the operation.
- 10. E. Cviki reported that Project Engineering is responding to the question of checking the vibrator frequency in air versus in concrete.
e O o DAILY INDEPENDENT ASSESSMENT TEAM MEETING Date: April 20, 1983 Attendees: Bechtel Stone / Webster MPQAD CPCo J. Fisher W. Kilker R. Sevo ------
J. Gaydos P. Barry S. Lucks Parsons P. Parish
- 1. J. Fisher stated that with respect to the UAT work package it has been determined that Mergentime will cut the pipe access later. The present work package will not include that activity.
- 2. R. Sevo requested a clarification on recently expressed Assessment Team concerns about concrete sampling. P. Barry and W. Kilker indicated that end of the pumpline sampling is of no quality concern to the Assessment
.. Team.
7 3 P. Barry said he had discussed his comments on the constructability package for grillages at piers E/W8 with FSO.
- 4. J. Gaydos responded to an earlier concern over the driving wedge length used at piers E/W9 All wedges conformed to the drawing requirements when driven but were later cut-off as required to avoid interfences with drift sets.
L
o
. O DAILY INDEPENDENT ASSESSMENT TEAM MEETING Date: April 21, 1983 l Attendees: Bechtel Stone / Webster MPQAD CPCo J. Gaydos W. Kilker R. Sevo G. Murray E. Cvikl S. Lucks Parsons P. Parish
- 1. W. Kilker advised that the FSO response to NIR #6 on lagging spacers had been received. The response stated that in general the Subcontractor had been advised, in general, to use the wider allowable spacing. The Team is in agreement with this recommendation but feels the procedure should be changed to reflect the recommendation. NIR #6 will remain open.
- 2. G. Murray related that based on a recent discussion with the NRC the pier load test at W11 maybe delayed. The work permit for performing the load test has not been signed off by the NRC.
_. 3 E. Cviki reported that since last evening (April 20) the turbinebuilding,
"~ as monitored by the deep-seated benchmark nearest to pier E8, has undergone a few mills settlement and that further settlement will necessitate rejacking a pier E9
- 4. E. Cviki said the Resident Engineering group will meet to discuss presentation of data proposed for the NRC during their site visit next week.
i
o O DAILY INDEPENDENT ASSESSMENT TEAM MEETING Date: April 22, 1983 Bechtel Stone / Webster MPQAD CPCo Attendees:
E. Cviki W. Kilker R. Sevo -----
J. Fisher A. Scott J. Gaydos Parsons P. Parish i
- 1. E. Cviki reported E9 and E12 piers will be rejacked today because a turbine building benchmark indicated the deflection criteria had reached the action I level.
- 2. J. Fisher said the benchmark pipes will be protected in the excavation from the construction operations.
3 E. Civkl said Engineering will establish the criteria for testing the concrete vibrator and forward this to QC.
- 4. There was a general discussion of the work released at the UAT.
f
)
)
O U
<mlNCIPAL STAFF Ce a4 azt2F p/RA SCSp L,, jg STONE & WEBSTER MICHIGAN, INC. A/RA pao q PPRP sto P.O. Box 2325. BOSTON. M ASSACHUSETTS O2107 DE ML ,4
,0L .
FILE /a /
United States Nuclear Regulatory Commission April 27, 1983 Midland Site Resident Inspection Office Route 7 J.O. No. 14358 Midland, MI 48640 Ref. MPF 31 Attention Mr. R. Cook RE: DOCKET NO. 50-329/330 MIDLAND PLANT - UNITS 1 and 2 INDEPENDENT ASSESSMENT OF UNDERPINNING REPORT NO. 31 -
A copy of the Independent Assessment of the Auxiliary Building Underpinning Weekly Report No. 31 for the period April 17, 1983 through April 23, 1983, is enclosed with this letter. Included as attachmenta, are the minutes of the daily meetings held during the week between mambers of the Assessment Team and Site Engineering, Construction, and Quality Assurance personnel.
If you have any questions with respect to his report, please contact me at (617) 589-2067).
Very truly yours, M
g A. Stanley Lucks Project Manager Enclosures ASL/ka APR 2 9 M
.