ML20095K975
| ML20095K975 | |
| Person / Time | |
|---|---|
| Site: | Fort Saint Vrain |
| Issue date: | 12/15/1995 |
| From: | PUBLIC SERVICE CO. OF COLORADO |
| To: | |
| References | |
| NUDOCS 9512290351 | |
| Download: ML20095K975 (24) | |
Text
ENCLOSURE 2 FORT ST. VRAIN PROJECT UPDATE Presentation to tite Nna6lee?
= Rem,a c kba r .
LrrSTitM 4 4 LiS S?O M 4 i:
290026 O Public m s.,*,c - Service-y,c.,.
w Jy 0 1 f0A"%8S!dM$$$jg7
I l
FORT ST. VRAIN UPDATE l
PUBLIC SERVICE COMPANY OF COLORADO PRESENTATION TO THE ,
s NUCLEAR REGULATORY COMMISSION December 7,1995 (Washington)
December 15,1995 (Region IV)
L____________________________________ __ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __ _ _ _ _ _ _ _ _
AGENDA
- Decommissioning Status Safety and Radiological Performance
- Final Release Survey
- Spent Fuel Status -- DOE Agreement
- PSCo Corporate Merger
- Repowering Status
- Present Concerns l
- Conclusions 1
l l
- Supplemental Information Page 1
DECOMMISSIONING STATUS Page 2
PRESTRESSED CONCRETE REACTOR VESSEL (PCRV)
~
/
49 CLN y , .y L g ge C.
r p
Wy:~P7 s ,Nd - .-
- CONTROL R00 DRIVES
/,/g) 5 P
!, I
, ACTWATED CONCRETE l- g e
D% $ l l
A !. .
l '
fl i
- 880E REFLECTOR BLOCKS
~
. . ~ FUS, ELEMENTS
. ~ i I pg,,N 111 d ..
~
CORE SUPPORT H
h -
- SNM GMMAM MODULES l FLOOR --- , /
Pwl /
i M w '
l
[ / HEUUM CIRCULATORS l u '
'/
/
UNER '
31' die.
hY '
l
,- - i N/
%- BOTTOM HEAD PENETRATIONS G/
\.
Page 3
+ ,
r k I
&y/
'*E
!/ pt. iI
Y \T Y >
- A SERIES OF VERTICAL k5 E <
j \
CONCRETE CUTS ARE Y) , .yi '
' MADE USING THE
- VERTICAL TENDON
'd ,
l n TUBES AS CONDUlTS l, ,% \ < FOR THE DIAMOND
, m AA 4> '
WIRE SA W.
V P ~~~
/ ,Q THE CONCRETE SLABS
' \\l 9 ARE REMOVED AND
\
\
TTI PACKAGED FOR I
, SHIPMENT.
I i
i I l I l io i N I
f i
i ces q o
l g j h
%f nn Y
PCRV ACTIVATED CONCRETE REMOVAL Page 4
l WW g<j fft? j 1
.J t.
l' ,4 M
V -
h Q 'a 8 y h 0
- j, l AFTER FINAL
- sJ CLEAN-UP THE jl* 'sur PCRV WILL BE l
,% \ LEFT AS SHOWN
$' &@ p_
q , STEEL PLA TE h : CLOSURES WILL
~
~x
, BE MADE FOR
& i 'Y i THE TOP HEAD h3 '
J AND THEPCRV
\ WILL BE LEFT
,G
' G '
. (;
FOR LONG ' TERM STORAGE FOR
~
, \ DISMANTLEMENT i
IN THE FUTURE.
