JOSEPH M. FARLEY NUCLEAR PLANT UNIT 1 NARRATIVE
SUMMARY
OF OPERATIONS OCTOBER There were no unit shutdowns or significant power reductions during the month of October.
The following major safety-related maintenance was performed in the month of October:
- 1. Performed miscellaneous corrective and preventive maintenance on diesel generators.
- 2. Completed re-racking of Unit I spent fuel pool. High density storage racks have been installed to increase the capacity to 1407 fuel assemblies.
l 0 ck y
k
~
, DOCKET NO. 50-348 UNIT 1
^
November 6, 1984 DATE COMPLETED BY J. D. Woodard TELEPHONE (205) 899-5156 M0ffill October. 1984 DAY AVERAGE DA!LY POWER LEVEL ' DAY
- VERACE DAILY POWER LEVEL (MWe Net) (MWe Net) 826 806 g, g7 2 829 gg 708
~3 829 19 nna 828 811 4 20 5 826 21 R09 821 g 809 6
819 23 810 7
8 818 24 811 9 770 ;$- 812 818 814 10 26 819 11 27 814 0 807 12 3 i
13 820 ;9 gio 14 819 30 811 687 811
- $ 33 16 810 l
l 2 G UCDONS On this form: . list the aversge daily unit puwer levelin MWe-Net for e:ch d:y in the reporting month. Compute to
, the neste:t whole rnepwast.
(997) 1 l
l l
. I I
l OPERATING DATA REPORT DOCKET NO. sn_1ag DATE 11 A RA l COMPLETED BY J. D. Woodard TELEPHONE (?nsi R99-5156 OPERATING STATUS Joseph M. Farley - Unit 1 Notes -
- 1. Unit Nm. '
- 2. Reporting Period: noenhar 1996 . (1) Cumulative data since 2652 12-1-77, date of
- 3. Licensed Thermal Power (MWt):
- 4. Nameplate Rating (Gross MWe): 860 commercial operation.
- 5. Design Electrical Rating (Net MWe):
829
- 6. Maximum Dependable Capacity (Gross MWe): Rat R
- 7. Maximum Dependable Capacity (Net MWe): 797 1
- 8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report. Give Reasons:
N/A
- 9. Power Level To which Restricted.If Any (Net MWe): N/A
- 10. Reasons For Restrictions. If Any: N/A i - . ..
This Month Yr..to-Date Cumulative
- 11. Hours In Reporting Period 745 7.320 60,648
- 12. Number Of Hours Reactor Was Critical 745.0 5,541.8 40,665.0 0.0 nn 3,650.0
- 13. Reactor Reserve Shutdown Hours
- 14. Hours Generator On-Line 745.0 5.457.0 lo.560.4
- 15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
- 16. Gross Thermal Energy Generated (MWH) 1,949,788 14,001,907 100,103.433 632,706 4,514,896 31,857.906
- 17. Gross Electrical Energy Generated (MWH)
- 18. Net Electrical Energy Generated (MWH) 399'734 4.255.466 - 29,956,528.
100.0 74.5 65.2
- 19. Unit Service Factor
- 20. Unit Availability Factor 100.0 74.5 65.2
- 21. Unit Capacity Factor (Using MDC Net) 101.0 72,9 62.0
- 22. Unit Capacity Factor (Using DER Net) 97*I 70.1 59.6
- 23. Unit Forced Outage Rate 0.0 1.4 13.6
- 24. Shutdowns Scheduled Over Next 6 Months (Type, Date and Duration,.of Each):
- 25. If Shut Down At End Of Report Period. Estimated Date of Startup:
- 26. Units In Test Status t Prior to Commercial Operation): Forecast Achieved a
INITIAL CRITICALITY 08-06-77 08-09-77 j
l INITIAL ELECTRICITY nn-?n_77 08-18-77
. COMMERCIAL OPERATION 12-01-77 12-01-77 i
(4[77 ) )
I i
s' .
L )s J .-
UNITSilU1 DOWNS AND POWER REIM)CilONS DOCKET NO. 5d-348- '.[
UNIT NAME .J,M. Farley - Unit.1 DATE 6-84 .
CU#*-*- * "' ' " D-'W" U #d
' REPORT MON 111 October. 1984 TELErilONE _"G.Q5) 899-5156 ,
"r
! c re 5 s4 'E E i
-. .E E g 5g Licenser Ev. g4 Cause & Cussective N.e . Date g Eg g 7,gx Event u 'l r] Acti.us to
- h3 5 ,C 2 i8 h R*E'"' # -
o p,gy,,,g,c,,,,,,,
6 THERE WERE N0 la IT SI UTDOW ;S OR SIGNIFICANT PO.IE 1 REDUCTIC NS DURING THE MONTH OF OCTOBER, 4
t l
l t i 3 3 4 F: Forced Reason: Method: Exhibit G -lasitucesons S: Stheduled A Equipmens Failure (Explain) -
I Manual for Prepasasiam of Data
- u Maintenance e,iTest 2 Manual Scram. Enisy Sheets for Licensee -
C Refueling 3 Autuniatic Scram. Event Rep w (i.ER) File INURI G-4 D.Regulasiuy Resisiction 4 0 hcr (Emplaise) 0161)
E4)pesaius Tsaining A license Exandnasion F-Adminisisasive 5 G Opcaatiimal Essur (limplain) Exhibit I - Same Sousee 19/77) II Othe: (Emplain)
- & m
f; . Malling Address f * .
- Alabama Power Cornpany
' 600 North 18th Strsot Post Office Box 2641 Btrmingham, Alabma 35291 f- Telephone 205 783-6090 t
ff( R. P. Mcdonald
[- Senior Vice President
[ Flintridge Building AlabaritaPower ce s zwwe~ sa:. .
November 9, 1984-Docket No. 50-348 Director, Office of Resource Management U. S. Nuclear Regulatory Commission -
Washington, D.C. 20555
Dear Sir:
RE: Joseph M. Farley Nuclear Plant Unit 1 Monthly Operating Data Report Attached are two (2) copies of the October 1984 Monthly Operating Report for Joseph M. Farley Nuclear Plant, Unit 1, reouired by Section 6.9.1.10 of Appendix A of the Technical Specifications. As requested by letter from Mr. John F. Stolz to Mr. Alan R. Barton, dated October 21, 1977, a " Narrative Summary of Operating Experience" is included in the attached report.
If you have any questions, please advise. -
Yours very trul , ,
N &.
f R. P. Mcdonald f/
RPM /KWM: sam Enclosures xc: Director, IE (10 copies)