M N, b,'ck '
,y -
,,9 && . i
\,,
PCRV FINAL DISPOSITION Page 5 L.___. . . . . _ . _ . . . _
DECOMMISSIONING STATUS PROGRESS SINCE MAY 1995:
- Removal of 12 Steam Generators Complete
- Removal of Activated Upper Beltline Concrete Complete
- Removal of Fuel Storage Wells Complete
- Removal of Shield Water System Complete, Release of Shield Water Complete
- Final Survey of Buildings Outside Restricted Area Complete
- PCRV and BOP Dismantlement, Decontamination Activities Are Approximately 90% Complete
- Characterization Surveys and Decontamination of Reactor Building Structures and Systems Are in Progress Page 6
DECOMMISSIONING STATUS REMAINING ACTIVITIES:
- Removal of Lower Beltline Concrete from PCRV
- Removal of Lower Plenum insulation
- Decontamination of Embedded Piping and PCRV Internal Surfaces
- Characterization and Decontamination of Reactor Building Surfaces and Systems
- Remove Reactor Building Ventilation System and Liquid Waste System
- Final Radiological Survey l
Turbine Building Surfaces Buildings and Areas inside Restricted Areo Unaffected Systems Effluent Pathways Reactor Building Surfaces Affected Systems
- Open Land Areas l
l Fr Je 7
, D NTE: 12-06-95 i PCRV n
N B7 B8 M ..- . R 8 .. M
... '0'b b &-6? '
' ~
B5 6:j-5') ~'
' j_jR
, B10
. l b
, -4 ;-
~
. . . . . .. g41:
B4 lL .'.???.., {
') 1.: ... B11 m.
Aip - j,jd.,.=.
Q-3iu 41 -3 } 0
...s. ..~.
. ..; - i h g
83 b 312 3 (1-2 '.). . .
... ,.. $ .2 jti R23-1 : :2-1 ;,at i
B2 s.. g1 NOTE: RADIAL CONCRETE CUT Bi3 B1 14 R2 IS IN PROGRESS AND BACK CUT B4 IS ALSO IN PROGRESS.
% CUT COMPLETE PREPARED BY BOB GUNNERSON
.___ .e
l ilil\I!i l !
N ,
D O l
C N E a I D g ,
0 E R N
S O x -
x I
I E
e T T l
E R
A L
x 6
4 J S E
C U i x C
1 J I R
6 0 N' x x
I I C A
M i
M M I
D E U x A R P
T A
N E x M R V
I I
P ,
x l O T
T C R x I
F A R
A d0 x J E L
x N
E U v D
I G
I E
V : L i N M A
O M .
l E E 0 T R I S . 4 5 O
& P i
E A S R l
C' .
L 5 J R 4 I Y 9 C E 1 J V mHe R l -
N U I S A . L A
M e N m I i
m F F E m a
l R T J O E S O L H m D
Y F
C E N l
K T O N C
(
0 S
R E
T U
D R)
M U
S D
E I M I
t E A R l
.S O 4
4 J mKC C 9 O V 1 J mL R C
I M
.G
. P l .R
.OI A C E
_ M L l f m
_ l F .tR m.
J I m u
D
.N
.EN S l
.A E N .M G l R N E A 0 E P H S IT C
F E E S H I R E l
F R C P
/ N A W A O l D O P C 3 S N C U S J O -
4 R D
-P 9 O C A D 1 J T E A E S E E i
C H E L S M R V E mI L P C l O R U F T C O G A E A P I &
R t F
E h f N E L 0 _
N L v 1 E _
l E I u I F G F H A E I
E L J M R -Nl U A i )
L E A E D m. I H I
S mN C N K .O S l C mC L 2 0 O L .E A 4
4
.D (
5 sP 1 9
l .O G B .B I A R S O A
l J
2 jll f l
OL eDed a!!!!!!!!!!
= MMMGMM%\\\\\\N i
~
a M@@MMM\\Mx\\\N i
- x MM@MMEMNNW i a
e MMM@MENNNNNNNY MMMMME\\\\\\\\ i N
$l m
e 8@MMMMh\\\\\\\N 5 g
a x MMM&\\\\\\\\\%\\\1 ! <
Sa MMMMENNNNNNNN\\\\\\\N e to !
5e MMMMMMM i H e M@MWN: h e M M ANNNNNNNNN M % \\N g e M M M & % \\\\ M M e s' M M E \\\\\\\\ % \\\1 O HVAC SYSTEMS MM'@Mh\\MN\\\\\\3 O
SAFETY AND RADIOLOGICAL PERFORMANCE OCCUPATIONAL RADIATION EXPOSURES:
(Person-REM)
Total Estimate per Decommissioning Plan 433 Expected Total Project Dose 392 Actual Dose to 12/1/95 366 l
l LOW LEVEL RADIOACTIVE WASTE SHIPPING:
l (Cubic Feet Shipped from FSV) l l
l Total Project Estimate 245,000 Shipped to 12/1/95 218,600
- 71,380 Curies l
- 442 Shipments l
Page 11
SAFETY AND RADIOLOGICAL PERFORMANCE (Continued)
TIME WORKED IN RADIOLOGICALLY CONTROLLED AREAS (RCA):
(Porson-Hours)
Actual RCA Hours to 12/1/95 573,000 Original Project Estimate 367,100 (per Decommissioning Plan)
PERSONNEL CONTAMINATIONS:
(Contaminations per 10,000 RCA hours)
! FSV 4.5 PWR Outages 6.5 BWR Outages 14.5 l
LOST WORKDAY INDICATORS:
- Only 3 Lost Time Work injuries
- Lost Work Day incidence Rate (per 200,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br />):
FSV 0.47 l Typical Construction Projects 6.9 (National Bureau of Labor Statistics)
- Severity Rate (per 200,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br />):
l l FSV 45.7 l l i Typical Construction Projects 132 Page 12
FINAL RELEASE SURVEY
- 1. REMAINS MAJOR CHALLENGE OF PROJECT
- 2. PROGRAM OVERVIEW:
FSV Buildings, Systems, and Land Areas Divided into 9 Survey Groupings Groups A through I include:
l l
- 289 Survey Packages 1
- 100,300 Measurement Locations
- 390,900 Measurements f
Page 13
l l
l FINAL RELEASE SURVEY (Continued)
- 3. EMBEDDED PIPING REPRESENTS SIGNIFICANT CHALLENGE
- 30,000 feet of Small Diameter Piping
- 5% of Measurements May Exceed Fixed Contamination Site Specific Guideline Values (SGLV)
> FSV SGLVs are 4,000 dpm/100 cm2(Average),
12,000 dpm/100 cm 2(Individual)
> All Measurements Are Expected < 50,000 dpm/100 cm 2After Aggressive Decontamination
- PSCo/WT Submitted Proposed Treatment on October 12,1995:
- Aggressive Decontamination
> Fill Piping With Grout That Exceeds SGLVs
> NRC Approval of Measurements That Cannot Be Reduced Below 100,000 dpm/100 cm 2
> Requested Approval By December 31,1995
- Dose Consequences 2.4 mrem Per Year --
from 2
100,000 dpm/100 cm
- Cost of Additional Decontamination or Removal Efforts to Meet SGLVs is From $3.1 Million to $33.9 Million
-- Not ALARA Page 14
FINAL RELEASE SURVEY (Continued)
- 4. BACKGROUND Widely Varying Background Complicates Demonstration That Exposure Rate Meets Release Criteria
- Release criteria is 5 pR/hr above background
- Background varies from 5 - 30 pR/hr
- WT developing methodology including use of in situ gamma spectrometer
- Need to Ensure NRC's Confirmatory Survey Uses Same Survey Protocol, Groundrules as PSCo l
S. CONCLUSION l
- NRC Inspected Final Survey Program September 25-28
> Reviewed Procedures and Records
> ORISE Performed independent Field Measurements
> GPU Independent Measurements Were Consistent With SEG, Expect Consistent with ORISE
> NRC Found that Program Was Being implemented l in Sound Manner i > Survey Packages Were Thorough, Although incomplete At Time of Inspection
- PSCo Appreciates NRC Efforts to Perform Confirmatory Survey in Parallel With PSCo/WT Final Survey --
Significant Savings in Time and Possible Rework
- Excellent Communications With NRC Staff Page 15
SPENT FUEL STATUS - DOE AGREEMENT PSCO AND DOE HAVE REACHED AGREEMENT IN PRINCIPLE
- DOE Takes Title to 2 New Spent Fuel Shipping Casks
- DOE Responsible For All Future Costs Before and After Title Transfer, e.g., Maintenance, Defueling, Decommissioning, Regulatory Changes l
l l
Page 16
PSCo CORPORATE MERGER 1
On August 23,1995, PSCo and Southwestern Public Service Company (SPS) of Amarillo, Texas Announced Intent for Merger, Under New Holding Company
- PSCo Will Remain an Entity Under New Holding Company, and Will Retain Existing Licenses
- Current Financial Assurance Provisions Unchanged
- SPS Has Substantial Generating Capacity with Primarily Coal and Natural Gas -- No Nuclear Involvement
- PSCo Will Own 61.9 % of Common Equity of New Holding Company: SPS Will Own 38.1 %
- NRC Concurrence Will Be Requested in Accordance With Information Notice 89-25 l
l l
l Page 17
l REPOWERING STATUS l
l PROJECT CONSTRUCTION IS PROCEEDING ON SCHEDULE
- Combustion Turbine and Generator Arrived On-site By ,
Rail On September 6,1995
- Installation 45% Complete
- Natural Gas Pipe Installation in Progress
> NRC Approval Received July 31,1995
- First Ignition Startup Test Scheduled for February 2, 1996 a
r e>
4,~'
Page 18
l PRESENT DECOMMISSIONING CONCERNS
- Completion of Final Survey for Site Release
- Approval of Embedded Piping Treatment
- Confirmation That Established FSV Site Release Criteria Will Not Be Subject to Change
- Final License Termination Process l
CONCLUSION
- FORT ST. VRAIN DECOMMISSIONING IS PROGRESSING WELL
- RADIOLOGICAL AND INDUSTRIAL SAFETY PERFORMANCE IS EXCELLENT
- THE PROJECT WILL BE COMPLETED AHEAD OF PROGRAM SCHEDULE AND UNDER BUDGET 1
!
- PSCo APPRECIATES NRC'S PROFESSIONALISM AND l DEDICATION DURING FSV DECOMMISSIONING PROJECT I
l Page 21
1 SUPPLEMENTAL INFORMATION
- STAFFING CHART e
l Page 22
FORT ST. VRAIN 1
l DECOMMISSIONING STAFF LEVELS l Legend W WESTINGHOUSE TEAM CONTRACT EMPLOYEES PSC EMPLOYEES soo 700 k k i
~ ~
g _. . i 3004 :.
CD tttt, w 4%.: .. :..
W ??-MI4 c
>- :TM$g+g O 4m -ti::T-7T- h"--i 'l .
3
.,,,,J 9 O- NN "
ti <$': ..w 2 : Jif 4.,j CONELACT EMPLOYEES W zoo _ :pp _ .grity -
e j g(ggt g i
- MF5 NMs iI![ ++r.r
+
- ml,
- k ,
&,-A. ,<+M,:::i:z::: :m p 7 __ ._. _. n, , .
g; ; ; ; ,
,y, ; ,, . M,,a i::
% 4: : :: :::,:0, 1 ,. :o m ,:::
',::52::
": :i:: :::i:- :: 2::
- i 200-- .
i:: :: :: MMMB:%:'i% :M2:: : :i:: :::i:: :: i:: ::%k 7 'i u _.. _ m.__,_. _
i k M:::i% %:i : :':i ::i%%:'::i:' ; :-:!O% : :50 .::2:: , :: ':::
' v-r , ]+ -
={ - T*"::: 2:::i:: .
[
M PSCEMPLOYEES i : [ hjjj,.j [
WESTINGilOUSETEAM r'4T+ 5 -- /
e 2:::i:::i:: .::m,,,,..,.. y _ _, _ ,-,, . .,,. .
o :. m I E? U'i M' ,'
M 100 - +
5 ? '
'-' i IS E_l'.kM k iMEE:2 r% E i :
+ ~
Yi"-M """"
-Y.D# M@ SiFJd Nhjhkgh.fh -h[: 23 ((_N$f $'$$ 55 : s
_m
'I...
7.
,gd '
- 1. --o. l b i' s 4
.s,
_ .p.. .
3 .-
. .s .
l l .I
. hl L i
f l- ;j Z!~ -
Ti ( h f h
,, e ,A. e e ,- e e e ,e ., ., e ,e e A - . A e e . e ,e e